1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The customer has just started developing mobile applications. Their requirements are changing daily as the team learns about new possibilities for mobile app functionalities. They are very excited to start delivering new features to their users as soon as possible.
The key focus is to launch features that provide value, gather feedback from the market, and continue development based on that feedback.
Which project life cycle would you recommend?
Predictive
Incremental
Iterative
Agile
Hybrid
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The client wants to develop a new website for an upcoming fashion line segment.
The clothing lines are expected to be presented in a specific sequential order.
Several in-house designers are involved in the project, and they are expected to present their collections soon (the launch date continues to shift).
The work results of each designer, once completed, can be showcased as previews on the new platform.
However, the current focus is on launching a campaign to highlight the upcoming fashion lines and build anticipation.
The next steps will depend on the designers and when they complete their designs.
Designers have not yet committed to a specific timeframe for delivering their final designs.
Which project life cycle would you recommend?
Predictive
Incremental
Iterative
Agile
Hybrid
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are managing a product called OPLAY — a collaboration platform where people can find their friends or communities and play games together. You have several games in mind that you could launch. Some of these games include:
Tetris (2 players)
UNO (2-player and 4-player modes)
You want to ensure that each type of game works flawlessly across all mobile platforms.
Errors cannot be tolerated, as they could be devastating for the brand and the application.
Which project life cycle would you recommend?
Predictive
Incremental
Iterative
Agile
Hybrid
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Your task is to build a bridge between two villages across a river.
The bridge should be constructed in a way that allows for the uninterrupted transport of vehicles and people from both villages.
A government body has awarded your organization the contract with specified requirements.
The emphasis is on completing the bridge soon, and within fixed costs.
Which project methodology should be selected for the implementation?
Predictive
Incremental
Iterative
Agile
Hybrid
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You work as a manager in one of the production units of an automotive company.
The company is facing a challenge related to a newly issued government regulation for 2022 regarding emissions and safety.
This will require a redesign of the engine and interior, including safety tires, in order to pass the new legally mandated tests.
The engine design is complex and involves many phases of trial and error.
The remaining phases of vehicle production, once the engine and safety standards are met, are easier to follow and involve a standard development process, such as assembly, painting, and testing.
Which methodology would you recommend for this scenario?
Predictive
Incremental
Iterative
Agile
Hybrid
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?