Which one of the following should be carried out before any electrical work takes place?
Safe isolation.
Safe insulation.
Safe continuity.
Safe polarity.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which one of the following units should be used to check if a circuit is dead?
Multimeter.
RCD.
Proving.
OHMs.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which one of the following tests should be carried out on insulation?
Polarity.
Resistance.
Impedance.
Continuity.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The floor area covered by a ring final circuit must not exceed
25 m²
50 m²
75 m²
100 m²
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The main protection on a domestic consumer unit is provided by which one of the following?
RCD.
RBC.
MCB.
MCD.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A 9.8 kW shower should be protected by a circuit breaker rated at
35 amp
40 amp
45 amp
50 amp
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which one of the following tests should be carried out to ensure that phase and neutral are not cross connected?
Polarity
Resistance
Impedance
Continuity
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?