Operations Strategy

Operations Strategy

12th Grade

7 Qs

quiz-placeholder

Similar activities

Freelancer Service Proposal & Pricing

Freelancer Service Proposal & Pricing

12th Grade - Professional Development

10 Qs

GROUP 2 RECAPULATION

GROUP 2 RECAPULATION

12th Grade

12 Qs

15 - Critical Path Analysis & Gantt Charts

15 - Critical Path Analysis & Gantt Charts

12th Grade

8 Qs

2.01 Project management 1

2.01 Project management 1

9th - 12th Grade

11 Qs

Internal/External Communication

Internal/External Communication

9th - 12th Grade

12 Qs

Worksheet 5: Project management tools and approaches (learner)

Worksheet 5: Project management tools and approaches (learner)

12th Grade

12 Qs

Project Scope Video & Questions

Project Scope Video & Questions

9th - 12th Grade

10 Qs

Week 8 P2 The Importance of  cash flow

Week 8 P2 The Importance of cash flow

9th - 12th Grade

10 Qs

Operations Strategy

Operations Strategy

Assessment

Quiz

Business

12th Grade

Medium

Created by

Maya Kharishma

Used 2+ times

FREE Resource

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following statements about project management is not true?

It needs clearly defined objective

It helps to allocate resources effectively

It ensures a product has a market

It helps to control a project

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following best describes critical path analysis?

It shows how a project can be completed with maximum labour resources

It shows how a project can be completed in the minimum time

It takes account of unforeseen events

It predicts the success of a project

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Which of the following statements is true?

E cannot start until D is completed

B cannot start until C is completed

F cannot start until D is completed

G cannot start until E and F are completed

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Which of the following statements is true?

D is on the critical path

B is not on the critical path

E is on the critical path

F and G are on the critical path

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

How much total float does activity E have?

0 days

2 days

6 days

4 days

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Which of the following statements about activity E is true?

It's not on the critical path

It has free float of 6 days

It has a total float of 2 days

It's on the critical path

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Total float is:

LFT - duration - EST

The total of all the free floats

The total slack in a project

The time an activity can be delayed without delaying the next activity