1-6 Agile Mindset Quiz New

Quiz
•
Professional Development
•
4th Grade
•
Medium
Afghanistan Center
Used 4+ times
FREE Resource
11 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is working on a project nearing completion using a hybrid approach. During the last daily standup, the team identified a risk of not delivering on time because team members have not initiated any of the tasks assigned to them. What should the project manager do in this situation?
Hire additional resources to increase capacity using the contingency budget.
Empower the team to self-organize and make decisions to overcome the delay.
Reassign the remaining tasks to the most experienced team members.
Inform the sponsor about the degraded performance of the team members.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A client wants to create an innovative software for the travel industry using an agile approach. A project manager was assigned to work on the details and estimates as requested by the client. What should the project manager do before sending the information to the client?
Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.
Sequence the tasks with estimates and add standard risk reserves to use for software development.
Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.
Work with the team to understand their views and add the appropriate dependencies and risks.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project to implement a new online landing platform has started. After the first sprint, the project sponsor requested a change. What should the project manager do next?
Escalate the change request to the sponsor.
Inform the stakeholders of the change.
Facilitate the update of the product backlog.
Validate the work completed.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is working on a project that is required to deliver value on an incremental basis. Which action should the project manager take to enable successful project execution?
Engage with the project sponsor to understand the scope.
Develop a comprehensive set of requirements.
Create a project schedule containing milestones.
Identify the tangible and intangible benefits.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager noticed that a team member has been struggling with some tasks. Team morale is low because they will not get the expected bonus if they do not finish on time. What should the project manager do next?
Update the project schedule and budget estimates.
Ask the HR department to replace the team member and add an additional resource.
Ask the client to approve a delay in the project schedule.
Acknowledge the team for their accomplishments, encourage them, and offer assistance to avoid future delays.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%. During the iteration retrospective, the team realizes that the complexity of the work was underestimated. What should the project manager do?
Update the issue log and escalate it to the project sponsor.
Ask to replace some team members with more experienced ones.
Meet with the team to review internal actions to resolve the situation.
Ask the technical manager to help the team with the issue.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An agile project team received an assignment to develop an industrial system. The team does not have any previous experience performing this type of work. How should this situation be handled?
Add an experienced professional to the team to reinforce knowledge sharing.
Create a separate team with experienced members.
Use a robotics vendor company to develop the interfaces.
Hire a consulting company to address questions and avoid delays.
Create a free account and access millions of resources
Similar Resources on Wayground
7 questions
Conflict Resolution Techniques

Quiz
•
4th Grade
12 questions
W.6 TA3 Workplace Meeting

Quiz
•
3rd Grade - University
8 questions
Project Management Methodologies

Quiz
•
4th Grade
7 questions
EEFs and OPAs

Quiz
•
4th Grade
10 questions
3. Definition of Project

Quiz
•
4th Grade
7 questions
Schedule Management Processes

Quiz
•
4th Grade
11 questions
Schedule Management Terms

Quiz
•
4th Grade
7 questions
Organizational Structures

Quiz
•
4th Grade
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
Discover more resources for Professional Development
12 questions
Passport Quiz 1

Quiz
•
1st - 5th Grade
10 questions
Making Predictions

Quiz
•
4th - 5th Grade
6 questions
Spiral Review 8/5

Quiz
•
4th Grade
18 questions
Rotation/Revolution Quiz

Quiz
•
4th Grade
22 questions
Geography Knowledge

Quiz
•
4th Grade
10 questions
Capitalization

Quiz
•
4th Grade
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Basic multiplication facts

Quiz
•
4th Grade