1.

The earliest method of used for planning of project was

a)

CPM

b)

PERT

c)

Milestone chart

d)

barchart

2.

The occurrence of the completion of an activity is called its

a)

head event

b)

tail event

c)

dual role event

d)

none of these

3.

Crashing is

a)

reduction in duration

b)

reduction in resources

c)

reduction in cost

d)

reduction in size

4.

In a project, the major quality control methods are

a)

Testing & Sampling

b)

Inspection & Testing

c)

Inspection & sampling

d)

Inspection, testing & sampling

5.

Which of the following is not related to the cost slope

a)

Crash cost

b)

Normal cost

c)

slack

d)

Crash time

6.

Direct cost includes cost of

a)

Cost of materials, equipment and manpower

b)

Cost of materials only

c)

Cost of material, manpower

d)

Cost of rent offices

7.

Cost slope is given by

a)

crash cost - normal cost / crash time - normal time

b)

crash cost - normal cost / normal time - crash time

c)

normal cost - crash cost / normal time - crash time

d)

crash time - normal time / normal cost - crash cost

8.

Cost slope gives the

a)

increase in cost by increase in time

b)

decrease in cost by increase in time

c)

decrease in cost by decrease in time

d)

increase in cost by decrease in time

9.

Latest start and finish time in CPM is determined by

a)

Forward pass

b)

Backward pass

c)

Upward pass

d)

Downward pass

10.

Total float is equal to

a)

LST + EST

b)

LST - EFT

c)

LST - EST

d)

LFT + EST

11.

In PERT, the variance of an activity is determined by

a)

(b-a)/6

b)

(b−a)2/6(b-a)^2/6

c)

(b−a)/62(b-a)/6^2

d)

((b−a)/6)2((b-a)/6)^2

12.

If the optimistic, most likely time and pessimistic time for an activity are 7, 8 and 10 respectively, the standard deviation is

a)

0.5

b)

0.25

c)

0.20

d)

0.35

13.

Zero float for any activity means that the activity is

a)

super-critical

b)

sub-critical

c)

Critical

d)

Non critical

14.

If an event has a TE of 10 days and a TL of 14 days, what is the Slack?

a)

4 days

b)

10 days

c)

14 days

d)

24 days

15.

Which of the following is a key component of a construction site's emergency preparedness plan?

a)

A list of aesthetic design elements

b)

Accessible fire extinguishers and a clear evacuation plan

c)

A budget for material procurement

d)

A schedule for non-critical tasks

16.

CPM, what happens if insufficient man-hours are allocated to a critical path activity?

a)

The project's budget remains unaffected

b)

The activity duration increases, delaying the entire project

c)

Only non-critical activities are delay

d)

The project's aesthetic design is compromised

17.

Which one is not an example of direct cost

a)

cost of materials

b)

cost of equipment and machinery

c)

cost of manpower

d)

supervision charges

18.

Which of the following is an example of indirect cost

a)

overhead charges

b)

Establishment charges

c)

both a & b

d)

only a

19.

If the optimistic, most likely time and pessimistic time for an activity are 7,8 and 10 respectively, the variance is

a)

0.5

b)

0.125

c)

0.225

d)

0.25

20.

A dummy activity

a)

is artificially introduced

b)

is represented by a dotted line

c)

does not require time

d)

all of these

21.

Critical path

a)

is always longest

b)

is always shortest

c)

maybe longest

d)

may be shortest

22.

CPM adopts

a)

probabilistic approach

b)

deterministic approach

c)

stochastic approach

d)

periodic approach

23.

The settlement between the two parties can be done by

a)

a third party or agency acceptable to both parties acting as a mediator and giving a settlement

b)

disputes can be settled through litigation in a court of law

c)

settlement of disputes by arbitration

d)

all the above

24.

If the variance of a dataset is 81, what is the standard deviation?

a)

9

b)

8

c)

7

d)

6

25.

------ is the field of applied ethics and system of moral principles that apply too the practice of engineering.

a)

Engineering ethics

b)

code of ethics

c)

ethics

d)

ethical judgement

26.

------ are adopted by an organizations to assist members in understanding the difference between right and wrong and in applying that understanding to their decisions.

a)

Engineering ethics

b)

code of ethics

c)

ethics

d)

ethical judgement

27.

Workmen compensation act was enforced in the year

a)

1948

b)

1944

c)

1946

d)

1923

28.

PERT method requires

a)

single time estimate

b)

double time estimate

c)

triple time estimate

d)

four time estimate

29.

What should be done to ensure safe operation of heavy machinery on a construction site?

a)

Allow untrained workers to operate machinery to save time

b)

Ensure operators are trained, equipment is maintained, and safe zones are marked

c)

Paint machinery in bright colors for visibility

d)

Operate machinery without daily inspections

30.

Which of the following is a mandatory requirement for workers handling hazardous materials on a construction site?

a)

Wearing decorative clothing.

b)

Operating heavy machinery without training

c)

Using appropriate personal protective equipment (PPE) like respirators.

d)

Completing a marketing training course