1-6 Agile Mindset Quiz New

1-6 Agile Mindset Quiz New

4th Grade

11 Qs

quiz-placeholder

Similar activities

ASP-SM-Fmk

ASP-SM-Fmk

KG - University

7 Qs

Organizational Structures

Organizational Structures

4th Grade

7 Qs

PMP 2017 PEOPLE

PMP 2017 PEOPLE

1st - 12th Grade

10 Qs

Team Development Stages

Team Development Stages

4th Grade

7 Qs

Make or Buy Decision  (Correction Needed)

Make or Buy Decision (Correction Needed)

4th Grade

7 Qs

Maslow's Hierarchy

Maslow's Hierarchy

4th Grade

7 Qs

Team Development Stages

Team Development Stages

4th Grade

7 Qs

Project management and Execution

Project management and Execution

1st Grade - Professional Development

10 Qs

1-6 Agile Mindset Quiz New

1-6 Agile Mindset Quiz New

Assessment

Quiz

Professional Development

4th Grade

Medium

Created by

Afghanistan Center

Used 4+ times

FREE Resource

11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is working on a project nearing completion using a hybrid approach. During the last daily standup, the team identified a risk of not delivering on time because team members have not initiated any of the tasks assigned to them. What should the project manager do in this situation?

Hire additional resources to increase capacity using the contingency budget.

Empower the team to self-organize and make decisions to overcome the delay.

Reassign the remaining tasks to the most experienced team members.

Inform the sponsor about the degraded performance of the team members.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A client wants to create an innovative software for the travel industry using an agile approach. A project manager was assigned to work on the details and estimates as requested by the client. What should the project manager do before sending the information to the client?

Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.

Sequence the tasks with estimates and add standard risk reserves to use for software development.

Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.

Work with the team to understand their views and add the appropriate dependencies and risks.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project to implement a new online landing platform has started. After the first sprint, the project sponsor requested a change. What should the project manager do next?

Escalate the change request to the sponsor.

Inform the stakeholders of the change.

Facilitate the update of the product backlog.

Validate the work completed.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is working on a project that is required to deliver value on an incremental basis. Which action should the project manager take to enable successful project execution?

Engage with the project sponsor to understand the scope.

Develop a comprehensive set of requirements.

Create a project schedule containing milestones.

Identify the tangible and intangible benefits.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager noticed that a team member has been struggling with some tasks. Team morale is low because they will not get the expected bonus if they do not finish on time. What should the project manager do next?

Update the project schedule and budget estimates.

Ask the HR department to replace the team member and add an additional resource.

Ask the client to approve a delay in the project schedule.

Acknowledge the team for their accomplishments, encourage them, and offer assistance to avoid future delays.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%. During the iteration retrospective, the team realizes that the complexity of the work was underestimated. What should the project manager do?

Update the issue log and escalate it to the project sponsor.

Ask to replace some team members with more experienced ones.

Meet with the team to review internal actions to resolve the situation.

Ask the technical manager to help the team with the issue.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An agile project team received an assignment to develop an industrial system. The team does not have any previous experience performing this type of work. How should this situation be handled?

Add an experienced professional to the team to reinforce knowledge sharing.

Create a separate team with experienced members.

Use a robotics vendor company to develop the interfaces.

Hire a consulting company to address questions and avoid delays.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?