1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The time-box for the Sprint Planning meeting is...
Whenever it is done
4 hours
Monthly
8 hours for a monthly Sprint. For shorter Sprints it is usually shorter
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A Development Team is waiting for a specific software component that they need to integrate and use. The component should be ready in a month. The Backlog Items with highest priorities depend on this specific component. What should the Product Owner do?
Make sure the dependency is visible in the Product Backlog and the Development Team has enough independent Items for the next Sprint
Nothing. The Product Backlog already has the most valuable items at the top. The Development Team cannot proceed further until the dependency is resolved
Remove the dependent Items from the Product Backlog and put them in a special wait list. When the dependency is resolved, the Items should be returned back
Transfer the dependent Items to the Integration Team
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What could be a source of requirements for any changes to be made to the product?
Product Backlog
Development Team
Key Stakeholders
CEO of the Organization
4.
MULTIPLE SELECT QUESTION
1 min • 1 pt
What happens when a Sprint is cancelled? Select three answers.
Any completed and "Done" Product Backlog items are reviewed
At the Sprint Retrospective the Scrum Master determines who from the Development Team is responsible for cancelling the Sprint
If part of the work is potentially releasable, the Product Owner typically accepts it
Several top Product Backlog Items are taken into the Sprint Backlog to replace the obsolete items
All incomplete Product Backlog Items are re-estimated and put back on the Product Backlog
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Scrum recommends using only those Scrum components and rules which suit most for a particular project.
False
True
6.
MULTIPLE SELECT QUESTION
1 min • 1 pt
Who participates in the Sprint Planning? Select three answers.
Product Owner
Key Stakeholders
Scrum Master
Development Team
Team Manager
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Definition of "Done" is created during the first Sprint and remains unchanged until the Product release.
False
True
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?