PMI SH Plan and Manage Budget and Resources

PMI SH Plan and Manage Budget and Resources

1st Grade

14 Qs

quiz-placeholder

Similar activities

RMP - 6. MONITOR & CLOSE RISK

RMP - 6. MONITOR & CLOSE RISK

1st Grade

14 Qs

Pre-Test CAPM

Pre-Test CAPM

1st Grade

16 Qs

09. Resource Management

09. Resource Management

1st - 3rd Grade

12 Qs

PMI-SH Plan and Manage Quality of Products/deliverables

PMI-SH Plan and Manage Quality of Products/deliverables

1st Grade

13 Qs

PM Quiz

PM Quiz

1st - 10th Grade

10 Qs

04. Integration Management

04. Integration Management

1st Grade

12 Qs

PMP Quiz -01

PMP Quiz -01

1st - 5th Grade

10 Qs

PMI SH - Evaluate and Deliver Project Benefits and Value

PMI SH - Evaluate and Deliver Project Benefits and Value

1st Grade

18 Qs

PMI SH Plan and Manage Budget and Resources

PMI SH Plan and Manage Budget and Resources

Assessment

Quiz

Professional Development

1st Grade

Hard

Created by

sudiyuwono wowo

FREE Resource

14 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt


Question

A project manager is developing a project budget. After estimating the cost of each activity, the manager adds a contingency reserve by increasing the estimated cost of all activities by the same percentage.

However, this resulted in the total cost exceeding the allocated budget even before adding the management reserve. 

What should the project manager do?

Request additional budget to ensure that all cost estimations are appropriately funded.

Reduce the percentage increase to reduce the total cost of the project.

Recalculate the contingency reserve based on identified risks and response strategies.

Allocate a portion of the contingency reserve to the management reserve.

Answer explanation

Increasing the estimated cost of all project activities by the same percentage is not a sensible way to estimate a contingency reserve. Contingency reserves are typically calculated based on identified risks, not directly on individual activity costs. The project manager should recalculate the contingency reserve to ensure that it is accurate and appropriately calculated.

The other answer choices are incorrect. 

Requesting an additional budget may not be necessary or feasible. The project manager should first attempt to optimize the contingency reserve based on identified risks.

Reducing the percentage increase without justification may restrict the ability to manage risks and could put the project in jeopardy. 

Management and contingency reserves serve different purposes. Allocating a portion of the contingency reserve to the management reserve is not appropriate and may cause serious issues in the future. 

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager planning a strategic predictive project has suddenly fallen ill. The project baseline must be submitted to the customer within 3 days, and the project management office (PMO) director must find someone to finish the planning. The choices are:

Project manager A: highly experienced in Scrum projects only, available immediately for 2 days only

Project manager B: moderately experienced mainly in construction projects, available the next day for 1 week

Which project manager should the PMO director choose and on what basis?

A is available immediately and has more experience to plan quickly and correctly.

B better understands the complexities of predictive planning and has use of a network of subject matter experts (SMEs).

A is more up to date and conversant with the latest project planning trends and methodologies.

B will be available to work for a longer period in case the submission deadline is missed.

Answer explanation

The more complex estimation work in predictive projects often relies on expert input. Access to SMEs as well as predictive mindset and experience would be critical to completing the planning baseline.

There is no point in selecting a project manager just because he / she is available

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager in a cross-functional organization needs to inform the department manager of the number and type of resources required, and the length of time they will be needed. What should the project manager use to present this resource information?

Resource assignments

Resource histogram

Responsibility assignment matrix (RAM)

Project organization chart

Answer explanation

A resource histogram, by definition defines resource requirements over time.

Resource assignments take place once the need for resources has been determined and available resources have been identified.

The Project organization chart and Responsibility assignment matrix will not identify the need for resources nor for what duration they are needed.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project execution phase overlaps with a holiday in the country where the majority of team members are based. This phase is critical, and all team members are required to work through the holiday. This negatively impacts team morale.

What should the project manager have done to avoid this?

Requested help from other teams based in other countries

Postponed project activities

Prepared the stakeholder engagement plan

Better developed the resource management plan

Answer explanation

The resource management plan takes into consideration factors that affect resource availability, including normally observed non-working days.

Requested help: Transitioning project work is a reactive step and not a practical solution in most cases.

Postponing activities further delays critical work and is therefore not an option

The stakeholder engagement plan doesn't address the issue of resource availability working on the project.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt


Question

A project manager learns that a functional manager is assigning a two-week task in another project to a team member. Loss of this resource for two weeks will jeopardize the project schedule.

What should the project manager do?

Review the resource management plan to determine how to negotiate with the functional manager.

Submit a change request to the change control board (CCB) to obtain a replacement resource from another department.

Meet with the project sponsor to discuss the priority levels of the two projects.

D.Assign another team member to perform the work of the team member who will be missing for two weeks.

Answer explanation

The project manager should review the resource management plan to determine how to negotiate with the functional manager. The resource management plan is used to help determine how resources are categorized, allocated, managed, and released. This will provide guidance as to how the project manager can negotiate with the resource's reporting manager.

The other answer choices are incorrect. CCB reviews and approves all project change requests, not resource management; meeting the project sponsor is an escalation that could be avoided; assigning another team member would have cost. 

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The sponsor notified the product owner that the budget was approved for a project. However, any additional investment for the project would have to wait until the next fiscal year.

The product owner is concerned that this will hold up the project.

What should the product owner do?

Track the budget based on the release plan and show the value to the business.

Explain that the project is just starting and the budget will need to be adjusted.

Track the budget based on each sprint and remove nice-to-have deliverables.

Ensure that the project manager monitors every invoice from the project.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A new project has high uncertainty in the cost required for completion. What approach should the project manager use to determine the expected costs?

Analogous estimating

Statistical techniques estimating

Parametric estimating

Three-point estimating

Answer explanation

Three-point estimating uses the most likely, optimistic, and pessimistic estimates, which improves estimate accuracy for a project with high uncertainty. Analogous estimating uses values from a previous similar project. Since this project has a high level of uncertainty, it can be assumed there is no similar project to compare. Parametric estimating uses a statistical relationship with historical data and is often used in construction. Other statistical techniques are not the best approach for a project with a high level of uncertainty.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?