Programming and Planning Quiz
Quiz
•
Professional Development
•
Professional Development
•
Practice Problem
•
Hard
CBE QS
Used 1+ times
FREE Resource
Enhance your content in a minute
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
What is the Total Float?
Free float is the amount of time an activity can be delayed before affecting the end date
Total float is the amount of time an activity can be delayed before affected a subsequent activity
Free float is the amount of time an activity can be delayed before affected a subsequent activity
Total float is the amount of time an activity can be delayed before affecting the end date
2.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
What is the Critical Path?
The shortest duration through the activity network, which in turn defines the longest time the project can be completed in. There is float on the CP
The longest duration through the activity network, which in turn defines the shortest time the project can be completed in. There is no float on the CP
The shortest duration through the activity network, which in turn defines the longest time the project can be completed in. There is no float on the CP
The longest duration through the activity network, which in turn defines the shortest time the project can be completed in. There is float on the CP
3.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
Explain Earned Value
Looks at the value earned by the project by a point in time. Two key metrics are the Schedule Performance Index and the Cost Performance Index (SPI and CPI)
Looks at the value spent by the project by a point in time. Two key metrics are the Schedule Performance Index and the Cost Performance Index (SPI and CPI)
Looks at the value spent by the project by a point in time. Two key metrics are the Schedule Efficiency Index and the Cost Performance Index (SEI and CPI)
Looks at the value earned by the project by a point in time. Two key metrics are the Schedule Efficiency Index and the Cost Performance Index (SEI and CPI)
4.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
Explain the SPI calculation
Earned Value divided by Planned Value
Planned Value divided by Earned Value
Actual Cost divided by Earned Value
Earned Value divided by Actual Cost
5.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
Explain the CPI calculation
Actual Cost divided by Earned Value
Earned Value divided by Planned Value
Planned Value divided by Earned Value
Earned Value divided by Actual Cost
6.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
What kinds of Delay analysis are you aware of?
Time impact analysis, Time Slice Window, and Retrospective analysis
Proactive analysis and Retrospective analysis
Time impact analysis, Time Slice Window, Collapsed As Built, and Time Slice Analysis
Time impact analysis, Time Slice Window, and Collapsed As Built
7.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
How do you create a programme?
Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify assumptions
Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify risks
Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify constraints
Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify opportunities
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
12 questions
Te Rito - Cyber Security
Quiz
•
Professional Development
10 questions
LEARNER AND THE LEARNING ENVIRONMENT
Quiz
•
Professional Development
10 questions
ICWLS 2023 Quiz
Quiz
•
Professional Development
15 questions
Competency Based Education
Quiz
•
Professional Development
15 questions
FOL. UF1 AEA2. COWORKING.
Quiz
•
Professional Development
15 questions
2PM Pub Quiz Sample Questions
Quiz
•
Professional Development
10 questions
Managing Projects
Quiz
•
Professional Development
13 questions
Objetivos generales de etapa
Quiz
•
Professional Development
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
54 questions
Analyzing Line Graphs & Tables
Quiz
•
4th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
Discover more resources for Professional Development
20 questions
Black History Month Trivia Game #1
Quiz
•
Professional Development
100 questions
Screening Test Customer Service
Quiz
•
Professional Development
20 questions
90s Cartoons
Quiz
•
Professional Development
10 questions
Reading a ruler in Inches
Quiz
•
4th Grade - Professio...
16 questions
Parallel, Perpendicular, and Intersecting Lines
Quiz
•
KG - Professional Dev...
12 questions
Valentines Day Trivia
Quiz
•
Professional Development
