Cost Estimation Quiz

Cost Estimation Quiz

University

10 Qs

quiz-placeholder

Similar activities

Saber Pro Test - Industrial Engineering (9th Semester)

Saber Pro Test - Industrial Engineering (9th Semester)

University

10 Qs

Recap of Sessions 14 & 15

Recap of Sessions 14 & 15

11th Grade - University

10 Qs

Lesson 3 Signal Conditioning and Conversion

Lesson 3 Signal Conditioning and Conversion

University

15 Qs

TOPIC 1-Materials and Prestressing Applications

TOPIC 1-Materials and Prestressing Applications

University

15 Qs

AWS WORKSHOP QUIZ

AWS WORKSHOP QUIZ

University

15 Qs

Value Engineering

Value Engineering

12th Grade - University

15 Qs

Project Cost Management

Project Cost Management

University

12 Qs

Methods of Estimating Quiz

Methods of Estimating Quiz

University

12 Qs

Cost Estimation Quiz

Cost Estimation Quiz

Assessment

Quiz

Engineering

University

Hard

Created by

SYED CHIK

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is another term for Capital Cost?

Depreciation Cost

Capital Expenditure (CapEx)

Revenue Expenditure

Operating Cost

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which factor is NOT considered in estimating purchased equipment costs?

Equipment capacity

Material of construction

Operator skill level

Time

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the typical cost exponent (n) for the six-tenths rule?

0.5

0.6

1.0

0.8

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What type of diagram is used in a Class 4 'Study Estimate'?

Process and Instrumentation Diagram (P&ID)

Block Flow Diagram (BFD)

Isometric Diagram

Elevation Diagram

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary use of a Plant Cost Index?

Adjusting historical costs for inflation

Calculating revenue

Estimating equipment capacity

Standardizing material quality

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which type of expenses includes freight, insurance, and taxes?

Direct expenses

Installation expenses

Indirect project expenses

Maintenance expense

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the Lang Factor Method, what does FLang represent?

Fixed costs

Lang factor for total plant costs

Labor costs

Freight charges

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?