Programming and Planning Quiz

Programming and Planning Quiz

Professional Development

10 Qs

quiz-placeholder

Similar activities

Evaluasi CP-TP-ATP

Evaluasi CP-TP-ATP

Professional Development

12 Qs

Modul Ajar - ATP - CP

Modul Ajar - ATP - CP

Professional Development

10 Qs

Quiz 5 FKI Semester 1 SLAPGU 2021

Quiz 5 FKI Semester 1 SLAPGU 2021

Professional Development

12 Qs

Metric Creation

Metric Creation

Professional Development

10 Qs

Introduction to Project Management for MT Nestle

Introduction to Project Management for MT Nestle

Professional Development

15 Qs

CGEIT Domain 2 MCQ (Additional)

CGEIT Domain 2 MCQ (Additional)

Professional Development

10 Qs

HR Metrics and Analytics Quiz

HR Metrics and Analytics Quiz

Professional Development

10 Qs

Kuis Gratifikasi dan WBS 2023

Kuis Gratifikasi dan WBS 2023

Professional Development

10 Qs

Programming and Planning Quiz

Programming and Planning Quiz

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

CBE QS

Used 1+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

What is the Total Float?

Free float is the amount of time an activity can be delayed before affecting the end date

Total float is the amount of time an activity can be delayed before affected a subsequent activity

Free float is the amount of time an activity can be delayed before affected a subsequent activity

Total float is the amount of time an activity can be delayed before affecting the end date

2.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

What is the Critical Path?

The shortest duration through the activity network, which in turn defines the longest time the project can be completed in. There is float on the CP

The longest duration through the activity network, which in turn defines the shortest time the project can be completed in. There is no float on the CP

The shortest duration through the activity network, which in turn defines the longest time the project can be completed in. There is no float on the CP

The longest duration through the activity network, which in turn defines the shortest time the project can be completed in. There is float on the CP

3.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

Explain Earned Value

Looks at the value earned by the project by a point in time. Two key metrics are the Schedule Performance Index and the Cost Performance Index (SPI and CPI)

Looks at the value spent by the project by a point in time. Two key metrics are the Schedule Performance Index and the Cost Performance Index (SPI and CPI)

Looks at the value spent by the project by a point in time. Two key metrics are the Schedule Efficiency Index and the Cost Performance Index (SEI and CPI)

Looks at the value earned by the project by a point in time. Two key metrics are the Schedule Efficiency Index and the Cost Performance Index (SEI and CPI)

4.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

Explain the SPI calculation

Earned Value divided by Planned Value

Planned Value divided by Earned Value

Actual Cost divided by Earned Value

Earned Value divided by Actual Cost

5.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

Explain the CPI calculation

Actual Cost divided by Earned Value

Earned Value divided by Planned Value

Planned Value divided by Earned Value

Earned Value divided by Actual Cost

6.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

What kinds of Delay analysis are you aware of?

Time impact analysis, Time Slice Window, and Retrospective analysis

Proactive analysis and Retrospective analysis

Time impact analysis, Time Slice Window, Collapsed As Built, and Time Slice Analysis

Time impact analysis, Time Slice Window, and Collapsed As Built

7.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

How do you create a programme?

Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify assumptions

Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify risks

Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify constraints

Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify opportunities

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?