1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An Activity-Based Schedule is not a schedule containing the dates of the activities defined for the project.

True

False

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An Activity List is a list of all activities defined for the project.

True

False

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Critical Path is the longest sequence of activities in the project schedule; this sequence of activities represents the earliest planned completion time for the project.

True

False

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A Dependency is not the required sequence of activities based on the work involved.

True

False

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A Dependency-Based Schedule is a schedule that does not contain the dates, but does contain the dependencies of the activities defined for the project, often displayed in the Gantt Chart form.

True

False

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Duration is the length of time that an activity continues and includes weekends or holidays.

True

False

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Finish-to-Finish Dependency is a type of dependency where an activity cannot finish until another activity has finished.

True

False

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?