Search Header Logo

PM with Int. Applications

Authored by Malak Attia

Business

University

5 Questions

Used 2+ times

PM with Int. Applications
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Organizations use __________ in conjunction with work breakdown structures to help management teams identify and eventually analyze risk

a.risk breakdown structures

a.contingency breakdown structures

a.scenario analysis

a.organizational breakdown structure

a.risk assessment

Answer explanation

Organizations use risk breakdown structures in conjunction with work breakdown structures to help management teams identify and eventually analyze risk. The focus at the beginning should be on risks that can affect the whole project as opposed to a specific section of the project or network.

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Adopting proven technology instead of experimental technology in order to eliminate technical failure would be an example of which risk response?

a.Mitigating

a.Retaining

a.Escalating

a.Transferring

a.Avoiding

Answer explanation

Although it is impossible to eliminate all risk events, some specific risks may be avoided before you launch the project. Adopting proven technology instead of experimental technology in order to eliminate technical failure would be an example of avoiding risk.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A key distinction between a risk response and a contingency plan is

a.a risk response is established only for moderate risks while contingency plans are established for major risks.

a.a risk response is part of the actual implementation plan and action is taken before the risk can materialize, while a contingency plan goes into effect only after the risk has transpired.

a.a risk response is only effective when you are able to assess the likelihood of the risk and its impact on the project; all other risks are covered by contingency planning.

a.a risk response is created by the project team and the project manager while the project manager and the customer agree on the contingency plan.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

This response allocates some or all of the responsibility of realizing the identified opportunity for the project.

Exploit

Share

Enhance

Accept

Answer explanation

Definition of a share response to an identified opportunity.

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is termed a

random chance

disaster

risk

hazard

bad luck

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?