1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Calculate the variance for the following: Pessimistic= 12, Optimistic = 2, Realistic = 5.

5

2.79

5.67

Not enough information

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Task C on the project has an ES of day three, an EF of day seven and an LS of day seven. Which of the following best describes this task?

It has slack (float) of zero days

It is behind schedule

It has slack (float) of four days and duration of five days

It has slack (float) of zero days and duration of four days

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following best describes the critical path slack (float)?

It can be the shortest duration on the project

It can be a positive number or zero

It can be a negative number or zero

It can be a positive number, negative number, or zero

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are a member of a project team that is doing a capital expansion upgrade project. Typically, your projects do not include capital assets. Which of the following documents are most likely to be updated first to reflect the change in project type?

Cost estimates

Cost baseline

Cost management Plan

Issue log

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Project A has an NPV of $150k over three years. Project B has an NPV of $330k over six years. Project C has an NPV of $170k over six years. Which of the following do you select?

Project A

Project B

Project C

Project A and C

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are having a home theater room added to your house. The project should take five days and cost $1,500 per day to complete. After three days, the project is 30% complete and $5,000 has been spent. What is the CPI?

0.45

0.50

0.40

1.00

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Company-wide server upgrades are an example of what type of project cost?

variable indirect

Variable

Fixed

Fixed direct

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development