For the given ACTIVITY ON ARROW AOA project network, what is the duration of the project? Given numbers are in 'days'
14 days
16 days
9 days
11 days
For the given ACTIVITY ON ARROW AOA project network, what is the Critical Path?
A-D-H-J
B-E-H-J
B-F-J
C-G-I-J