A recently appointed project manager takes charge of a project initiated last year focused on renovating a bustling airport terminal.
Even though the project uses a hybrid development approach—making incremental updates to the terminal—it has encountered many issues, especially creating conflicts with airport operations. The recently appointed project manager inquires with the project team about their usual approach to managing problems and risks, but none of the team members provide a definite response.
What should the project manager do first?
Modify the risk register
Switch to a predictive approach for better risk management
Start to identify potential risks
Update the risk management plan
Luna is working on a construction project that spans over 12 months. She reviews the schedule and notice that there are times when certain team members on her project team are severely over allocated, which means she might need to bring on extra resources to help handle the extra load.
However, at other times during her project the team is under-allocated, which means she may have to lay off some team members.
Which of the following should she does to rearrange her resources so that a priority given to constant number of resources are used in the project?
Crashing
Resource Smoothing
Fast Tracking
Resource Leveling
April is a project manager at her organization. She is currently assigned to work on a project to migrate a large number of servers from an on-site data center at her organization to an off-site data center that is monitored 24/7 by a third party vendor. The company believes this offloading will increase efficiency and reduce work requirements in areas where the company is not specialized.
April is putting together the project requirements, constraints, and assumptions. Which document is April likely working on?
April is gathering the project requirements so she is probably working on the Project Management Plan
The Project Scope Statement is the document that contains the project requirements, the constraints on the project, and the assumptions used
April is drafting the Project Charter so that she can start work on her project
April is most likely drafting the Communications Management Plan since the project constraints usually deal with the project communications and when everyone is unavailable for meetings
Niclole is the project manager of the Raffles MIS Project. This project is to create a new software package for a client. She is working with the client, business analysts, software developers, business developers, and the sales team to create the vision and requirements of the newly initiated project.
Of the following, which one determines the scope of the project?
The customer and the stakeholders
The project sponsor
The performing organizations management
The project manager
Which of the following is a method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model?
This schedule network analysis technique calculates the early start, early finish, late start, and late finish dates for all activities without regard to any resource limitations by performing a forward and backward pass analysis through the schedule network.
Schedule Compression
Critical Chain Method
Critical Path Method
PERT
Angie is a project manager for her organization. Her current project assignment is with a team that is working to construct a component that will be used in a shuttle that will be launched by a commercial space travel organization.
The client corporation has stringent quality requirements that must be adhered to, otherwise the component could endanger the lives of the passengers on the shuttle.
Angie should be concerned with the quality attributes of the product her team is building.
Which statement best describes quality attributes in this context?
The quality attributes of the component Angie’s team is build are the acceptance criteria that are to be met mandatorily
The quality attributes of that Angie is concerned about provide a basis for judging a project's success or failure
The quality attributes that Angie is referencing in this situation provide a basis for determining how effectively Angie’s organization supports the project
The quality attributes are the specific characteristics for which Angie’s team`s product is designed and tested
Elements of the project that are well known or have fixed requirements follow a predictive development life cycle, and those elements that are still evolving follow an adaptive development life cycle. Which of the following project life cycle types does this statement refer to?
Iterative Life Cycle
Adaptive Life Cycle
Predictive Life Cycle
Hybrid Life Cycle
A municipal waste management project that merges several administrative tasks with minor public works is referred to as a hybrid project. An agile track makes good progress on key objectives, but small tasks are accumulating in the backlog. These tasks are typically short and can be completed within a day, but they are dependent on different unpredictable triggering events.
Which approach would be most effective to clear out these minor tasks faster?
To align the story sizes with the primary objectives, group various small tasks together.
Prioritize the backlog by favoring the smallest stories, and assign them daily.
Reorder the backlog regularly, so that recently triggered events increase the priority of the stories.
Incorporate the small tasks into either the Definition of Done or the acceptance criteria for those dependent stories.
For a project to streamline processes, a product team has finished eight of the ten scheduled iterations. The product owner discovers a significant, company-wide budget adjustment while adjusting the backlog for iteration nine and writes the following email:
Dear Project Team for Streamlining,
Our project will be impacted by yesterday's budget modification. I might have to reprioritize some of our scheduled tasks.
How ought the team captain to react?
Respond with any suggestions for limiting the scope while still doing two more iterations
Watch and wait for the product owner to revise the backlog's priorities and provide any suggestions as required
To learn more about the budget reduction, get in touch with the sponsor on the approach ahead
The team should be disbanded to give everyone time to locate new role in different project with budget
David is a project manager for Cambridge university. Currently, he is developing schedule for a project. As he was performing the critical path method on the project, he encountered three different types of float.
Map the correct float statement in the following:
Total Float: Amount of type an activity can be delayed without delaying the project end date
Free Float: Amount of type an activity can be delayed without delaying the early start date of its successor
Project Float: Amount of type an activity can be delayed without delaying the externally imposed project completion date required by the customer or management
All floats are right
Crissy is a project manager at her organization. She has recently noticed that her interactions with one of the engineers on her project have been very tense. Crissy knows she needs buy-in from this engineer for her project to successfully meet the objectives.
Crissy will begin reviewing the types of communication she has with this engineer to try to find ways to improve her communications.
Which one of the following is not a type of communication?
Crissy will review her formal written communications prior to sending them off to the engineer to ensure that her written word is not sending any unintended tone or messages
Crissy will try to be more mindful of her paralingual communications since this can have a major impact on how verbal messages are understood
Crissy will seek out a peer to give her feedback on her nonverbal communications just in case she is acting in a way that might be off-putting without realizing it
Crissy will evaluate her communications for any unintended noise that might be preventing her messages from being received with the meaning with which they were sent
Jessica is a project manager on a large construction project. Late in the project, her client demands a big change. She assesses the impact of the change and tells the client how much time and money it will cost.
But the client won't allow any change to the schedule and won't pay anything more for change. Jessica explains that the proposed change is well outside the documented scope of the original work.
The client tells Jessica that he doesn't care what was in the original scope and that she needs to implement the change with no impact to schedule or budget.
What conflict resolution technique is the client using?
Confronting
Withdrawal
Smoothing
Forcing
Momen is a project manager for his company. He has recently been assigned to a new project in a different country. He will be using a Project Stakeholder Management plan template provided by his PMO, but his head of PMO has suggested that he tailor the way he applies the Project Stakeholder Management Process in light of differences between this project and the previous project.
Momen should consider all of the following when tailoring his plan, except for
Momen should identify how many stakeholders are there that will be involved in his project, and how diverse the culture is within the stakeholder community
Momen should consider how complex the relationships are within the stakeholder community. The more networks a stakeholder or stakeholder group participates in, the more complex the networks of information and misinformation the stakeholder may receive
Momen should consider what communication technology is available, and also what support mechanisms are in place to ensure that best value is achieved from the technology
Momen will want to look into whether the buyers and sellers are in the same or reasonably close location, including if in different time zones, countries, or continents
You are managing a large construction project, and a sudden change in government regulations requires a significant alteration in the project design. This change will have a substantial impact on the project timeline and budget.
What should you do to demonstrate resiliency in managing this situation
Immediately communicate the change to all project stakeholders and seek their input on the revised project plan
Conduct a thorough analysis of the impact of the change on the project timeline, budget, and resources
Engage with subject matter experts and consultants to explore alternative solutions and assess and minimize the impact of the change
Revise the project plan and implement the necessary adjustments to accommodate the new design requirements
As a Project Management Professional there are a lot of issues to be handled during a project.
Which of the following statements about Control Quality is accurate?
A. Prevention refers to keeping errors out of the process, whereas inspection refers to keeping errors out of the hands of the customer.
B. Attribute sampling determines whether the result conforms or not, and variables sampling determines the degree of conformity.
C. Tolerances refer to a specified range of accepted results and control limits refer to thresholds, which can indicate whether the process is out of control.
D. Control Quality is only performed during the Monitoring and Controlling phase of a project.
A,B,C
A,C,D
A,B,D
B,C,D
While carrying out a project, a key team member expresses concerns about the approach outlined in the project management plan. The member surprises the project manager with negative feedback during a weekly status update meeting.
What steps should the project manager take to deal with the team member's concerns?
Proceed with the meeting and make sure that the concerns are documented in the risk register once the meeting is concluded
After reminding the team member of the expected meeting etiquette, continue with the planned agenda items. Afterwards, seek feedback regarding the expected meeting conduct
Bear in mind that it is unwise for a project to proceed if key team members are in disagreement. Utilize the meeting as an opportunity to address the concerns of that member
Briefly acknowledge the team member's concerns, proceed with the meeting, and arrange a private meeting with the member to further discuss their concerns to manage the risk
Upon recognizing that stakeholder interests will be contradictory in a project, the project manager elects to employ a stakeholder engagement assessment matrix.
This matrix identifies a powerful stakeholder who is unenthusiastic about the project. The project manager must bring this stakeholder's expectations in line with the project's objectives.
How can the project manager accomplish this goal?
Develop a stakeholder engagement plan for engaging with stakeholders
Convey the stakeholder engagement plan
Meet with all stakeholders to establish agreement on project goals
Make sure that the stakeholder register is complete and updated
In a hybrid virtual reality project that includes an agile software track and a predictive electronics track, delays are piling up halfway into the project due to inconsistent deliverable releases between the two tracks.
To address this issue, the project manager should consider combining which elements to create a shared network diagram?
Definition of Ready that includes dependency milestones
Epic breakdown that includes work breakdown structure
Product backlog that includes critical path task sequence
Definition of Done that includes exit criteria
Definition of Ready that includes work breakdown structure
The Trustees of a Race Track have appointed Ava as the Project Manager for a $400 million redevelopment project. They expect the project to be completed before the Race Date exactly 3 Years from Project Start Date.
Which of the following parameters will help in determining the probability of finishing on time?
PERT Technique
Critical path method
Variance Analysis
Standard deviation from PERT simulation
Paris is a project manager at her organization. She is currently assigned to a project that will install a new software for her company that gives all the companys users access to a centralized reporting system. As part of her role, Paris is responsible for ensuring the quality of this system as it is conceptualized, designed, and implemented. Paris will be doing a cost of quality calculation for this.
Which of the following is not included in her calculation?
Paris will track the time her team members spend on testing the project to find defects, and then repairing those defects through reprogramming
Paris will calculate how much time the quality managers spent writing the quality standards that were used to evaluate the project
Paris should include the Project manager’s time spent creating the project management plan since this clearly contributed to the quality of the project
Paris will include the cost of her team members’ time spent reviewing specifications, plans and other documents
Zain is a project manager at his organisation, where he is currently assigned to work on a project that requires several permits from regulatory agencies. Zain is adding the permit applications to his schedule, which is tricky because each one requires a certain amount of work to be done on the project before the application can be submitted.
Two applications, in particular,, have to be submitted in a specific order. The completion of the application to Bravo Permitting is dependent on the Initiating of the successor application to Alpha Approvals. What relationship is implied between these two activities?
The work required by the permit applications can best be expressed with a Finish-to-Start relationship
The permit applications will be best represented in the schedule as a Finish-to-Finish relationship
The two activities that cover these permit applications should have a Start-to-Start relationship
The two activities have an implied relationship that would be best expressed in the schedule as a Start-to-Finish relationship
Ava is a project scheduler at her organization, which is an engineering-based organization with a centralized project management office. She is the only person at her organization that has access to project schedules, and few if any of the engineers understand critical path method scheduling.
She frequently receives change requests for project schedules, and must try to translate those requests into actionable schedule activities. Ava often uses decomposition to complete these changes.
Which statement below makes the most sense in light of Ava's role at her organization?
Ava will wait for the task to expire so that it will naturally break down into smaller parts, which is known as organic decomposition
Ava will work with the engineers to take a requested deliverable and break it down into the smaller work packages so that it can be organized and planned
Ava will work with the PMO to categorize work packages into categories that make sense to engineers and project managers that have to work together
Working independently, Ava will begin dividing work packages into deliverables that can be planned for
Justin is a project manager for his organisation. Justin's boss, the head of PMO, likes to receive weekly updates on each project. Justin is getting ready to draft his update to his boss. He updated cost information today and calculated that his project has an EV of $15,000, PV of $12,000 and AC of $11,000.
Which of the following updates from Justin is most accurate?
Justin can report that his project is ahead of schedule and within its budget, which should make his boss happy
Justin will have to report that the project is within its budget, but has fallen behind schedule
Justin can report that the project is ahead of schedule, but for various reasons has over-run its budget
Justin is about to have a rough day. He will have to report to his boss that the project is behind schedule and over its budget
The product owner has been notified by the legal team that a different company possesses a patent for an innovative feature utilized in the product being developed by the agile team. The product is currently 75% finished.
What actions should the product owner take to choose the best course of action?
Collaborate with the legal department to locate markets where the patent has not been registered
Conduct a marginal economics analysis and determine the feasible solution with essential features that can be released
Stop the project promptly to avoid additional expenses
Proceed with the product's development by eliminating the patented element
During a meeting, a project manager learns that a business result needs to be delivered in four weeks, although the original plan was sixteen weeks. The project manager also hears that there is no available technical resource who might be able to join the team. The project manager knows the technical resource manager because they worked together on a previous project.
What is the first thing the project manager should do?
Notify the project sponsor about the lack of a technical resource
Immediately escalate the issue to decision makers in the organization
Check with the technical resource manager to see if there is an available technical resource
Since time is short, hire an outside party to meet the need for a technical resource
Robin is providing update of her company to the CEO. This is a high-visibility project that she has been assigned to as the project manager. The CEO is particularly interested in knowing the value of the work that has been completed to date so that he can give his board an update on the project progress.
Which of the following is the most relevant information for the CEO?
Robin should tell the CEO about the Planned Value of the project at this point in the project lifecycle
Robin will want to tell the CEO about the earned value on her project as the best way to answer his question
Robin should provide the CEO with current actual cost information since that is the value of the project to date
Robin will need to give the CEO the budgeted cost for work scheduled, or BCWS
Jonathan is the PO of 30 members agile team and they are planning the tools they will use for the project. They are debating how they should show what work is in progress.
Of the following options, which tool are they most likely to select?
User story backlog
sprint backlog
Task board
Product roadmap
Kanban Board
As a project manager, you have recently completed a software development project for a client. To assess customer satisfaction, you decide to measure the Net Promoter Score (NPS) by surveying your client's users. The survey results indicate that 40% of the respondents are promoters, 30% are passives, and 30% are detractors.
What is the NPS for this project?
10
0
-10
20
You are managing a project with 23 team members and six key stakeholders. Two team members identify a problem with the current approach. Addressing that problem will require changes to the project plan and its subsidiary plans. One of the stakeholders previously indicated that any delays are unacceptable, and your team members tell you that its possible the change could cause the team to miss at least one critical deadline.
What is the BEST way to deal with this situation?
Analyze the impact that the change will have on the work to be done, the schedule and the budget
Deny the change because any delays are unacceptable
Gather consensus among the team that you should make the change before approaching the stakeholders, so that they can see the team supports making the change
Make the change to the project plan and subsidiary plans, and ask the team to implement the change
Mary is the Senior Systems Architect of Global Software LLC. The company is planning a software release in 5 hours, but Mary just identified that one of the functions is not working properly. She rushed to James, who is the Chief Systems Architect in the subject matter, and explained the situation. James immediately advised to debug the function and restart the system. Mary completed the actions James advised and found the problem was now resolved.
What type of authority was James utilizing when Mary promptly adopted his suggestions?
James was putting himself in a position for Mary to be indebted to him, so he was demonstrating ingratiating power
James was most likely demonstrating Expert Power in this situation by demonstrating his knowledge and expertise in guiding mary
James was demonstrating Relational Power by demonstrating the important position he holds in relation to Mary, his employee
James was most likely demonstrating Situational Power because he was helpful only in this situation, and does not have power over Mary in any other context
During the last retrospective, an agile team recognized several risks, one of which is the possibility of employing a contractor to accelerate a crucial investigation's pace during the next iteration.
How should the team classify this risk?
Emergent
Issue
Threat
Opportunity
Residual
Claire has replaced a project manager on a project that is already in the execution phase. The project is behind schedule and she has been specifically brought in to ensure the project meets its schedule. She decided to review the schedule network diagram created by the earlier project manager and she realizes that the project is 3 weeks behind schedule.
After reviewing the activities and the network diagram she decided to Crash the schedule. So this means she ____
Decrease the scope of the project after discussing with the sponsors
Perform activities in Parallel to decrease the schedule
Add additional resources to the activities on the Critical path
Discuss with the sponsors and explain how it is not going to be possible to meet the schedule
Anne is a project manager for a construction company in London. She is currently working on a project to modernize the living quarters in one of the smaller castles located outside of the city limits. The project has been underway for some time. Anne wants to determine how well the project is executing.
Which tool might she use to evaluate how the project is executing at a specific point in time?
Anne should calculate the cost performance index, or CPI, to evaluate how well her project is executing
Anne should refer to historical data and compare the progress of her project to the progress of other similar projects to see if it is on track
Anne can rely on her expert judgement to evaluate the project execution if she has at least 10 years of experience, otherwise she should defer to the judgement of her PMO manager
Anne should perform a cost variance analysis to evaluate the execution of her project at a specific point in time
After two months into a three-year roll-out of a mobile telecommunications project, the project manager realizes that roughly 15% of the equipment is banned for delivery due to an embargo. The procurement contract with vendor does not account for this embargo, but the company may face substantial penalties for not completing the delivery.
What is the appropriate solution for the situation for delivery in the project lifecycle?
Introduce an agile approach track with client to analyze and prepare for the delivery of substitute equipment
Investigate additional insurance and contingency strategies to account for the risk's cost
Compare the costs of the penalties for delivering the equipment or not delivering it and choose the lesser of the two
Assume the client's penalties, end the project, and terminate the company's operations in that country
DSDM uses the MoSCoW technique to create the list of prioritized requirements. In the term "MoSCoW technique," "M" stands for:
Must have
Mostly have
Must not have
Medium
MVP
Liam is a project manager at his organization, and he has been assigned to a project that is in progress because the previous project manager was promoted.
He is currently working on Stakeholder Management for the project, which the previous project manager did not complete. Which of the following statements is most true about when Liam should perform stakeholder analysis?
Liam should perform stakeholder analysis when identifying stakeholders on his project
Liam will perform stakeholder analysis when developing the project charter, since this information will need to be included in the project charter
When creating the project management plan, Liam will perform Stakeholder Analysis as part of this process
Liam will perform stakeholder analysis when putting changes through change control so that he can analyze the impact of the changes on his stakeholders
Abrar is in the process of executing a project that deals with laying out electrical cables connecting two cities. He has been reporting progress on a monthly basis. Due to unplanned vacations this month, many of the staff have not reported to work.
This has caused a delay in the schedule. Abrar decides to check if the schedule variance is within the allowable threshold. What document should he refer to?
Project Management Plan
Activity Definition
Project Schedule Network Diagram
Schedule Management Plan
Numerous risks and issues have been noted by the agile team, however the notes might use some clarification. Of the following, which are risks? (Select all that apply as risk)
burndown chart is out of date and delayed
During this iteration, the new DevOps toolchain may be mandate to complete the work
Requirements are not clear and flawed as a result of a misunderstanding of the vision statement
The project's technical lead has left the business
It has been mentioned by a senior VP that there are further prerequisites in project
Barbie is a project manager at a tech company, but she is currently managing a project to build her dream house. She wants to hire someone to do the landscaping on her house, but she isn't 100% sure yet what all she wants included in landscaping. She received several proposals for the work.
Considering the scope is not fully defined for her landscaping, which contract would be best?
All-Green Landscaping submitted a proposal to perform landscaping work with a target fee of $2000
Bravo Landscaping submitted a contract proposal to perform the landscaping work for a fixed price of $2 per square foot of her yard
Charlie's Landscaping submitted a proposal to perform the work as a cost-reimbursable contract
Delta Landscaping provided a proposal to complete the landscaping work for a fixed price of $5000
Bruce has an excellent idea for a new project that can increase productivity by 20 percent in his organization.
However, management declines to approve the proposed project because resources are already devoted to other related projects and not providing optimized benefits with proposed project.
What Bruce has just experienced is called which of the following?
Management by exception
Management Reserve
Parametric modeling
Program Management
A single project is being worked on by three different teams, with each team responsible for a different part of the project. As the parts are highly interdependent, the team leader has expressed concerns that conflicts may arise when the outputs from the three teams are combined.
What advice or direction should the project manager provide to the team leader?
Pinpoint any possible conflicts and schedule a weekly meeting where all three teams can come together to oversee each other's work
Determine which team's work should be given priority, and postpone the work of the other two teams to guarantee that there are no conflicts
Record any conflicts as they happen and take steps to resolve any issues that emerge
Advise all three teams to continue working concurrently, acknowledging that any conflicts can be dealt with during the testing phase
Lara is a project manager at an engineering firm. She is currently putting together a bid for a project to replace a bridge on the interstate in town. Her proposal includes a schedule that overlaps the design activities with the construction activities on the project.
She has to work with a construction firm in town, and the two companies will submit their bid together. Which of the following statements is true of Lara's project?
Lara is developing a project schedule that takes advantage of the synchronous manufacturing technique
Lara is proposing a parallel management strategy for the bridge project
The schedule Lara is proposing represents a major process improvement over designing the project and constructing it afterwards
Lara is using overlapping activities to fast-track her schedule for the bridge design project
Organizations performing projects will usually divide each project into several project phases to improve management control. This also provides links to the ongoing operations of the performing organization. Collectively, project phases interactions grouped and overlapping between multiple phases from initiation to closure is also called:
Project management life cycle
Project phases life cycle
Product life cycle
Project life cycle
As a project manager you will be asked to communicate with many different people from varied levels in the organization that have disparate backgrounds. It's important to find the best communication for each situation instead of relying on one method in all situation.
If you can get good at this it will set you apart from your peers, since most project managers prefer what kind of communication?
Most project managers prefer lateral communications, since they are more laid-back than communicating upwards or downwards
Most project managers prefer written communicaiton so that if a resource tries to claim down the line that they weren't informed of something, the PM has a written record of the exchange
Most PM's prefer oral communications because they can assess the responses of the person they are talking to and gauge if the person is understanding
Most project managers prefer downward communication because you don't have to be as politically correct when talking to someone that's a lower level than you
Felina is the project manager of a software implementation project. Three days before the software is supposed to enter Beta testing, there is a change order issued by the client that asks for a complete redesign of the interface. This type of redesign is unprecedented, and Felina finds herself at the center of a crisis. In previous weeks her leadership with the team had been minimal, but now she must jump to the front of the team as per the scenario and quickly figure out a way to implement the client's requested change order. What form of power is Felina exercising in this situation?
Felina is exercising Coercive Power because she will have to force others to do things they would not normally be inclined to do
Felina is exercising Informational Power because she has received the information from the client and will have to communicate it to the project team to gain buy-in
Felina is exercising Referent Power because she will have to call on her reputation gained by her previous body of work to convince the project team to follow her through this stressful time
Felina is exercising Situational Power because the situation is requiring her to step into a more involved role in her project team
Jamie Anderson is the CEO of Club Royale Design LLC, which is the largest designer of night clubs and bars in Los Angeles, California. Recently, Jamie appointed his wife as the head of the PMO for Club Royale. This appointment included the authority to be the sponsor of an upcoming project, a collaboration with a very well known actress and singer.
What form of power did Jamie give his wife by appointing her head of PMO and giving her sponsorship authority?
By appointing her head of the PMO and giving her sponsorship authority, Jamie has given his wife Formal power through her title
By appointing her head of the PMO and giving her sponsorship authority, Jamie has given his wife Authoritative power through investing her with the authority of the office she now holds
By appointing her head of the PMO and giving her sponsorship authority, Jamie has given his wife Legitimate power by verifying her authority with a title and office
By appointing her head of the PMO and giving her Sponsorship authority, Jamie has given his wife all the above forms of power
You are a project manager managing a large software project. It has a month long design phase in which the team would be preparing the design documents for independent project modules. Review activity for these modules can be recommended to begin 15 days after starting the design phase.
The 15 days difference between the start of the design phase and the start of the review shows _ _ _ _ _between the two activities.
Lead
Lag
External dependency
Mandatory Dependency
Bethany is a project manager at her organization. Her current project assignment is the PM on a project to modernize the camp sites at a state park, including running electricity and sewer hookups to the individual camp sites to they can accommodate recreational vehicles. Since the project is being funded through the State Park, there is a very strict budget that may limit some of the work that can be done on the project.
Which of the following statements is first and most true about the project budget?
The budget on the project is an assumption that the State Park made, that will likely prove to be an erroneous assumption since most government projects end up way over budget
In this context, the project budget is a good scenario of a project constraint because it limits the project in some way
The project budget is a kill point on the project, because if at any point the budget projection is more than the budget allowance, the State Park will probably kill the project
The budget is a representation of project risk and Bethany needs to come up with a risk response plan to account for the budget
Azalea is the project manager of an IT company. She is creating a collection and filing structure that details methods used to gather and store various types of information, and is also writing procedures to collect and disseminate updates and corrections to the concerned stakeholders.
Where will she record this information control procedures and processes?
Information retrieval system
Information distribution methods
Project records
Communications Management Plan
Frank is planning procurement activities for his multi-million dollar project based in Jeneva. He is assessing different pricing contracts. He came across a contract type where the seller's performance period spans a considerable period of years, as is desired with many long-term relationships.
It is a complete project with detailed scope, but with a special provision to the contract price on moral grounds due to changed conditions like inflation, or cost increases (or decreases) for specific commodities or materials.
What is the name of this contract type?
Firm Fixed Price Contracts (FFP)
Fixed Price Incentive Fee Contracts (FPIF)
Fixed Price with Economic Price Adjustment Contracts (FP-EPA)
Time & Materials
An agile team member resolved a problem that had blocked work for several weeks. However, following the software release, it became evident that the solution resulted in a malfunctioning function. Consequently, the quality director requests an explanation.
In which two ways should the project manager react?
Ask the team member to present his rationale and lessons learned
Collaborate with the team to identify any deficiencies in the Definition of Done
Issue a warning to the team member about NOT taking risky initiatives
Collaborate with the team to recognize any inadequacies in the Definition of Ready
Respond to the director that mistakes are inevitable but will be remedied
Dakota was recently hired on under a contract to perform project management services for an internet service provider. His current project involves running a new fiber trunk in an urban area. The project should be relatively simple since there is an existing conduit, but since there are lots of stakeholders and Dakota's company doesn't own the conduit, the project could become more complex. Dakota has just completed the requirements management plan and defined the scope of the project.
Which statement is the best explanation of Dakota's next step?
Dakota will need to take steps to validate the scope listed in his scope definition statement before he performs any further work on the project
Dakota should take some time to define the activities in his project so that he can create the schedule and let the stakeholders know if he will finish on time
Dakota needs to start on the Control Project process since it sounds like there is a significant risk that his project might get away from him
Dakota will need to use the scope statement and management plan to create a work breakdown structure, or WBS, for his project
A company is starting to introduce Agile practices, and the project manager has been asked to identify how to introduce the new process.
What should be the project managers initial approach and plan ?
Institute daily standup meetings immediately to get regular updates
mandate the Agile Manifesto to the team
Balance training and teaching principles with Agile practices by assessing knowledge gap
understand the teams progress in learning new methods
Despite the team's efforts to fix the problems, certain items continue to appear in the Kanban blocked column. All of the obstacles are related to required corporate business operations, which increase wait times, the retrospective indicates.
What should the project manager do next?
While the team is at a team-building activity, act as a servant leader to address the outstanding business process concerns
Spend the following iteration training the team how to use the business procedures to enable more independent work
To streamline procedure and secure the team coaching on the processes work with process owners
Set up an information radiator to showcase the level of support of stakeholders for the project goals, with a ranking system in place
Hank is the CEO of a small company that does data analytics. Hank employs about 75 people and likes to run a tight ship. He wants to keep costs down and maximize the profitability of his small company. To this end, he sends out a memo stating that all project managers are now required to use only pencils, not pens, and that they may only request new pencils when the current pencils are less than 1 inch in length.
To show how serious he is in this directive, Hank searches online and finds some strong terminology to include in his memo: Failure to comply with this expectation will result in disciplinary action. What kind of power is Hank using?
Hank is using Coercive Power, because he is forcing others to do things he wants them to do through threat of punishment.
Hank is using Informational Power by providing others with information about the potential consequences of their decisions
Hank is using Referent Power by referring to policies and procedures that could have an impact on how his employees approach their choices
Hank is using Persuasive Power by providing his employees with an empassioned case to follow his way of thinking
In the context of change management, which model focuses on individual change and the stages individuals go through when transitioning from the current state to the desired future state?
ADKAR model
RACI model
SWOT Analysis
PERT
You are in charge of a project to develop software. A new feature that your team is creating needs to be integrated with a third-party API. The team runs into an unanticipated technical problem with the API integration. To examine alternative answers and choose the best course of action, they suggest running a spike.
What approach would be best for you as the project manager?
Approve the spike immediately and allocate resources to conduct the necessary investigation
Consult with the team to gather more information about the specific technical challenge and its impact on the project
Proceed with the original plan and hope that the team can resolve the technical challenge without a spike
Delay the project until the technical challenge is resolved, avoiding the need for a spike
Brighton is planning procurement activities for his multi-million dollar project based in New York. He is assessing different pricing contracts. He came across a contract type which is favored by most buying organizations because the price for goods is set at the outset and not subject to change unless the scope of work changes. Any cost increase due to adverse performance is the responsibility of the seller, who is obligated to complete the effort.
What is the name of this contract type?
Firm Fixed Price Contracts (FFP)
Fixed Price Incentive Fee Contracts (FPIF)
Fixed Price with Economic Price Adjustment Contracts (FP-EPA)
Time and Materials
You are assigned as a project manager to an existing project where the previous project manager departed without notice. After your first meeting with the project team, they pointed out some issues within the project that were common with other previous similar projects. You decide that you need to go through the proper documents to analyze its data, identify these common issues, and address possible resolutions?
Which documents are you supposed to cite?
I can analyze Requirement Documents data as they contain all stakeholders requirements, and thus it will help me identify these common issues and develop possible resolutions
By analyzing the Assumption Log and project charter data to determine the objective from the project and all assumptions aiding me in identifying these common issues and develop possible resolutions
I can analyze the Lesson Learned Register data to identify common issues to develop possible resolutions
I can analyze change log data as it contains the identified changes that have occurred throughout the project; this will help me identify these common issues and develop possible resolutions
Evan is a project scheduler at his organization. The owner of the company recently hired his nephew as a project manager, but the nephew had no project management experience. Evan is trying to explain to the new project manager how critical path scheduling works. Evan is explaining why it's important to know the longest path through the network that shows the shortest duration in which the project can be completed.
Which statement is most true about the concept Evan is explaining?
Evan is teaching the new project manager at his company about the Critical Path in a project schedule network
The concept that Evan is teaching the new project manager is the Project schedule concept
The common phrase for the concept Evan is teaching the new project manager is Least possible time
None of the above statements accurately represent the concept demonstrated in the question
Picasso took over a customer project for his company. From the inputs available, including contract, statement of work, and project charter, he has developed a project management plan.
He already presented that plan in a meeting with key stakeholders including his project sponsor and some representatives from the customer organization. During the meeting he sensed a high level of dissatisfaction by the customer executives, who signaled that the project might not produce the results that their company had expected. In his understanding, all necessary actions have been planned to meet the customers requirements.
What should he do next?
Arrange meetings with the customer to identify their needs, wants and expectations for the project. Then create a narrative Scope Statement from this information to document the agreed upon project scope
Request a written statement from the customer(s) detailing the requirements which they believe are not addressed by your plan. Use this statement to update the project plan
Request a formal meeting at the top executive level to sort out misunderstandings, then submit a change request, re-plan your project where necessary, and continue with the project work
Do not over-react. Performed according to your plan, the project will produce a convincing product for the customer. As soon as the executives will see it, they will probably change their opinion and accept it
You are in your third month of project execution which is expected to continue for a duration of 14 calendar months. Your sponsor has asked for a performance report. You decide to create a S curve. Based on the S curve you report your Actual Cost which is more than the Earned Value.
Also the Planned Value is greater than the Earned Value. What would be the interpretation of this data ?
The project is over budget and behind schedule
The project is on schedule and on budget
The project is over budget but on schedule
The project is on budget but behind schedule
Tragedy strikes on a project aimed at refurbishing a bus terminal and upgrading the service. An unforeseen natural disaster has caused damage to both the site and the neighboring city.. The project team, watching from a safe location 250 kilometers away, is in emergency response mode.
What should the project team do next?
Use the contingency budget
Activate the management reserve
Update the risk register
Engage stakeholders to develop a risk response
Elbert has been working as a project manager at his organization for several years. Recently his PMO offered a training on a new software that assists project managers in performing risk assessment.
Elbert is excited for the new tool because it will allow him to model risks on a computer to show random probabilities. Which of the following statements is most likely true about Elbert's new tool?
Elbert will be able to use the new software to perform a computerized risk audit on his projects, which will save him a significant amount of time
Elbert will be using the new software to perform Monte Carlo simulation analysis on his projects
Elbert can use the new software to perform EMV analysis and calculate the value of his projects in "today's" dollars
Elbert will use the new software to establish a faster way to implement the Delphi Technique for his clients
You have recently joined an organizations project management office.After reviewing the organizational assets you realize that project managers have not routinely documented lessons learned for their projects.
There are a few projects that are about to start - You decide to call up a meeting of all the project managers and explain the need of Lessons Learned.In order to get a buy in from your managers - What would you focus on as the best use of this document
It helps the team to plan tasks
It helps in performance reporting
It will help the manager to better control the project
The historical information can be used for other projects
The project manager is facing challenges in obtaining consistent feedback from stakeholders, which is necessary to identify assumptions and constraints.
How can the project manager improve stakeholder engagement?
Use political awareness techniques
Institute checklist policies
Research effective meeting management techniques
Make use of effective facilitation techniques
A software development project is under the purview of a project manager, and the project team, originally following a predictive approach, has opted to switch to an agile approach due to evolving requirements and customer needs.
Which three actions should the project manager prioritize to ensure a smooth transition from a predictive to an agile approach and that the team adapts well?
Train the team on the agile mindset
Create a detailed plan for the transition
Engage the team in a discussion on the transition
Implement agile practices and inform the team
Request an agile coach to help the team
Kimmy is a project manager at an electronics manufacturing company. She is currently engaged in reviewing the scope statement on the project she was just assigned to. Kimmy is taking over the project from another project manager.
Kimmy can expect to find the product scope descrption and the project deliverables in the scope statement. What else should Kimmy look for in the scope statement?
Kimmy should be sure to identify the Scope Baseline in the scope statement, so that she has something to compare against if there are any changes made to the project scope
Kimmy can find the product acceptance criteria in the project scope statement
Kimmy should be able to discern the complete Work Breakdown Structure from her copy of the project scope statement
Kimmy should be able to find the WBS dictionary in one of the appendicies to the project scope statement