Project Mgmt. I Final Review 2 21-22

Project Mgmt. I Final Review 2 21-22

9th - 12th Grade

20 Qs

quiz-placeholder

Similar activities

Pengajian perniagaan

Pengajian perniagaan

12th Grade

15 Qs

Revision Questions Contracts Form 4

Revision Questions Contracts Form 4

8th - 12th Grade

20 Qs

Administrasi Umum

Administrasi Umum

10th Grade

20 Qs

Importance of Human Resource

Importance of Human Resource

10th Grade

20 Qs

Bus Man U2 AOS1

Bus Man U2 AOS1

11th Grade

15 Qs

OCR Business - Influences on a business

OCR Business - Influences on a business

10th - 11th Grade

25 Qs

The Farming Business

The Farming Business

9th Grade

15 Qs

Project Mgmt. I Final Review 2 21-22

Project Mgmt. I Final Review 2 21-22

Assessment

Quiz

Business

9th - 12th Grade

Medium

Created by

Bobbie Jones

Used 5+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager is creating an estimate to set up an office building's electrical system. He has twenty-two years of experience managing similar projects. The client needs the estimate quickly. Which type of estimate is he most likely to provide?

analogous estimating

parametric estimating

reserve analysis

three-point estimating

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Adam's Construction has accepted a contract to build a six-story office building. The company is using a timeline from a two-story building project the company completed in the previous month to develop the schedule for this project. Adam's Construction is using:

analogous estimating.

parametric estimating.

three-point estimating.

reserve analysis.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Chandler is setting up a time schedule for beta testing a new software project. Currently, the company has one computer lab compatible with his new program, and there are three other software programs being tested on that lab's systems. Chandler modifies the timeline to account for sharing the computer systems. He is using which schedule analysis tool?

critical path method

critical chain method

reserve analysis

schedule compression

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Jenna's team is creating a new product. A deliverable for the project consists of building a website for the product. Jenna announces that she will be outsourcing this deliverable. Company A estimated a cost of

$60,000 with completion in 3 months, Company B estimated a cost of $100,000 with completion in 2 months, and Company C estimated a cost of $50,000 with completion in 4 months. Jenna averages the three

proposed costs and determines that she will need to put $70,000 into the project budget for the website deliverable. What cost estimating technique did Jenna use?

cost performance baseline

historical relationships

project funding requirements

vendor bid analysis

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Angela is a project manager for a construction project to build a 5 bedroom, 2-story home. She has fifteen years of experience and needs to give a quick estimate. Which type of estimate is most likely to be used?

analogous estimating.

parametric estimating.

three-point estimating.

reserve analysis.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager has been hired to landscape a new primary school playground. The client has allowed sixteen weeks to complete the project, which will take a total of twelve weeks. The project manager decides to begin the project immediately so that she has extra time for weather delays. What is being used?

analogous estimating.

parametric estimating.

three-point estimating.

reserve analysis.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

In the critical path image, what is the critical path?

B, D, H

A, C, H

F, G

E, D

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?