Mod 7 Unit 3

Mod 7 Unit 3

University

16 Qs

quiz-placeholder

Similar activities

HRD process

HRD process

University

11 Qs

Random

Random

KG - Professional Development

11 Qs

Theorist Quiz

Theorist Quiz

University

20 Qs

TEDx Orientation Quiz

TEDx Orientation Quiz

University

20 Qs

ServSafe Quiz

ServSafe Quiz

KG - University

20 Qs

Chapter 1

Chapter 1

University

14 Qs

The 1st Industrial Society

The 1st Industrial Society

KG - University

15 Qs

EDCI 3002 GP 3

EDCI 3002 GP 3

University

12 Qs

Mod 7 Unit 3

Mod 7 Unit 3

Assessment

Quiz

Other

University

Medium

Created by

Cherie McGuire

Used 15+ times

FREE Resource

16 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Earned Value (EV) of a project is:

The actual cost incurred for the work completed.

The planned cost of the total project.

The value of work actually performed.

The difference between planned and actual progress.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

EVA measures separately for a specific point in time:

Net profit

Economic profit

Operating profit

Shareholder value

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a component of EVM?

Earned Value (EV)

Project Value (PV)

Budgeted Value (BV)

Scheduled Value (SV)

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The planned value (PV) is based on which of the following?

Baseline budgeted cost

Baseline schedule

Actual cost

Project manager's estimate

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The actual cost (AC) in project management is:

the total cost incurred for the actual work completed during a specific time period.

the estimated cost of the project at completion.

the budgeted cost of work scheduled.

the difference between earned value and planned value.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Budget at completion (BAC) in project management is:

The total budget allocated for the project.

The amount spent on the project so far.

The estimated cost to complete the project.

The difference between the planned and actual budget.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The earned value (EV) of each activity in EVA measures is calculated by:

Multiplying the percentage of work completed by the project budget

Dividing the total project budget by the number of activities

Adding the actual cost to the planned value

Subtracting the planned value from the actual cost

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?