What is the Total Float?
Programming and Planning Quiz

Quiz
•
Professional Development
•
Professional Development
•
Hard
CBE QS
Used 1+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
Free float is the amount of time an activity can be delayed before affecting the end date
Total float is the amount of time an activity can be delayed before affected a subsequent activity
Free float is the amount of time an activity can be delayed before affected a subsequent activity
Total float is the amount of time an activity can be delayed before affecting the end date
2.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
What is the Critical Path?
The shortest duration through the activity network, which in turn defines the longest time the project can be completed in. There is float on the CP
The longest duration through the activity network, which in turn defines the shortest time the project can be completed in. There is no float on the CP
The shortest duration through the activity network, which in turn defines the longest time the project can be completed in. There is no float on the CP
The longest duration through the activity network, which in turn defines the shortest time the project can be completed in. There is float on the CP
3.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
Explain Earned Value
Looks at the value earned by the project by a point in time. Two key metrics are the Schedule Performance Index and the Cost Performance Index (SPI and CPI)
Looks at the value spent by the project by a point in time. Two key metrics are the Schedule Performance Index and the Cost Performance Index (SPI and CPI)
Looks at the value spent by the project by a point in time. Two key metrics are the Schedule Efficiency Index and the Cost Performance Index (SEI and CPI)
Looks at the value earned by the project by a point in time. Two key metrics are the Schedule Efficiency Index and the Cost Performance Index (SEI and CPI)
4.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
Explain the SPI calculation
Earned Value divided by Planned Value
Planned Value divided by Earned Value
Actual Cost divided by Earned Value
Earned Value divided by Actual Cost
5.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
Explain the CPI calculation
Actual Cost divided by Earned Value
Earned Value divided by Planned Value
Planned Value divided by Earned Value
Earned Value divided by Actual Cost
6.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
What kinds of Delay analysis are you aware of?
Time impact analysis, Time Slice Window, and Retrospective analysis
Proactive analysis and Retrospective analysis
Time impact analysis, Time Slice Window, Collapsed As Built, and Time Slice Analysis
Time impact analysis, Time Slice Window, and Collapsed As Built
7.
MULTIPLE CHOICE QUESTION
1 min • 20 pts
How do you create a programme?
Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify assumptions
Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify risks
Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify constraints
Scope of programme, WBS, Plug in constraints, Fill in what I know, Consult wider team, Add risk and opportunity, Run analysis of scenarios, Identify the CP, Identify opportunities
Create a free account and access millions of resources
Similar Resources on Quizizz
10 questions
Practice Exam 2 Part 2

Quiz
•
Professional Development
7 questions
Integrity Talks

Quiz
•
Professional Development
10 questions
Evaluasi Sosialisasi WBS

Quiz
•
Professional Development
10 questions
Capaian Pembelajaran

Quiz
•
Professional Development
9 questions
Gestion de projet WEB

Quiz
•
Professional Development
7 questions
Scope Management Process - Assignment

Quiz
•
Professional Development
6 questions
Validate and Control Scope - Assignment

Quiz
•
Professional Development
10 questions
IT Project Management - IT Project Planning

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade