Wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

11. Inspection & Testing

Total questions: 46

Worksheet time: 23mins

Name
Class
Date
1.

Why should all documentation given after initial verification be kept in a safe place?

a)

Adds value if selling the property

b)

To reduce insurance premiums

c)

As reference for any persons inspecting any work at a later date

d)

To comply with any local authority inspections

2.

For safety reasons, what is the recognised status for undertaking and signing off inspection and test work?

a)

a skilled person

b)

an instructed person

c)

a person qualified in PAT testing

d)

a person who is a member of the IET

3.

On which two documents is prospective fault current recorded?

a)

Minor Electrical Installation Works Certificate and Schedule of Inspections

b)

Electrical Installation Certificate and Schedule of test results

c)

Electrical Installation Certificate and Minor Electrical Installation Works Certificate

d)

Schedule of Inspections and Schedule of test results

4.

Which is one of the documents that must accompany an Electrical Installation Certificate?

a)

Minor Electrical Installation Works Certificate

b)

Landlords safety certificate

c)

Electrical indemnity certificate

d)

Schedule of Inspections

5.

On completion of electrical work, all appropriate documentation should be

a)

Given to the building inspector

b)

Retained by the electrician

c)

Left next to the mains position

d)

Given to the person ordering the work

6.

Functional testing may involve

a)

Insulation resistance testing

b)

Disconnecting an appliance

c)

Turning on a light switch

d)

Continuity testing

7.

A check for phase sequence at the main intake to a three phase installation indicated a result of L1, L3, L2. The correct orientation at each subsequence distribution board is

a)

L1, L3, L2

b)

L2, L3, L1

c)

L2, L1, L3

d)

L3, L2, L1

8.

One reason for testing that the phase sequence is the same across an installation is

a)

The hold-on relay in motor starters can be connected to the correct phase

b)

Fluorescent lamps will not make moving machinery appear stationary

c)

The installer will know the direction of rotation of three phase machines

d)

Power factor correction capacitors can be connected the right way around

9.

The table shows the results for a test carried out on a 30mA RCD to BSEN 61008, that is being used for additional protection. Which statement best describes the result of the test?

a)

The RCD fails as it should trip within 0.4s at 15mA leakage

b)

The RCD fails as it should trip within 300ms at 30mA leakage

c)

The RCD passes as it trips quicker than all the required tripping times

d)

The RCD fails as it should trip within 0.02s at 150mA leakage

10.

What is the minimum permitted value to be found on a protective device at the origin of 230V single phase circuit where Ze is 0.12Ω?

a)

1500

b)

6000

c)

3000

d)

10000

11.

The measured value of prospective fault current for a single phase installation can be checked by

a)

Voltage divided by Ze

b)

Voltage divided by the demand load

c)

Looking in BS7671 IET Wiring Regulations

d)

Looking in BS7671 One Site Guide

12.

Calculate the maximum permitted value of earth fault loop impedance for a circuit when the maximum tabulated value quoted in BS7671 is 2.4Ω.

a)

1.92 Ω

b)

4.84 Ω

c)

2.16 Ω

d)

2.42 Ω

13.

If Ze is to be obtained by direct measurement, the

a)

Main switch is off and the earthing lead is connected

b)

Main switch is off and the earthing lead disconnected

c)

Main switch is on and the earthing lead connected

d)

Main switch is on and the earthing lead disconnected

14.

Which of these best describes the fault current return path to the origin of the supply, for a TT earthing system?

a)

The fault current returns to the origin via the general mass of earth

b)

The fault current returns to the origin via a separate earthing conductor

c)

The fault current returns to the origin via a combined earth and neutral conductor

d)

The fault current returns to the origin via the line and neutral conductor

15.

The three results from an earth electrode tester on a TT system were 100Ω, 110Ω, 90Ω. What value is recorded on the schedule of test results?

a)

100 Ω

b)

110 Ω

c)

90 Ω

d)

200 Ω

16.

Which instrument is used to confirm the polarity of the incoming supply?

a)

An earth fault loop impedance tester

b)

An approved voltage indicator

c)

A low resistance ohm meter

d)

An insulation resistance meter

17.

The test for polarity must not be used to check

a)

That single pole devices are in the line conductor only

b)

If the supply to the installation is live

c)

If wiring is correctly connected

d)

If the centre-contact of an Edison Screw lamp holder is connected to the line conductor

18.

When a cables length is reduced, the effect on the insulation resistance will be to

a)

Stay the same

b)

Reduce

c)

Increase

d)

Fluctuate

19.

A circuit is being supplied with a voltage of up to and including 500V. Identify the minimum expected insulation resistance test value, and the correct scale of measurement.

a)

0.5 MΩ

b)

1.0 MΩ

c)

500 MΩ

d)

230 V

20.

What is the best action to take when carrying out an insulation resistance test on a surge protection device that is vulnerable to the test voltage and cannot be reasonably removed?

a)

The test voltage is reduced to 250V and the test is carried out as normal with a requirement of a minimum value of 1MΩ

b)

The test voltage is reduced to 250V and the test is carried out as normal with a requirement of a minimum value of 0.5MΩ

c)

The test is carried out differently with measurement taken from line to CPC and neutral to CPC but not from line to neutral

d)

If the circuit is visible along the whole of its length, it is not tested but is subject to a thorough visual inspection instead

21.

What is the effect on the overall resistance if two cables are connected in parallel?

a)

Decreases

b)

Remains the same

c)

Increases

d)

Increase momentarily then decreases

22.

A ring final circuit test is carried out. During step 1 of the test the resistance of the end to end loops at the consumer unit are r1: 0.8 Ω and r2: 1 Ω. If the circuit has no spurs, what is the expected value of R1 + R2?

a)

0.6 Ω

b)

0.45 Ω

c)

0.3 Ω

d)

0.9 Ω

23.

Which is not an advantage of test method 1, when measuring the continuity of protective conductors?

a)

There is no long wandering lead to present a hazard

b)

Correct polarity can be checked at the same time

c)

Continuity of bonding conductors is easily measured

d)

R1 + R2 can be measured directly at the same time

24.

The low resistance of the protective bonding conductors should be verified to ensure that

a)

The RCD (Residual Current Device) operates within the required 30ms

b)

The protective device operates within the required time

c)

Touch voltage is limited in the event of a fault to earth

d)

Touch voltage is limited in the event of a short circuit

25.

The sequence of testing in GN3 is carried out during initial verification of new build because

a)

The result of a previous test may influence the next test

b)

This is the sequence laid down by the Building regulations and cannot be changed

c)

GN3 is a statutory document and must be followed in that order

d)

This is the sequence laid down by the Electricity at Work Regulations and cannot be changed

26.

When conducting an insulation resistance test on a whole distribution board as allowed under certain conditions in BS 7671. The result was 1.2MΩ. What would be the most appropriate action to taken in this situation?

a)

Record the value, issue a code 1 and lock off the isolator

b)

Record the value and take no further action

c)

Record the value, tell the client that it meets the requirements and the premises will need testing again in three months

d)

Disconnect the circuits and test individually as possibly a circuit is deteriorating

27.

Why are details of the test instrument included on the schedule of test results?

a)

In order to compare test results from that instrument with others

b)

So that the test can be repeated with exactly the same test instrument

c)

So that calibration records for the instrument can be checked if necessary

d)

To find out if the test instrument is reading correctly on some tests

28.

For a circuit having an R1 + R2 reading of 0.37 Ω the test instrument and range should be

a)

An insulation resistance test instrument set to the maximum range

b)

A low resistance ohmmeter set to the minimum range

c)

An insulation resistance test instrument set to the minimum range

d)

A low resistance ohmmeter set to the maximum range

29.

Which dead tests should be performed on a ring final circuit?

a)

Continuity, Insulation Resistance, Polarity

b)

Continuity, Polarity, CPC and RCD testing

c)

Insulation Resistance, Polarity, Earth Fault Impedance

d)

Continuity, Polarity, Earth Loop Impedance

30.

What is the minimum IP rating for correctly rated and protected current, using equipment in zone 1 of a room containing fixed bath if there are no water jets?

a)

IP X5

b)

IP 4X

c)

IP X4

d)

IP 5X

31.

What is not allowed for use on a construction or demolition site under normal conditions?

a)

Reduced low voltage

b)

A PME facility as a means of earthing

c)

SELV

d)

PELV

32.

A radial power circuit has been installed without any spurs, and protected by a 32A, type B circuit breaker. What is the minimum c.s.a of the live conductors?

a)

4mm²

b)

6mm²

c)

1.5mm²

d)

2.5mm²

33.

When inspecting a 10mm² single core cable used as a protective conductor, it must be checked that it is constructed from

a)

Aluminium

b)

Copper

c)

Chromium

d)

Steel

34.

The inspector’s sense of touch will help to identify

a)

If the MCB’s correctly selected

b)

A loose connection

c)

If the cables have been correctly identified

d)

The correct connection of equipment

35.

When inspecting a system that uses double insulation as a protective measure, what symbol would be present on the equipment?

a)

a circle inside a circle

b)

a rectangle inside a rectangle

c)

a square inside a square

d)

a triangle inside a triangle

36.

The main source of information to check the suitability of an electrical installation is

a)

Electricity at Work Act

b)

IET Wiring Regulations

c)

RIDDOR

d)

PUWER

37.

The Electricity At Work Regulation 1989 are

a)

Non-statutory

b)

Statutory

c)

A code of practice

d)

A training document

38.

Information on the requirements for an initial verification can be found in

a)

Guidance note 5

b)

Guidance note 7

c)

Guidance note 3

d)

Guidance note 1

39.

The purpose of the initial verification process is to verify that the

a)

Installation complies with BS7671

b)

Installation has been completed by a competent person

c)

Tester has the correct test instruments

d)

Necessary paperwork is in place

40.

During this initial verification, checks are carried out to ensure that

a)

Test instruments are calibrated and up to date

b)

All parts of the fixed installation are correctly selected and erected

c)

The tester has the correct qualifications and experience

d)

The serial numbers of the meters are recorded on the certificates

41.

Test leads for use on circuits measuring above 50 volts shall comply with the requirements of

a)

BSEN 60898

b)

BS 7671

c)

BS 88

d)

GS 38

42.

A shop has instructed an electrician to work on the lighting system without isolating the circuit, as the shop owner did not want the shop to be in darkness. The best response would be to

a)

Refuse to do the work and walk off the job

b)

Complete the work taking extra care

c)

Suggest a re-visit when the shop is closed

d)

Complete the work as it has RCD protection

43.

For what reason might isolation of a circuit need to occur on a weekend?

a)

Need to maintain productivity in a factory

b)

Need to maintain overtime work

c)

Avoids the need to notify a loss of supply

d)

So that apprentices can learn the trade

44.

The first action when following the procedures for safely isolating is to

a)

Test the circuit

b)

Safely isolate

c)

Prove the test instrument

d)

Carry out a risk assessment

45.

Which is an example of correctly securing the safe isolation of a circuit?

a)

Leaving a signed label at the isolator

b)

The use of a padlock on an isolator

c)

Turning the isolator into the off position

d)

The use of a fixing device on an isolator

46.

Which statutory document refers to the safe practice when performing inspection and test with regard to those carrying out the test and other people in the building?

a)

BS7671 IET Wiring Regulations

b)

Guidance Notes 3: Inspection and Test

c)

BS7671 On Site Guide

d)

Electricity at Work Regulations 1989