
PMI SP Stakeholder Communications Management

Quiz
•
Professional Development
•
Professional Development
•
Medium
PMI Trainer
Used 3+ times
FREE Resource
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
One of your senior stakeholder in the project complained to you and brought to your notice that the project is not useful for the business unit. What do you do next as a project manager?
Review the business case with your senior stakeholder
Escalate the issue to your manager to keep him notified as stakeholder is not showing interest
Escalate the issue to your sponsor and do not communicate to stakeholder further until issue is sorted out
Escalate the issue to the manager of the senior stakeholder to keep him notified as stakeholder is not showing interest
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is NOT a key consideration when developing a schedule approach?
Project scope and objectives
Available resources and constraints
Organisational culture and structure
Communication plan
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
When analyzing major milestones against the Statement of Work (SOW), which of the following should be considered?
Project high level risks and uncertainties
major dependencies in project schedule
high level project constraints
All of the above
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
I cannot finish my day at the job until my colleague comes and starts his shift. which logic is this?
common and basic Simple Finish to Start logic
SS
FF
SF
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Engineer is asking his team members to give the possibilities of the task durations with timelines by considering different use case scenarios. what is he doing?
He is performing Schedule risk analysis
He is collecting inputs for PERT Analysis
He is collecting Best case, worst case and mist likely inputs
All the above
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Critical chain method considers buffers in the schedule
True
False
Never
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is the primary purpose of archiving schedule files?
To free up storage space on the project server
To ensure compliance with data protection regulations
To maintain historical records for future reference
To update the project schedule baseline
Create a free account and access millions of resources
Similar Resources on Wayground
20 questions
PMP Assessment

Quiz
•
Professional Development
20 questions
Pre-Test Project Management [15/04/25]

Quiz
•
Professional Development
20 questions
Project Management Basics Quiz

Quiz
•
Professional Development
15 questions
Stakeholders

Quiz
•
10th Grade - Professi...
15 questions
SG20_Test_S8_CH10&13 Communications & Stakeholder

Quiz
•
Professional Development
25 questions
PMP Exam Preparation Mocktest Integration & Stakeholder (25)

Quiz
•
Professional Development
22 questions
Lesson-4 Lead The Project Team

Quiz
•
Professional Development
20 questions
Quiziz Week 3 Day 2

Quiz
•
Professional Development
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade