Wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

Contract Changes Quiz

Total questions: 74

Worksheet time: 42mins

Name
Class
Date
1.

What is considered a significant potential risk when making changes to a construction contract?

a)

The impact on the contractor's schedule

b)

The impact on time and cost

c)

The quality of construction materials

d)

The weather conditions during construction

2.

Which of the following is NOT listed as a source of changes to the contract?

a)

Changes in the materials to be used

b)

Corrections to errors or omissions in the plans or specifications

c)

Changes in government regulations

d)

Acceleration or delays to the work

3.

What is the AIA approach to changes in a contract designed to protect?

a)

The interests of the owner, contractor, and subcontractor

b)

The financial stability of the contractor only

c)

The timeline of the project completion

d)

The legal responsibilities of the subcontractor

4.

According to the text, what can a contractor not do without providing something additional in return?

a)

Issue a work change proposal request

b)

Charge more money

c)

Agree to a contract change

d)

Evaluate the impacts of a work change

5.

What does a change order have to meet the same requirements as?

a)

A work change proposal request

b)

A deductive change order

c)

Contract formation requirements such as offer, acceptance, and consideration

d)

The preexisting duty rule

6.

What is the first step in the general process for agreed changes according to the flowchart?

a)

Contractor determines price and time impacts of change and gives owner a charge order request

b)

Owner issues formal change order to the construction contract

c)

Owner defines the change and issues a work change proposal request to contractor

d)

Contractor completes the change work

7.

Which of the following is NOT a reason why parties might not agree to a contract change?

a)

The issue actually constitutes a contract change.

b)

The price is inaccurate or unfair.

c)

Whether overhead and profit are fair to include in the change order.

d)

The contractor completes the work in less time than estimated.

8.

What happens after the contractor determines the price and time impacts of a change?

a)

The contractor starts working without approval.

b)

The owner issues a formal change order to the construction contract.

c)

The owner defines the change and issues a work change proposal request to contractor.

d)

The contractor gives the owner a charge order request.

9.

What is the final step in the general process for agreed changes as shown in the flowchart?

a)

Contractor determines price and time impacts of change and gives owner a charge order request

b)

Owner defines the change and issues a work change proposal request to contractor

c)

Owner issues formal change order to the construction contract

d)

Contractor completes the change work

10.

What does CCD stand for in the context of construction contracts?

a)

Construction Change Directive

b)

Construction Contract Document

c)

Construction Control Diagram

d)

Construction Coordination Duty

11.

Who has the right to unilaterally issue a construction change directive?

a)

The contractor

b)

The owner or his agent

c)

The project manager

d)

The subcontractor

12.

What is the risk for the contractor when continuing work with a construction change directive without an agreement?

a)

No risk, as the directive guarantees payment

b)

Risk of not receiving additional compensation

c)

Risk of project cancellation

d)

Risk of legal action from the owner

13.

What is a cardinal change in the context of construction changes?

a)

A minor modification to the contract

b)

A change within the scope of the original contract

c)

A change that exceeds what is considered a "change" to the existing contract

d)

A change that reduces the project cost

14.

What is the general process for implementing owner directed contract changes according to FIGURE 12-2?

a)

Owner issues construction change directive, contractor completes disputed work, contractor processes claim for reimbursement of additional work

b)

Contractor requests change, owner approves, contractor completes work

c)

Owner issues construction change directive, contractor rejects directive, owner seeks legal action

d)

Contractor completes disputed work, owner issues construction change directive, contractor processes claim

15.

What is a cardinal change in the context of a contract?

a)

A) A minor adjustment to the original contract that is easily accommodated.

b)

B) A change so far beyond what the parties contemplated that it constitutes a new agreement.

c)

C) A change that is within the original scope of work and contemplated by the contract.

d)

D) A change that is required due to errors or omissions in the original contract plans.

16.

Which of the following is NOT one of the four primary factors that might indicate a change rises to the level of a cardinal change?

a)

A) The impact of the change(s) on the original plans/specifications.

b)

B) How much the change increased the complexity/difficulty of the work.

c)

C) Disruption to coordination or methods of construction.

d)

D) The change resulting in a decreased overall cost of the project.

17.

What is the consequence of a change being determined as cardinal for public contracts?

a)

A) The contract is slightly modified but remains in effect.

b)

B) The contractor is given a bonus for accommodating the change.

c)

C) The contractor is excused from performance and the contract is considered void.

d)

D) The contract is extended to allow for additional time to complete the project.

18.

How has the nature of change required for a finding of cardinal change been described?

a)

A) Insignificant

b)

B) Moderate

c)

C) Drastic

d)

D) Beneficial

19.

What was the case mentioned as an example of cardinal change?

a)

A) General Contracting v. O'Connor

b)

B) Bruner & O'Connor on Construction Law

c)

C) General Contracting & Construction v. United States

d)

D) O'Connor v. General Construction

20.

What is a constructive change in the context of contract changes?

a)

A change that is directed by the owner and memorialized in a change order.

b)

A change that imposes an obligation on the contractor to do work outside the scope of the contract, without a formal change order or directive.

c)

A change that is recognized by the owner as necessary and is included in the contract documents.

d)

A change that results in reduced costs for the contractor and is agreed upon by all parties.

21.

What can a contractor do if they encounter a constructive change?

a)

The contractor can ignore the change since it is not formally recognized.

b)

The contractor can immediately stop work on the project.

c)

The contractor must look to the claim provision of the contract to assert the right to additional time or payment.

d)

The contractor can renegotiate the entire contract with the owner.

22.

Which of the following scenarios could be considered a constructive change?

a)

The owner provides a change order for additional work that is within the scope of the contract.

b)

The contractor decides to change the materials used without consulting the owner.

c)

The owner rejects work that is in accordance with the contract documents, requiring additional work from the contractor.

d)

The contractor voluntarily decides to upgrade a component of the project at no extra cost.

23.

What is the first step in the general process for constructive changes according to the flowchart?

a)

Owner reviews whether change is legitimate and priced fairly

b)

Contractor completes work and processes claim for constructive change

c)

Contractor determines price and time impacts of change and gives owner a charge order request

d)

Owner signs change order to the construction contract and work progresses

24.

What happens if the owner does not approve the change order request?

a)

The contractor stops working immediately

b)

The owner signs change order to the construction contract and work progresses

c)

The contractor completes work and processes claim for constructive change

d)

The contractor determines a new price and resubmits the charge order request

25.

According to the text, what is risky about relying on doctrines such as waiver of the procedural requirements and oral modification of the contract?

a)

They are not legally binding

b)

They rely on the court's interpretation of the facts in a particular case

c)

They are universally accepted legal practices

d)

They guarantee payment for the contractor

26.

Why should construction contracts contain a provision for addressing conditions discovered on the site that were not anticipated by the parties?

a)

To ensure that the project is completed on time

b)

To guarantee a fixed price for the project

c)

To address conditions discovered on the site that were not anticipated by the parties

d)

To comply with government regulations

27.

What is a common differing site condition that is found in the AIA 201-2017 3.7.4 (the General Conditions) and other standard contracts?

a)

Type I differing site conditions

b)

Type II differing site conditions

c)

Type III differing site conditions

d)

Type IV differing site conditions

28.

To assert a claim of Type I differing site conditions, the contractor must demonstrate that the condition:

a)

was exactly as represented in the contract documents

b)

was foreseen based on a reasonable investigation of the site

c)

differed materially from what was represented in the contract documents

d)

did not cause any delay or additional costs

29.

Which of the following is NOT a requirement for a contractor to assert a claim of Type I differing site conditions?

a)

The condition was not foreseeable based on a reasonable investigation of the site or interpretation of the contract documents

b)

The contractor gave sufficient notice as required by the contract

c)

The contractor suffered delay and/or incurred additional costs as a result of the condition

d)

The condition was usual and could have been reasonably anticipated

30.

For a Type II differing site condition, the contractor must show that the condition:

a)

was usual and would have been reasonably anticipated based on the contract documents

b)

was unusual and would not have been reasonably anticipated based on the contract documents

c)

did not differ from what was represented in the contract documents

d)

was not material to the work being performed

31.

What is the consequence for a contractor if they fail to provide notice within the prescribed time frame according to the AIA documents?

a)

The contractor is entitled to additional compensation.

b)

The contractor is granted an extension of time for the condition.

c)

The contractor is barred from recovery.

d)

The contractor's obligation to perform tests is waived.

32.

What can be a defense for a subcontractor if a site inspection would have revealed a condition that they did not perform such an inspection?

a)

The subcontractor is entitled to increased pay.

b)

The subcontractor can claim extended time for the condition.

c)

The subcontractor's lack of inspection can be a defense to a claim for increased pay or extended time.

d)

The subcontractor is automatically granted additional compensation.

33.

In the case of COMMONWEALTH v. AMEC CIVIL, INC., what was the primary cause of delay in the construction project?

a)

Inaccurate representations in the contract documents.

b)

Ambiguities interpreted against the owner.

c)

Difficulties in the construction of concrete-filled drilled shafts.

d)

The subcontractor's failure to perform a site inspection.

34.

What was the key feature of the contract for the construction of Bridge 616?

a)

The construction of a dam

b)

The construction of Bridge 616 across Kerr Lake

c)

The renovation of an existing bridge

d)

The installation of traffic signals

35.

What was AMEC's claim against VDOT in May 2006 related to?

a)

Incorrect payment calculations

b)

Differing site conditions and additional compensation

c)

Delays in construction timelines

d)

Environmental impact concerns

36.

How much did the trial court award AMEC in the lawsuit against VDOT?

a)

Approximately 21 million dollars

b)

Approximately 30 million dollars

c)

Approximately 15 million dollars

d)

Approximately 25 million dollars

37.

What does the U.S. Army Corps of Engineers regulate in relation to Kerr Lake's water level?

a)

The fishing regulations

b)

The water quality standards

c)

The water level to prevent flooding downstream

d)

The recreational activities on the lake

38.

What was the critical issue with the construction of Bridge 616 related to Kerr Lake's water level?

a)

The water level was too low for construction

b)

The water level was critical to the construction and AMEC could not access the lake to complete the bridge columns when the water level was too high

c)

The water level had no impact on the construction

d)

The water level was artificially lowered for construction purposes

39.

Who was AMEC's estimate and engineering manager that testified about the fluctuating lake levels at trial?

a)

Dale V. Goodman

b)

Charlie H. Guerrant

c)

Peter Buchardt

d)

Grant Ralston

40.

What did Charlie H. Guerrant testify about the water levels at Kerr Lake in 2003?

a)

They were lower than usual

b)

They fluctuated normally

c)

They were higher than those encountered in 2003 for a long period

d)

They did not affect the construction

41.

What did Dale V. Goodman state about the high water at Kerr Lake?

a)

It was a common occurrence

b)

It was an unusual circumstance

c)

It had no impact on the project

d)

It was accurately predicted

42.

What action did AMEC's project manager take in March 2003 regarding the high water levels?

a)

He ignored the situation

b)

He wrote a letter to VDOT informing them of the situation

c)

He requested immediate project cancellation

d)

He adjusted the project timeline without informing anyone

43.

What was the result of the sustained elevated lake water levels a year later?

a)

AMEC's contract was terminated

b)

The project was completed ahead of schedule

c)

VDOT issued two work orders extending the project completion date

d)

The high water levels were deemed normal

44.

According to the August 2004 letter, what was the reason given by VDOT for the time extension from March 1, 2003, through July 27, 2003?

a)

Differing site conditions encountered during the work

b)

Unusual period of high-water levels

c)

Routine fluctuations in water level

d)

AMEC's request for additional compensation

45.

Under Specification § 104.03, what are the two types of conditions that may warrant additional compensation?

a)

Subsurface or latent physical conditions and unknown physical conditions of an unusual nature

b)

High-water levels and routine water fluctuations

c)

Known conditional risks and non-routine water level fluctuations

d)

Type I condition and Type II condition

46.

What did the Court of Appeals conclude about the "high-water" differing site condition claim by AMEC?

a)

It was valid because the water levels were unforeseeable and unusual

b)

It was defeated because no Type I condition existed

c)

It was accepted because AMEC provided sufficient historical data

d)

It was upheld because the contract had a baseline for water levels

47.

What did AMEC argue in their appeal to this Court regarding the elevated lake water levels?

a)

They were routine and should have been expected

b)

They constituted a differing site condition

c)

They were within the historical range recorded by the U.S. Army Corps

d)

They were accurately factored into AMEC's risk assessment

48.

How did the Court of Appeals apply an improper standard of review according to AMEC?

a)

By reviewing the circuit court's findings de novo

b)

By not considering the historical records of water levels

c)

By establishing a baseline for water level fluctuations

d)

By ignoring the contractual terms for additional compensation

49.

What did the Court of Appeals correctly hold regarding the elevated water levels in the VDOT case?

a)

The elevated water levels were a Type I differing site condition.

b)

The elevated water levels were not a Type I differing site condition.

c)

The elevated water levels were a result of binding representations.

d)

The elevated water levels were a known, unpredictable condition.

50.

According to the case Asphalt Roads & Materials Company, Inc. v. Commonwealth, what is the purpose of the differing site conditions clause?

a)

To ensure that the contractor takes on all the risk of subsurface conditions.

b)

To provide a clear definition of what constitutes a Type I and Type II differing site condition.

c)

To shift the risk of adverse subsurface or latent physical conditions from the contractor to the government.

d)

To encourage low, competitive bids by sharing the risk of differing site conditions.

51.

What did the North Carolina State Highway Commission v. Ray D. Lowder, Inc. case emphasize about the differing site conditions clause?

a)

It is intended to cover all types of environmental conditions.

b)

It is meant to encourage low bids by assuming all risks.

c)

It is to encourage fair competition by stating that the purpose is to take some of the gamble out of bidding.

d)

It is to ensure that the government always bears the risk of differing site conditions.

52.

What is the purpose of the clause mentioned in Foster Constr. C.A. & Williams Bros. Co. v. United States?

a)

To guarantee profits for contractors regardless of subsurface conditions.

b)

To take some of the gamble out of bidding on subsurface conditions.

c)

To make contractors responsible for accurate bidding without considering the risk of differing site conditions.

d)

To ensure that the government is solely responsible for any subsurface conditions encountered.

53.

What does the analysis of a Type II differing site condition require?

a)

Contract interpretation and a factual determination.

b)

A legal determination and a review de novo on appeal.

c)

A comparison with similar contracts in the area.

d)

Proof that the conditions were unforeseeable at the time of bidding.

54.

In the case discussed, what did the court conclude about the sustained elevated water levels?

a)

They constituted a Type I differing site condition.

b)

They did not constitute a Type I differing site condition because they were not a subsurface or latent physical condition.

c)

They were a Type II differing site condition under Specification § 104.03.

d)

They were a known physical condition at the time the contract was executed.

55.

What was the unusual circumstance mentioned in the case discussed?

a)

A) A natural disaster

b)

B) Sustained elevated water levels

c)

C) A common construction delay

d)

D) An error in the contract

56.

According to the text, who manages the water level of Kerr Lake?

a)

A) The Virginia Court of Appeals

b)

B) AMEC as a contractor

c)

C) The U.S. Army Corps

d)

D) VDOT

57.

What did the court conclude regarding the elevated lake levels?

a)

A) They were a natural event and an act of God.

b)

B) They were the result of the U.S. Army Corps' exercise of control over the dam.

c)

C) They were a risk that should have been included in the contract without inflation.

d)

D) They were a common occurrence that could be reasonably anticipated.

58.

What was the court's decision regarding the differing site condition claim related to the elevated lake levels?

a)

A) The court upheld the Virginia Court of Appeals' decision.

b)

B) The court found VDOT responsible for the costs.

c)

C) The court reversed the Virginia Court of Appeals' decision.

d)

D) The court decided it was a natural disaster.

59.

What does the Supreme Court of Virginia say is the purpose of including a differing site conditions provision in a construction contract?

a)

To provide a clear framework for managing unexpected site conditions

b)

To allocate risk for differing site conditions between the contractor and owner

c)

To ensure timely completion of construction projects

d)

To reduce the overall cost of construction

60.

What is the test to determine if a contractor has a valid Type I differing site conditions claim?

a)

The contractor must prove that the conditions were unforeseeable

b)

The contractor must demonstrate that the conditions were as expected

c)

The contractor must show that the conditions were identical to other sites

d)

The contractor must verify that the conditions were made known to the owner beforehand

61.

Did AMEC establish a Type I differing site conditions claim? Why or why not?

4 lines
62.

What is the test to determine if a contractor has a valid Type II differing site conditions claim?

a)

The contractor must prove that the conditions were unforeseeable and differ materially from those indicated in the contract

b)

The contractor must demonstrate that the conditions were as expected and indicated in the contract

c)

The contractor must show that the conditions were identical to other sites and indicated in the contract

d)

The contractor must verify that the conditions were made known to the owner beforehand and differ materially from those indicated in the contract

63.

Did AMEC establish a Type II differing site conditions claim?

4 lines
64.

Give at least 3 examples of potential sources of changes to a construction contract.

a)

Weather conditions, client requests, and material shortages

b)

Extended field and home office overhead, labor and materials cost escalation, seasonal shifts

c)

Design errors, legal disputes, and equipment failure

d)

Budget cuts, change in project scope, and regulatory changes

65.

Explain the difference between “changed” work and “extra” work.

a)

"Changed" work is work that has been modified from the original plan, while "extra" work is additional work that was not included in the original scope.

b)

"Changed" work is work that is done by subcontractors, while "extra" work is done by the original contractors.

c)

"Changed" work is work that is less expensive than originally planned, while "extra" work is more costly.

d)

"Changed" work is work that is completed ahead of schedule, while "extra" work is work that is delayed.

66.

Give an example of how the “preexisting duty rule” relates to construction contract changes.

a)

It refers to the obligation of the contractor to complete the work as per the original contract without additional payment.

b)

It is the responsibility of the client to provide all necessary permits and licenses before construction begins.

c)

It involves the contractor's duty to ensure all materials meet pre-agreed standards.

d)

It pertains to the architect's duty to inspect the work regularly.

67.

What are the steps taken by the project team to process a contract change when all parties are in agreement?

a)

Review the contract, negotiate terms, and sign a change order

b)

Submit a complaint, wait for a resolution, and then proceed with the change

c)

Ignore the change, continue with the original plan, and resolve discrepancies later

d)

Adjust the project timeline, inform all stakeholders, and document the changes

68.

Give three common reasons that disagreements arise with changes when the parties cannot agree.

a)

Different interpretations of the contract, unexpected site conditions, and personal conflicts

b)

Scheduling conflicts, weather delays, and equipment malfunctions

c)

Miscommunication, lack of resources, and changes in project leadership

d)

Budget overruns, quality control issues, and stakeholder disapproval

69.

A __________ is a change that is neither memorialized in a change order nor unilaterally directed by the owner.

a)

cardinal change

b)

constructive change

c)

direct change

d)

unilateral change

70.

Which of the following situations would likely be considered a cardinal change?

a)

A minor adjustment to the project scope

b)

A change resulting from a clerical error

c)

A significant alteration that fundamentally changes the nature of the contract

d)

A change in project leadership

71.

Constructive changes on a project typically occur when:

a)

The project is completed ahead of schedule

b)

There is a change in the market price of materials

c)

There are informal or unofficial orders that result in additional work

d)

The project scope is reduced

72.

Which of the following is NOT a method used to determine cost and time associated with change work?

a)

Time and motion studies

b)

Market analysis

c)

Expert judgment

d)

Detailed cost estimating

73.

Which of the following is NOT an example of direct costs associated with change work?

a)

Labor

b)

Equipment

c)

Overhead

d)

Materials

74.

Which of the following is NOT an example of potential impact costs that result from a contract change?

a)

Loss of productivity

b)

Accelerated schedules

c)

All are potential impact costs

d)

Extended overhead