1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Identify the most common purpose of critical path analysis.

To effectively delayer an organization

To determine methods to return to solvency

To improve efficiency of the production process

To safely enter a new international market

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In critical path analysis, what does the term “float” refer to?

The earliest start time of an activity

The latest finish time of an activity

The time an activity can be delayed without delaying the project

The total time required to complete a project

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a network diagram, what does an arrow represent?

A dependency between activities

The duration of an activity

The earliest start time of an activity

The latest finish time of an activity

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Identify the missing labels from the image below:

(a) activity duration, (b) earliest start time, (c) latest finishing time

(a) earliest start time, (b) activity duration, (c) latest finishing time

(a) node number, (b) activity duration, (c) latest finishing time

(a) node number, (b) earliest start time, (c) latest finishing time

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Identify the term used to describe the difference between the earliest start time and the latest finishing time for any given node in a network diagram.

Dummy activity

Duration

Earliest start time

Float

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Identify the statement that best describes a dummy activity in critical path analysis.

A false activity that is planned but unlikely to be needed or completed

A logical dependency between two indirectly linked tasks

A major activity that consumes more than 50% of the project length

A simple activity that can be completed by anyone with the organization

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Identify the part of a critical path diagram used to show tasks/activities in the project.

Arrow heads

Circles

Lines

Numbers

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Microsoft

Continue with Microsoft

or continue with

Facebook

Facebook

Apple

Apple

Others

Others

Already have an account?