Programming and Planning Quiz

Programming and Planning Quiz

Professional Development

10 Qs

quiz-placeholder

Similar activities

Intro to the 6S Pyramid

Intro to the 6S Pyramid

Professional Development

10 Qs

Office T&T

Office T&T

Professional Development

12 Qs

learning about glady's

learning about glady's

KG - Professional Development

12 Qs

Nuts and Bolts Review

Nuts and Bolts Review

Professional Development

11 Qs

online exam

online exam

Professional Development

10 Qs

3-D Printing Day-4

3-D Printing Day-4

Professional Development

10 Qs

ASP-SM-Art

ASP-SM-Art

Professional Development

8 Qs

Programming and Planning Quiz

Programming and Planning Quiz

Assessment

Quiz

Professional Development

Professional Development

Practice Problem

Hard

Created by

CBE QS

Used 1+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

What is the Total Float?

Free float is the amount of time an activity can be delayed before affecting the end date

Total float is the amount of time an activity can be delayed before affected a subsequent activity

Free float is the amount of time an activity can be delayed before affected a subsequent activity

Total float is the amount of time an activity can be delayed before affecting the end date

2.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

What is the Critical Path?

The shortest duration through the activity network, which in turn defines the longest time the project can be completed in. There is float on the CP

The longest duration through the activity network, which in turn defines the shortest time the project can be completed in. There is no float on the CP

The shortest duration through the activity network, which in turn defines the longest time the project can be completed in. There is no float on the CP

The longest duration through the activity network, which in turn defines the shortest time the project can be completed in. There is float on the CP

3.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

Explain Earned Value

Looks at the value earned by the project by a point in time. Two key metrics are the Schedule Performance Index and the Cost Performance Index (SPI and CPI)

Looks at the value spent by the project by a point in time. Two key metrics are the Schedule Performance Index and the Cost Performance Index (SPI and CPI)

Looks at the value spent by the project by a point in time. Two key metrics are the Schedule Efficiency Index and the Cost Performance Index (SEI and CPI)

Looks at the value earned by the project by a point in time. Two key metrics are the Schedule Efficiency Index and the Cost Performance Index (SEI and CPI)

4.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

Explain the SPI calculation

Earned Value divided by Planned Value

Planned Value divided by Earned Value

Actual Cost divided by Earned Value

Earned Value divided by Actual Cost

5.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

Explain the CPI calculation

Actual Cost divided by Earned Value

Earned Value divided by Planned Value

Planned Value divided by Earned Value

Earned Value divided by Actual Cost

6.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

What kinds of Delay analysis are you aware of?

Time impact analysis, Time Slice Window, and Retrospective analysis

Proactive analysis and Retrospective analysis

Time impact analysis, Time Slice Window, Collapsed As Built, and Time Slice Analysis

Time impact analysis, Time Slice Window, and Collapsed As Built

7.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

How do you create a programme?

Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify assumptions

Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify risks

Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify constraints

Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify opportunities

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?