1.

For the given ACTIVITY ON ARROW AOA project network, what is the duration of the project? Given numbers are in 'days'

a)

14 days

b)

16 days

c)

9 days

d)

11 days

2.

For the given ACTIVITY ON ARROW AOA project network, what is the Critical Path?

a)

A-D-H-J

b)

B-E-H-J

c)

B-F-J

d)

C-G-I-J