The service provider and their client agree on about 80% of the scope of a project contract they are working on for the delivery of marketing content. The client has a fixed budget and target completion date and wants to get the most business value from the project as possible by increasing the scope based on a best-effort delivery close to the end of the project. What should the project manager do?
PMI SH - Determine Appropriate Project Methodology/methods and P

Quiz
•
Professional Development
•
1st - 3rd Grade
•
Hard
sudiyuwono wowo
FREE Resource
21 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Create the contract based on the agreed scope and plan addendum changes.
Ensure that a change control process is documented in the contract.
Propose a dynamic scope contract option and add a fixed number of iterations.
Increase the number of resources in the contract to deliver the requirements.
Answer explanation
Solution: C. Propose a dynamic scope contract option and add a fixed number of iterations.
Best-effort changes at the end of a project can be delivered at a fixed cost by specifying a fixed number of increments where additional scope can be prioritized. Strict change control or addendums would risk missing the completion date. Adding resources is not necessary if the scope is on a best-effort basis.
The other answer choices are incorrect.
Creating the contract based on the agreed-upon scope and planning an addendum is not flexible enough to accommodate the client's need to increase the scope of the project.
Adding a change control process to the contract is not enough to address the client's need for a flexible scope.
Increasing the number of resources may not be possible due to fixed budget constraints.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is managing an agile project. The project sponsor asks the project manager whether agile supports entering a fixed-price contract with the customer instead of a time-and-materials contract. The customer needs a fixed-price contract to support their concrete business goals.
What should the project manager's response to the sponsor be?
Inform the customer that agile does not support fixed-price contracts, as it favors customer collaboration over contract negotiation.
Inform the customer that agile supports only time-and-materials contracts, as scope is not fixed in agile.
Agree with the customer to move forward with fixed-price contract, as there is no such restriction in agile.
Influence the customer to use a time-and-materials contract, as the cost overrun of this contract lies with the customer.
Answer explanation
Solution: C. Agree with the customer to move forward with fixed-price contract, as there is no such restriction in agile.
In agile environments, specific sellers may be used to extend the team. This collaborative working relationship can lead to a shared risk procurement model where both the buyer and the seller share in the risk and rewards associated with a project.
Larger projects may use an adaptive approach for some deliverables and a more stable approach for other parts. In these cases, a governing agreement such as a master services agreement (MSA) may be used for the overall engagement, with the adaptive work being placed in an appendix or supplement. This allows changes to occur on the adaptive scope without impacting the overall contract
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project team has been tasked to build a new product. The team builds the demo first and add features to the initial product. This is an example of what technical practice?
Test-Driven Development (TDD)
Continuous Delivery
Behavior-Driven Development
Spikes
Answer explanation
Solution: B. Continuous Delivery
Continous delivery technique allow the team to create a demo and continously make improvements until the product is complete and the client is satisfied.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is leading an agile project. For iterations one through five, the team’s velocity chart displays 18 story points, 30 story points, 22 story points, 23 story points, and 22 story points.
What does this information demonstrate about the team's performance?
The team is not following agile practices properly.
The team's velocity is stabilizing over time.
The team is lagging behind as per the schedule.
The team needs to change their agile methodology.
Answer explanation
Solution: B. The team's velocity is stabilizing over time.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project team lead meets with the project manager before a scheduled kick-off meeting. The team lead is worried that expectations regarding project deliverables might not be realistic.
What should the project manager do?
Review the project business case and the results of the feasibility study.
Facilitate a meeting between the project sponsor and the team lead to discuss the concerns.
Meet with the stakeholders to discuss the concerns and record their conclusions in the stakeholder engagement plan.
Identify the risks and agreed-upon risk responses and modify the risk register accordingly.
Answer explanation
Solution: A. Review the project business case and the results of the feasibility study
To ensure that the deliverables are realistic, the project manager needs to review the feasibility study and then evaluate the results. The objectives of the project will be determined in the business case, along with the feasibility study to determine the validity of the project. This may result in a go/no-do decision to initiate the project.
None of the other choices will ensure this
Meeting with the project sponsor or stakeholders will not be helpful before you know how feasible the project is.
The risk register can be updated after the the validity of the project is determined.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is managing an agile project. A new team member, who has never worked in an agile team, joins the project. The new member asks the project manager to explain why an agile approach is used.
What should the project manager's response be?
To eliminate the risk and increase the predictability and visibility
To deliver value faster and change the scope based on feedback
To reduce the costs and increase the quality of the end deliverables
To eliminate the need for documentation by delivering working products
Answer explanation
Solution: B. To deliver value faster and change the scope based on feedback
Agile doesn't reduce costs due to iterative delivery but will deliver business value by delivering faster what the business needs.
Agile doesn't reduce risk even increasing the positive risk (opportunities) and doesn't exclude documentation.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is managing a project where requirements are fixed and the workflow is planned for the full development lifecycle. Additionally, the customer involvement is at specific milestones and testing happens post-build.
Which methodology should a project manager use for this project?
Agile
Hybrid
Predictive
Continuous Improvement
Answer explanation
Solution: C. Predictive
Project life cycles can range along a continuum from predictive approaches at one end to adaptive or agile approaches at the other. In a predictive life cycle, the project deliverables are defined at the beginning of the project and any changes to the scope are progressively managed. In an adaptive or agile life cycle, the deliverables are developed over multiple iterations where a detailed scope is defined and approved for each iteration when it begins
Create a free account and access millions of resources
Similar Resources on Quizizz
20 questions
Agile PM#1 Quiz

Quiz
•
1st Grade - University
18 questions
PMI SH - Integrate Project Planning Activities

Quiz
•
1st Grade
16 questions
Pre-Test CAPM

Quiz
•
1st Grade
16 questions
RMP - 2. STRATEGY & PLANNING

Quiz
•
1st Grade
21 questions
RMP - 5. RISK RESPONSE

Quiz
•
1st Grade
23 questions
Program Strategy Alignment

Quiz
•
1st Grade
24 questions
RMP - 3. RISK IDENTIFICATION

Quiz
•
1st Grade
18 questions
PMI SH - Plan and Manage Procurement

Quiz
•
1st Grade
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade