Project Controls PC 07 Rev 03

Project Controls PC 07 Rev 03

1st Grade

15 Qs

quiz-placeholder

Similar activities

Chapt5

Chapt5

1st Grade

10 Qs

PM Quiz

PM Quiz

1st - 10th Grade

10 Qs

CAPM Cost & Quality

CAPM Cost & Quality

1st Grade

16 Qs

Course 1- Foundations of Project Management

Course 1- Foundations of Project Management

1st - 3rd Grade

10 Qs

Chapt2

Chapt2

1st Grade

10 Qs

Pre-Test CAPM

Pre-Test CAPM

1st Grade

16 Qs

CHAPTER 4 (i)

CHAPTER 4 (i)

1st Grade

15 Qs

Chapt4

Chapt4

1st Grade

10 Qs

Project Controls PC 07 Rev 03

Project Controls PC 07 Rev 03

Assessment

Quiz

Professional Development

1st Grade

Medium

Created by

Gary Carr

Used 8+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The ------- Schedule, is the process of monitoring the status of the project to update the project schedule and managing

changes to the schedule baseline. The key benefit of this process is that the schedule baseline is maintained throughout the project. Which option is the correct missing word?

Monitor

Change

Control

Plan

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Project Management Plan is an Input and an Output to the Control Schedule process?

True

False

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Controlling the schedule allows for which project document updates?

Basis of Estimates

Risk Register

Assumptions Log

All options listed

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Project Management Plan updates as a result of controlling the schedule include?

Cost Baseline

Change Requests

Project Charter

All options listed

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A diagonal line plotted on a graph showing the work remaining following trend analysis and forecasting is named?

Pareto Chart

S-Curve

Burn Down Chart

Resource Calendar

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

analyzing schedule performance against the schedule baseline such as actual start and finish dates, percent complete, and remaining duration for work in progress is carried out in ?

Performance Reviews

Risk Management Meetings

Change Control Board Meetings

SOW Document

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

----- analysis examines project performance over time to determine whether performance is improving or deteriorating. What is the missing word prior to analysis?

Risk

Assumption

SOW

Trend

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?