PMP Exam Preparation - Ch 12 Project Procurement Management

PMP Exam Preparation - Ch 12 Project Procurement Management

KG

10 Qs

quiz-placeholder

Similar activities

PMP Exam Preparation Mentoring Ch 5 Project Scope Management

PMP Exam Preparation Mentoring Ch 5 Project Scope Management

KG

10 Qs

PMP Exam Mentoring - Ch 6 Project Schedule Management

PMP Exam Mentoring - Ch 6 Project Schedule Management

KG

10 Qs

PMP Exam Mentoring Ch 8 Project Quality Management

PMP Exam Mentoring Ch 8 Project Quality Management

KG

10 Qs

Study Group PMP Exam Preparation Chapter 1, 2 and 3

Study Group PMP Exam Preparation Chapter 1, 2 and 3

KG

10 Qs

PMI ACP - Domain 5 - Adaptive Planning

PMI ACP - Domain 5 - Adaptive Planning

KG

10 Qs

PMP Exam Study Group - Chapter 6 Schedule

PMP Exam Study Group - Chapter 6 Schedule

KG

10 Qs

Project Knowledge Areas: Resource & Communication

Project Knowledge Areas: Resource & Communication

KG

6 Qs

BIMT

BIMT

Professional Development

15 Qs

PMP Exam Preparation - Ch 12 Project Procurement Management

PMP Exam Preparation - Ch 12 Project Procurement Management

Assessment

Quiz

Education

KG

Hard

Created by

quiz eNetwoQ

Used 25+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

1. The project manager has met with the team, and they are currently deciding whether they should develop internal software to meet the needs of the project sponsor or purchase external commercial software. What process are they currently engaged in?
A. Plan Procurement Management
B. Conduct Procurement
C. Control Procurement
D. Make or Buy Analysis

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

2. The project manager has negotiated a fixed-price contract with a steel supplier. The contract is for 4 years. The seller has requested that the cost be increased by 4% every year due to inflation and fuel costs. What type of contract should the project manager use?
A. Firm Fixed Price
B. Fixed Price Incentive
C. Fixed Price Economic Price Adjustment
D. Cost Plus Fixed Fee

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

3. As the project manager is getting ready to send out the request for proposals for the project, he contacts the PMO for a list of properly vetted sellers. What is the name of this list?
A. Qualified Seller List
B. Pre-qualified Seller list
C. Pre-approved selelr list
D. Approved seller list

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

4. The project manager and the team have come up with a few different criteria they will use when selecting a seller. The criteria include costs, qualifications, licenses, and financial stability of the seller. What best describes these criteria? <br /><br /><br />
A. Procurement Documents
B. Agreement
C. Request for Proposal
D. Source Selection Criteria

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

5. While working on the office renovation project, the project manager has received multiple bids from different vendors. What the project manager thought would be a cost-effective contract turned out to be very expensive. The project manager then hires a professional estimator to determine what the contract should cost. What is the project manager looking for? <br /><br /><br />
A. Outside estimate
B. Building Cost estimate
C. Independent Cost Estimate
D. PMO

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

6. The project manager and the team have determined that they will procure the installation and configuration of the telephone systems for the new computer network. They have determined that the type of agreement they will use is a cost-plus-fixed-fee contract. What project document will specify the type of contract that will be used? <br /><br /><br />
A. Procurement Management Plan
B. Procurement Strategy
C. Statement of work
D. Bid Document

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

7. The project manager has met with over six different sellers and has negotiated with them. Finally, he has selected one of the sellers and awarded the contract. What process group are these activities part of? <br /><br /><br />
A. Planning
B. Executing
C. Iniating
D. Monitoring and Controlling

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?