UPIP PMP-Scheduling-Cost-quality

UPIP PMP-Scheduling-Cost-quality

Professional Development

12 Qs

quiz-placeholder

Similar activities

Lean Six Sigma Green Belt

Lean Six Sigma Green Belt

Professional Development

14 Qs

R2H Day One Internship Expectation Review Guidelines

R2H Day One Internship Expectation Review Guidelines

Professional Development

10 Qs

Duration Estimate In Work Program

Duration Estimate In Work Program

Professional Development

10 Qs

International project management

International project management

Professional Development

10 Qs

Yeh PMs akhir karte kya hai!

Yeh PMs akhir karte kya hai!

Professional Development

15 Qs

Project Management Essential 1

Project Management Essential 1

Professional Development

10 Qs

Quiz Lesson 3 - Topic C (Schedule)

Quiz Lesson 3 - Topic C (Schedule)

Professional Development

10 Qs

Project management principles

Project management principles

Professional Development

12 Qs

UPIP PMP-Scheduling-Cost-quality

UPIP PMP-Scheduling-Cost-quality

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Tony Prensa, PMP

Used 4+ times

FREE Resource

12 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Calculate the variance for the following: Pessimistic= 12, Optimistic = 2, Realistic = 5.

5

2.79

5.67

Not enough information

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Task C on the project has an ES of day three, an EF of day seven and an LS of day seven. Which of the following best describes this task?

It has slack (float) of zero days

It is behind schedule

It has slack (float) of four days and duration of five days

It has slack (float) of zero days and duration of four days

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following best describes the critical path slack (float)?

It can be the shortest duration on the project

It can be a positive number or zero

It can be a negative number or zero

It can be a positive number, negative number, or zero

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are a member of a project team that is doing a capital expansion upgrade project. Typically, your projects do not include capital assets. Which of the following documents are most likely to be updated first to reflect the change in project type?

Cost estimates

Cost baseline

Cost management Plan

Issue log

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Project A has an NPV of $150k over three years. Project B has an NPV of $330k over six years. Project C has an NPV of $170k over six years. Which of the following do you select?

Project A

Project B

Project C

Project A and C

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are having a home theater room added to your house. The project should take five days and cost $1,500 per day to complete. After three days, the project is 30% complete and $5,000 has been spent. What is the CPI?

0.45

0.50

0.40

1.00

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Company-wide server upgrades are an example of what type of project cost?

variable indirect

Variable

Fixed

Fixed direct

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?