60 Question Practice PMP Quiz

60 Question Practice PMP Quiz

Professional Development

60 Qs

quiz-placeholder

Similar activities

AWS Security 01

AWS Security 01

Professional Development

58 Qs

Manajerial 3 P3K

Manajerial 3 P3K

Professional Development

60 Qs

SG20 Baseline Top60 -- The Hardest Questions Ever!

SG20 Baseline Top60 -- The Hardest Questions Ever!

Professional Development

60 Qs

Weekend Quiz W2

Weekend Quiz W2

Professional Development

60 Qs

PRINCE 2 - Sample Paper 1 (60Q)

PRINCE 2 - Sample Paper 1 (60Q)

Professional Development

60 Qs

CompTIA Project+ Practice Tests, Chapter #1 questions #1-59

CompTIA Project+ Practice Tests, Chapter #1 questions #1-59

Professional Development

59 Qs

Quizizz #1

Quizizz #1

Professional Development

60 Qs

PMP Exam 1-60

PMP Exam 1-60

Professional Development

60 Qs

60 Question Practice PMP Quiz

60 Question Practice PMP Quiz

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Michael Myers

FREE Resource

60 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of these is a valid negative risk response?

Exploit

Mitigate

Enhance

Share

Answer explanation

B - Risk mitigation is a valid response to negative risks. [PMBOK 6th edition, Page 443] [Project Risk Management]

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of these is accurate regarding risk management?

Organizations are not likely to perceive risk as a threat to project success.

It has its origins in the uncertainty present in all projects.

The attitudes of individuals and organizations must not be a factor affecting risk management.

It is a passive activity in project management.

Answer explanation

B - Risk management does indeed have its origins in the uncertainty present in all projects. [PMBOK 6th edition, Pages 397-400] [Project Risk Management]

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Anne is the project manager of a project. She has evaluated certain responses from prospective sellers and wants to select a contract model that will transfer risk to the seller. Which of the following should she select in order to achieve this?

Time and Material contract

Fixed price contract

Cost-Plus-Fixed-Fee contract

Cost-Plus-Incentive-Fee contract

Answer explanation

B - A fixed-price contract enables the buyer to transfer risk to the seller. [PMBOK 6th Edition, Page 445, 471] [Project Risk Management]

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Your project sponsor has asked you to present your project’s high-level risk register to him in the next project update meeting. To create your high-level risk register, which of the following processes must be performed?

Plan Risk Management

Perform Qualitative Risk Analysis

Identify Risks

Monitor Risks

Answer explanation

C - A high-level risk register contains the identified risks only. The risk register is created during the Identify Risks process. [PMBOK 6th edition, Page 409] [Project Risk Management]

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of these is an input to the Monitor Risks process?

Risk audits

Change requests

Work performance information

Work Performance Reports

Answer explanation

D - Work Performance Reports are inputs to the Monitor Risks process. [PMBOK 6th edition, Page 453] [Project Risk Management]

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is true about risks?

The risk register documents all the identified risks in detail.

Risk impact should be considered, but probability of occurrence is not important

Risks always have negative impact and not positive.

Risk Response Plan is another name for Risk Management Plan

Answer explanation

A - The risk register contains details of the identified risks. [PMBOK 6th edition, Page 417] [Project Risk Management]

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During which stage of risk planning are risks prioritized based on their relative probability and impact?

Perform Qualitative risk analysis

Identify Risks

Perform Quantitative risk analysis

Plan Risk Responses

Answer explanation

A - Perform Qualitative Risk Analysis assesses the impact and likelihood of identified risks. During this process, the risks are prioritized based on their relative probability and impact. [PMBOK 6th edition, Page 419] [Project Risk Management]

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?