Contract Changes Quiz
Quiz
•
Professional Development
•
University
•
Practice Problem
•
Easy
Eileen Pesantes
Used 9+ times
FREE Resource
Enhance your content in a minute
27 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is required for a Construction Change Directive to be issued?
Agreement by the Owner and Architect only
Agreement among the Owner, Contractor, and Architect
Approval by the Contractor alone
Approval by owner only
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Under what conditions should changes in the Work be performed as stated in AIA article §7.1.3?
Only with the approval of the Architect
Under applicable provisions of the Contract Documents, unless otherwise provided in the Change Order, Construction Change Directive or order for a minor change in the Work
At the discretion of the Contractor
Without any written instructions
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does a Change Order require according to §7.2.1?
A written instrument prepared by the Contractor
A verbal agreement between the Owner and Architect
A written instrument prepared by the Architect and signed by the Owner, Contractor, and Architect
A public announcement
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the one question to answer to determine if a claim/change order is actually necessary?
Was the work completed on time?
Was there a change from the original project scope?
Was the project budget exceeded?
Was the quality of work up to standards?
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Who initiates a Change Order?
Owner
Designer
Contractor
Local Code Enforcement Agency
All can initiate a change order
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Contract changes mainly occur because of which of the following reasons?
Change in government regulations
Change in owner requirements
Successful completion of project phases
Reduction in project scope
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is NOT a reason for contract changes?
Omissions, errors or design features that cannot be built as designed
Non-compliance with code or regulations
Change in owner requirements
Contractor or sub need to redo work due to their fault
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
22 questions
Make sentences (STEM sentence)
Quiz
•
9th Grade - Professio...
22 questions
Art and craft
Quiz
•
10th Grade - Professi...
22 questions
Cashier Hungary Quiz
Quiz
•
University
23 questions
MUSIC AND MOVEMENT Session-I
Quiz
•
11th Grade - Professi...
25 questions
Density on the Conventional Radiograph
Quiz
•
University - Professi...
25 questions
Technology in Teaching and Learning
Quiz
•
University
22 questions
Hydraulics Week 3
Quiz
•
University
22 questions
Oral & Written Communication
Quiz
•
University
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
15 questions
4:3 Model Multiplication of Decimals by Whole Numbers
Quiz
•
5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
The Best Christmas Pageant Ever Chapters 1 & 2
Quiz
•
4th Grade
12 questions
Unit 4 Review Day
Quiz
•
3rd Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade