2018 International Plumbing Code

2018 International Plumbing Code

Professional Development

49 Qs

quiz-placeholder

Similar activities

BSA Lifeguard Review

BSA Lifeguard Review

Professional Development

50 Qs

Photo Judging Quiz

Photo Judging Quiz

Professional Development

50 Qs

2017 Nursery/Landscape CDE

2017 Nursery/Landscape CDE

Professional Development

50 Qs

ESTHETICS: Ch. 12, Makeup Essentials

ESTHETICS: Ch. 12, Makeup Essentials

Professional Development

53 Qs

Minecraft

Minecraft

2nd Grade - Professional Development

50 Qs

MED #8

MED #8

Professional Development

52 Qs

GL After Leave

GL After Leave

Professional Development

50 Qs

minecraft

minecraft

KG - Professional Development

44 Qs

2018 International Plumbing Code

2018 International Plumbing Code

Assessment

Quiz

Other

Professional Development

Hard

Created by

Johnny Thulin

Used 21+ times

FREE Resource

49 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

1. A __________ is permitted to discharge to an approved nonpotable water system.

clothes washer

bidet

floor drain

sink

Answer explanation

301.3, Exception

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When installed horizontally, 1-1/4-inch polypropylene pipe and tubing shall be supported at maximum intervals of __________.

32 inches

8 feet

48 inches

10 feet

Answer explanation

Table 308.5

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

1. All of the following are minimum requirements of a water heater installation, except __________.

a valve on the cold water supply to the water heater

a drain valve at the bottom of each tank-type water heater

a means to prevent siphoning of the tank in the event of a negative supply

pressure

a means to provide continuous circulation from the piping systems to the

heater

Answer explanation

501.3, 503.1 and 504.1

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When there is a conflict between the requirements of the code and the manufacturer’s

installation instructions, the __________ requirements apply.

code

more specific

more restrictive

manufacturer’s

Answer explanation

301.7

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

1. When is a common building sewer connecting more than one building to the public sewer allowed?

when the building tenants agree to the shared use of the sewer

when the city sewer system does not extend to the property line

when the common sewer is controlled by a property owners association

when all buildings using the common sewer are located on the same

property

Answer explanation

Sec. 701.3

6.

DROPDOWN QUESTION

1 min • 5 pts

2. Where the wastewater temperature will exceed __________ °F, the drainage piping material must be rated for the highest temperature of the wastewater.

​ (a)  

140
110
120
160

Answer explanation

702.5

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

1. Water closets installed in public and employee restrooms do not require __________ seats.

a. nonabsorbent b. elongated

c. open front d. integral

nonabsorbent

elongated

open front

integral

Answer explanation

425.2 and 425.3

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?