Prep-Cast CAPM Domain#3 : Agile Framework/Methodologies

Authored by sudiyuwono wowo

Professional Development

1st Grade

Used 1+ times

Prep-Cast CAPM Domain#3 : Agile Framework/Methodologies
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A new project will require extensive stakeholder involvement and is expected to produce its first deliverable as soon as one month after getting the green light to proceed. The deliverable is anticipated to have a high degree of innovation. The performing organization operates in an industry that has considerable regulatory oversight.

What development approach should the project manager recommend for this project?

Adaptive

Predictive

Hybrid

D

Innovative

2.

MATCH QUESTION

1 min • 1 pt

Match the followingYou are planning a project where requirements cannot be defined upfront. This situation presents various challenges to managing the scope of this project. You know that an agile project management approach may help in addressing some of the challenges.

Match the challenges (on the left) with how they are approached in agile (on the right):

Ongoing discovery and refinement of the

Risk of building a wrong product

Building and reviewing prototypes

Frequent changes in customer priorities

Demonstrating product increments to stak

The inability to define scope upfront

Grooming and reprioritizing the product

Gap between the initial requirements and real requirements

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An agile project has entered its seventh sprint. Two days before the end of the sprint, the customer informs the product owner that they forgot to include one feature in the sprint. A senior manager overhears the conversation and states that including the feature represents scope creep and should not be allowed.

What is the product owner's best course of action?

Work with the customer to prioritize the feature in the product backlog

Request that the customer submit a change request

Instruct the team to develop the feature in the current sprint

Reject the feature as instructed by the senior manager

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You meet with your team to determine the life cycle for your project. After analyzing the best way to define and manage requirements, develop deliverables, handle changes, control risk and cost, and engage key stakeholders, the decision is made to select a hybrid life cycle.

With the project life cycle selected, how often will the key stakeholders be involved?

Continuously

At specific milestones

Regularly

Not involved at all

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The product owner needs to consider multiple factors when adding items to the product backlog of an agile project.

How should this be done?

Consider factors such as new features, risks, and defects

Build the backlog from the work breakdown structure (WBS)

Consult with the sponsor on how to add items to the backlog

Let the team decide on what should be added to the backlog

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager facilitates an iteration retrospective meeting. The team members acknowledge that they were unable to meet the iteration goal. To gain insights into velocity and see what can be improved going forward, the participants analyze the burndown chart of the iteration, trying to correlate working days with the number of story points completed on those days.

Assuming no scope has been added throughout the iteration, during which period was the gap between the plan and story points remaining the largest?

(On the actual exam, you will be requested to click the correct area in the image. But here in the simulator, please select the answer below.)

A

B

C

D

7.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

The latest software released to the customer in the first project phase is full of defects. The customer is angry and demands that the development of the new release, which is planned to be delivered in the second phase, is much more transparent. The customer wants to see the team's results more regularly and without very long development intervals in-between.

Which of the following could the project team introduce in the second phase to better comply with the customer's demand? (Choose four.)

A cadence with regular timeboxes

Regular and frequent retrospectives

Optimization at the level of each individual team member

Test-driven development practices

Incremental delivery using a backlog

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?