Quiziz Week 2 Day 4

Quiziz Week 2 Day 4

Professional Development

20 Qs

quiz-placeholder

Similar activities

Quiziz Week 3 Day 2

Quiziz Week 3 Day 2

Professional Development

20 Qs

November W III - II

November W III - II

Professional Development

15 Qs

PMP Quiz Project Stakeholder, Integration, Quality

PMP Quiz Project Stakeholder, Integration, Quality

Professional Development

20 Qs

PMP Exam Preparation Mocktest Integration & Stakeholder (25)

PMP Exam Preparation Mocktest Integration & Stakeholder (25)

Professional Development

25 Qs

Project Integration Test

Project Integration Test

Professional Development

15 Qs

Project Management

Project Management

Professional Development

20 Qs

SG20_Test_S8_CH10&13 Communications & Stakeholder

SG20_Test_S8_CH10&13 Communications & Stakeholder

Professional Development

15 Qs

10. Communication & SH

10. Communication & SH

Professional Development

16 Qs

Quiziz Week 2 Day 4

Quiziz Week 2 Day 4

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Dedy Hartanto

Used 2+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager is about to close a project that missed its performance goals. The project manager is gathering the information that is most pertinent to the project’s poor performance. Which of the following is least likely to help in this task?
Risk report
Project team assignments
Assumption log
Change log

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager has taken over a project early in its execution. The company has a policy that specifies the minimum frequency for conducting risk audits on all projects. What should the project manager do to determine the timing of the risk audits for this particular project?
Look in the project management plan
Check the applicable policy in the organizational process assets
Review the risk register for risk audit information
Use discretion to determine when and if a risk audit is needed

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

As part of project planning, a team member is using the resource breakdown structure and RACI chart. What process would benefit the most from these techniques?
Control Costs
Plan Resource Management
Identify Stakeholders
Manage Project Knowledge

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

While updating the monthly cost reports, you have discovered that an error was made in the original funding request. As a result, the budgeted amount approved was higher than the project actually needed. You understand that the cost baseline should be updated. What should you do next?
Issue a change request
Update the cost baseline
Prepare cost estimates
Issue work performance reports

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The project manager and members of the project team start an Ishikawa diagram for a quality issue. Someone writes down 'source material' as a potential cause. What is the next best action for the project manager?
Instruct the production department to stop using the source material
Request the team to brainstorm other possible causes of the quality issue
Suggest switching from the Ishikawa diagram to the cause-and-effect diagram
Direct the team to focus on issues from the customer perspective of quality

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project team is testing a prototype of a new drone. Something goes wrong and causes the drone to crash and explode.Fortunately, this risk has been identified early in the project, and the contingency reserves allocated for the risk are sufficient to construct another prototype. What should the project manager do next?
Submit a change request to update the cost baseline
Use the contingency reserves to construct a new prototype
Submit a change request to tap into the contingency reserves
Terminate the project since the only prototype was destroyed

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project sponsor asks the project manager how well the project is doing in terms of budget. The project manager reviews work performance data and informs the sponsor that the project is doing well. What is wrong with the project manager's approach?
Nothing is wrong with the project manager's approach.
The project manager should have reviewed work performance information.
The project manager should have reviewed the cost baseline.
The project manager should have consulted the accounting department.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?