UPIP PMP-Scheduling-Cost-quality
Authored by Tony Prensa, PMP
Professional Development
Professional Development
Used 5+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
12 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Calculate the variance for the following: Pessimistic= 12, Optimistic = 2, Realistic = 5.
5
2.79
5.67
Not enough information
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Task C on the project has an ES of day three, an EF of day seven and an LS of day seven. Which of the following best describes this task?
It has slack (float) of zero days
It is behind schedule
It has slack (float) of four days and duration of five days
It has slack (float) of zero days and duration of four days
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following best describes the critical path slack (float)?
It can be the shortest duration on the project
It can be a positive number or zero
It can be a negative number or zero
It can be a positive number, negative number, or zero
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are a member of a project team that is doing a capital expansion upgrade project. Typically, your projects do not include capital assets. Which of the following documents are most likely to be updated first to reflect the change in project type?
Cost estimates
Cost baseline
Cost management Plan
Issue log
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Project A has an NPV of $150k over three years. Project B has an NPV of $330k over six years. Project C has an NPV of $170k over six years. Which of the following do you select?
Project A
Project B
Project C
Project A and C
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are having a home theater room added to your house. The project should take five days and cost $1,500 per day to complete. After three days, the project is 30% complete and $5,000 has been spent. What is the CPI?
0.45
0.50
0.40
1.00
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Company-wide server upgrades are an example of what type of project cost?
variable indirect
Variable
Fixed
Fixed direct
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
Military Must-Know-Words 1 - 10 (Quiz 2)
Quiz
•
Professional Development
12 questions
U 9-10 Summit 1 Review
Quiz
•
Professional Development
10 questions
New Hire Orientation
Quiz
•
Professional Development
10 questions
Motorcycle and ATV
Quiz
•
Professional Development
10 questions
Vitamin C 2024
Quiz
•
Professional Development
15 questions
Sports Analytics
Quiz
•
Professional Development
10 questions
Business Writing 4
Quiz
•
Professional Development
12 questions
Cycle 4: Session 8 Review.
Quiz
•
Professional Development
Popular Resources on Wayground
8 questions
Spartan Way - Classroom Responsible
Quiz
•
9th - 12th Grade
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
14 questions
Boundaries & Healthy Relationships
Lesson
•
6th - 8th Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
3 questions
Integrity and Your Health
Lesson
•
6th - 8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
9 questions
FOREST Perception
Lesson
•
KG
20 questions
Main Idea and Details
Quiz
•
5th Grade
Discover more resources for Professional Development
15 questions
LOTE_SPN2 5WEEK3 Day 2 Itinerary
Quiz
•
Professional Development
6 questions
Copy of G5_U6_L5_22-23
Lesson
•
KG - Professional Dev...
10 questions
March Quiz
Quiz
•
Professional Development
5 questions
Copy of G5_U6_L8_22-23
Lesson
•
KG - Professional Dev...
10 questions
suffixes FUL OR LESS
Quiz
•
Professional Development