RMP - 5. RISK RESPONSE

RMP - 5. RISK RESPONSE

1st Grade

21 Qs

quiz-placeholder

Similar activities

PMI SH - Evaluate and Deliver Project Benefits and Value

PMI SH - Evaluate and Deliver Project Benefits and Value

1st Grade

18 Qs

ACP dari Bit.ly

ACP dari Bit.ly

1st Grade

20 Qs

Quality

Quality

1st Grade

16 Qs

ISO 27001 Quizz Section 456 (Day#2B)

ISO 27001 Quizz Section 456 (Day#2B)

1st Grade - University

20 Qs

Domain#2 Value Driven Delivery Mike Griffith

Domain#2 Value Driven Delivery Mike Griffith

1st Grade

20 Qs

Domain#7 Continuous Improvement Mike Griffith

Domain#7 Continuous Improvement Mike Griffith

1st Grade

20 Qs

RMP - 4. RISK ANALYSIS

RMP - 4. RISK ANALYSIS

1st Grade

23 Qs

PMI SH - Negotiate Project Agreements

PMI SH - Negotiate Project Agreements

1st Grade

16 Qs

RMP - 5. RISK RESPONSE

RMP - 5. RISK RESPONSE

Assessment

Quiz

Professional Development

1st Grade

Easy

Created by

sudiyuwono wowo

Used 4+ times

FREE Resource

21 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request. The project sponsor rejects the change request. What should the project manager have done differently?
Performed an analysis to affirm the request is valid before submitting.
Executed the risk strategy response and recorded it in the risk register.
Contacted the other stakeholders so they know the request is in process.
Informed the client and the project sponsor that the request is being submitted.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You identified a risk in your project that is difficult for you to manage, therefore, you give the responsibility to manage this risk to an outside source. What kind of risk response strategy is this?
Accept.
Exploit.
Avoid.
D. Transfer.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project lost 10 productive days due to bad weather. In order to make up for the lost time, the project management team calls for an emergency meeting and decides to apply fast-tracking as a schedule compression technique. This is an example of:
Workaround.
Risk escalation.
Risk mitigation.
Risk avoidance.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project team is working on a risk response strategy by evaluating every risk and coming up with suitable response strategies. However, one particular risk with a negative impact cannot be avoided or mitigated. Furthermore, there is no way to transfer risk by outsourcing or buying insurance. What is the best the team can do about the risk?
Accept the risk.
Share the risk by allocating ownership to a third party.
Revisit the risk Response Strategy.
Treat it as a secondary risk and update it in the Risk Register.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?
Change the risk response strategy.
Conduct a cost-benefit analysis.
Highlight this situation to the project manager.
Analyze the situation and meet with the risk owner.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

John is the project manager of the ABC Project. He and the project team have identified a risk event in the project with a high probability of occurrence, and the risk event has a high-cost impact on the project. John discusses the risk event with Sara, the primary project customer, and she decides that the requirement surrounding the risk event should be removed from the project. The removal of the requirements does affect the project scope, but it can release the project from the high-risk exposure. What risk response has been enacted in this project?
Mitigation.
Transference.
Avoidance.
Acceptance.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are a risk manager for a big construction project. You and the project team successfully identified and analyzed risks. As a part of the risk response process, what is the purpose of mitigating negative risks?
To reduce the probability of risk occurrence, and reduce the impact.
To increase the probability of a risk occurrence, and reduce the impact.
Transfer the probability of a risk occurrence to a third party, and reduce the impact.
To accept the probability of a risk occurrence and reduce the impact.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?