1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A RACI matrix is one way to show roles and responsibilities on your project. What does RACI stand for?

Responsible, Approve, Consult, Identify
Responsible, Accountable, Consulted, Informed
Retain, Approve, Confirm, Inform
Responsible, Accountable, Confirm, Inform

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Everybody does what Tom says because he and the president of the company are golfing buddies. What kind of power does he hold over the team?

Legitimate
Reward
Punishment
Referent

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What’s the most effective approach to conflict resolution?

Smoothing
Confronting
Compromise
Withdrawal

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Two of your team members are having a disagreement over which technical solution to use. What’s the first thing that you should do in this situation?

Consult the technical documents.
Tell the team members to work out the problem themselves.
Ask the team members to write up a change request
Meet with the team members and figure out what’s causing the disagreement.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Joe is a project manager on a large software project. Very late in his project, the customer asked for a huge change and wouldn’t give him any more time to complete the project. At a weekly status meeting, the client demanded that the project be finished on time. Joe told the client that he wasn’t going to do any more status meetings until the client was ready to be reasonable about the situation. Which conflict resolution technique was he using?

Forcing
Compromise
Withdrawal
Confronting

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You have a team of engineers working on your project. Two of the engineers have frequent disagreements. You ask them to resolve their differences through a discussion. However, that does not yield any results. Subsequently, you intervene, and based on your analysis of the situation, you suggest some changes in the way they work with each other. This still does not yield results, and you find that the project schedule is beginning to suffer. What is your next course of action?

Ensure that they work in different shifts so that they don't clash with each other.
Don't do anything. Differences of opinion among the team members are a healthy situation
Speak to the two team members and ask them to resolve their conflict amicably.
Take disciplinary action, if required, since the needs of the project are not being met.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following describes Maslow’s Hierarchy of Needs?

You can’t be good at your job if you don’t have a nice office.
You need to feel safe and accepted to want to be good at your job
Your boss’s needs are more important than yours.
The company’s needs are most important, then the boss’s, then the employee’s.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?