All-in-one CAPM/PMP: Chapter 5 - Scope

All-in-one CAPM/PMP: Chapter 5 - Scope

Professional Development

20 Qs

quiz-placeholder

Similar activities

Project Management - 2nd Day

Project Management - 2nd Day

Professional Development

17 Qs

Future Heroes

Future Heroes

Professional Development

18 Qs

Project Integration Management

Project Integration Management

Professional Development

15 Qs

Project Management Basics Quiz

Project Management Basics Quiz

Professional Development

20 Qs

Project Planning and Scheduling Revision Ch2

Project Planning and Scheduling Revision Ch2

Professional Development

23 Qs

PMP Questions 6th Edition Quiz 2

PMP Questions 6th Edition Quiz 2

Professional Development

20 Qs

PMP Questions 6th Edition Quiz 4

PMP Questions 6th Edition Quiz 4

Professional Development

20 Qs

Quiziz Week 2 Day 3

Quiziz Week 2 Day 3

Professional Development

20 Qs

All-in-one CAPM/PMP: Chapter 5 - Scope

All-in-one CAPM/PMP: Chapter 5 - Scope

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Patrick Pepin

Used 3+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Henry is the project manager for his organization, and management has asked him to create a project management plan to define the scope statement.

Which project management plan guides the creation of the detailed project scope statement?

  1. The charter

  1. The project management plan

  1. The project scope plan

  1. The project scope management plan

Answer explanation

The project scope management plan defines the creation of the detailed project scope statement. A, the charter, does include the preliminary project scope statement, but not the detailed one defined by the project scope management plan. B, the project management plan, is a parent of the project scope management plan. C is not a valid plan, so this answer is incorrect.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are the project manager of the GYH Project. This project will create a walking bridge across the Tennessee River. You've been asked to start the process of creating the project scope statement and you need to gather the elements for this process.

Which one of the following is not needed to define the project scope?

  1. A project charter

  1. Organizational process assets

  1. A risk management plan

  1. Requirements documentation

Answer explanation

At this point, you won't need, or likely have, the risk management plan to define the project scope. A, B, and D are incorrect statements because you'll need the project charter, organizational process assets, and the requirements documentation to define the project scope.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are the project manager of the BHY Project. Your project customer has demanded that the project be completed by December 1.

December 1 is an example of which one of the following?

  1. A constraint

  1. An assumption

  1. A project boundary

  1. Product acceptance criteria

Answer explanation

This is an example of a project constraint. B is incorrect because this is a requirement, not an assumption. C is incorrect because project boundaries define things that are within and outside of the project scope. D is incorrect because product acceptance criteria are an example of functions and features the product must have to be acceptable to the customer.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Marty is the project manager of the Highway 41 Bridge Project and he's working with his project team members to create the WBS. Marty shows the team how to break down the project scope into the WBS components, but the team doesn't understand how far down the breakdown should occur.

Marty should call the lowest-level item in a WBS what?

  1. A deliverable

  1. A work package

  1. An activity

  1. A leaf object

Answer explanation

The smallest item in the WBS is called the work package. A, deliverables, may be true to a degree, but B is a more precise answer. C is incorrect because activities are found in the activity list. D is an invalid WBS term

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are working with the project team to create the WBS. Some elements in the WBS can't be broken down yet. You and the team elect to break down these items later in the project as more details become available.

This approach to creating the WBS is also known as what?

  1. Decomposition

  1. The 8/80 Rule

  1. Parkinson's Law

  1. Rolling wave planning

Answer explanation

I his is a clear example of rolling wave planning. A is incorrect because decomposition describes the breakdown process of the project scope. B is incorrect because the 8/80 Rule defines the guideline for the amount of labor that should be related to each work package in the WBS. C, Parkinson's Law, is not relevant to this question. Parkinson's Law states that work will expand to fulfill the amount of time allotted to it.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are the project manager for your organization and you're creating the WBS for a new project. In your WBS, you're numbering each level of the components following a project sequenced numbering order. lour WBS is numbered in a hierarchical fashion for easy identification and reference.

This numbering scheme is called what?

  1. Code of accounts

  1. Chart of accounts

  1. WBS template

  1. WBS dictionary

Answer explanation

The WBS numbering scheme is called the code of accounts. B, chart of accounts, is a project management accounting system. C, a WBS template, can be a prepopulated WBS or a WBS from a previous project used to define the current project's WBS. D is incorrect because the WBS dictionary defines the attributes of each WBS element.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You'll use the scope management plan to define the project scope statement. You'll also use this plan to build the scope baseline.

Which two items are parts of the scope baseline for the project?

  1. The project scope management plan and project charter

  1. The project scope management plan and the WBS

  1. The WBS and WBS dictionary

  1. Time and cost baselines

Answer explanation

The WBS and WBS dictionary are two of the three components of the scope baseline. The approved detailed project scope statement is the third portion of the scope baseline. A, B, and D are all incorrect because they do not accurately define the scope baseline.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?