Programming and Planning Quiz

Quiz
•
Professional Development
•
Professional Development
•
Hard
CBE QS
Used 1+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
What is the Total Float?
Free float is the amount of time an activity can be delayed before affecting the end date
Total float is the amount of time an activity can be delayed before affected a subsequent activity
Free float is the amount of time an activity can be delayed before affected a subsequent activity
Total float is the amount of time an activity can be delayed before affecting the end date
2.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
What is the Critical Path?
The shortest duration through the activity network, which in turn defines the longest time the project can be completed in. There is float on the CP
The longest duration through the activity network, which in turn defines the shortest time the project can be completed in. There is no float on the CP
The shortest duration through the activity network, which in turn defines the longest time the project can be completed in. There is no float on the CP
The longest duration through the activity network, which in turn defines the shortest time the project can be completed in. There is float on the CP
3.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
Explain Earned Value
Looks at the value earned by the project by a point in time. Two key metrics are the Schedule Performance Index and the Cost Performance Index (SPI and CPI)
Looks at the value spent by the project by a point in time. Two key metrics are the Schedule Performance Index and the Cost Performance Index (SPI and CPI)
Looks at the value spent by the project by a point in time. Two key metrics are the Schedule Efficiency Index and the Cost Performance Index (SEI and CPI)
Looks at the value earned by the project by a point in time. Two key metrics are the Schedule Efficiency Index and the Cost Performance Index (SEI and CPI)
4.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
Explain the SPI calculation
Earned Value divided by Planned Value
Planned Value divided by Earned Value
Actual Cost divided by Earned Value
Earned Value divided by Actual Cost
5.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
Explain the CPI calculation
Actual Cost divided by Earned Value
Earned Value divided by Planned Value
Planned Value divided by Earned Value
Earned Value divided by Actual Cost
6.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
What kinds of Delay analysis are you aware of?
Time impact analysis, Time Slice Window, and Retrospective analysis
Proactive analysis and Retrospective analysis
Time impact analysis, Time Slice Window, Collapsed As Built, and Time Slice Analysis
Time impact analysis, Time Slice Window, and Collapsed As Built
7.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
How do you create a programme?
Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify assumptions
Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify risks
Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify constraints
Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify opportunities
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
Workshop Caribbean

Quiz
•
Professional Development
12 questions
BPS Gratifikasi dan WBS Corpu

Quiz
•
Professional Development
10 questions
Project Scope Management

Quiz
•
Professional Development
10 questions
Pop Quiz week 2

Quiz
•
Professional Development
13 questions
Customer Success Chapter 2

Quiz
•
Professional Development
10 questions
Marketing 3

Quiz
•
Professional Development
10 questions
Harkodia Quiz

Quiz
•
Professional Development
5 questions
Initiating Phase Part 1 Quiz

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
9/11 Experience and Reflections

Interactive video
•
10th - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
9 questions
Tips & Tricks

Lesson
•
6th - 8th Grade