1.

Inspection may identify flaws in equipment. A/an __________ can be performed to if the equipment can continue to operate safely under what conditions and for how long?

a)

Risk-Based assessment

b)

Extensive NDE Inspection

c)

Fitness for service analysis

d)

Finite element analysis

2.

Understanding the two-dimensional aspect of risk allows new insight into the use of:

a)

Innovative nondestructive methods and associated cost

b)

Employees or contractors to perform the required inspections

c)

Risk for inspection prioritization and planning

d)

Laser measuring devices or conventional measuring devices

3.

The amount and type of codes and standards used by a facility...

a)

Can have a significant impact on RBI results

b)

Will have little bearing on RBI results

c)

Must be the latest edition with current addendum

d)

Must be the edition and addendum the equipment was fabricated to

4.

It is usually more economical to modify the process or change metallurgy:

a)

During a major turnaround or outage

b)

Only after exhaustive studies are completed

c)

Just before the plant goes online

d)

When a plant is being designed

5.

Identification of the credible damage mechanisms and failure modes for all equipment included in an RBI study is essential:

a)

In determining the most cost-effective method of conducting the study

b)

To the quality and effectiveness of the RBI analysis

c)

To ensure proper identification of the equipment

d)

To ensure that only the highest risk equipment is inspected

6.

Quantitative models usually contain one or more:

a)

Customized failure scenarios or outcomes

b)

Standard failure scenarios or outcomes

c)

Generic plant failure scenarios or outcomes

d)

Inspection methodologies to detect failure modes

7.

The results of a quantitative analysis are usually:

a)

Numeric

b)

Only provided to upper management

c)

Alphabetically listed

d)

Reported as high, medium, or low

8.

Changes in process conditions and hardware changes, such as modification or replacement:

a)

Are not considered in the RBI assessment

b)

Can significantly alter the risk

c)

Since RBI is concerned with detection of deterioration mechanisms there would be no impact on the risk itself

d)

Should be reported to the jurisdictional authority within thirty days of the changes

9.

The best definition of mitigation is:

a)

Completely arresting and stopping a negative consequence

b)

Temporarily removing a negative consequence

c)

Limitation of any negative consequence

d)

Action taken to repair a negative consequence to prevent its recurrence

10.

An RBI assessment will:

a)

Determine the most appropriate way to handle the consequence of failure

b)

Determine the risk associated with the item assessed

c)

Determine the ultimate cost to reduce risks

d)

Determine the most appropriate repair methods

11.

One of the most important aspects of managing risk through Risk-Based Inspection is:

a)

Locating areas in the process stream where bottlenecks can occur

b)

Defining the demarcation points where specialist functions might overlap

c)

Development and use of mitigation strategies

d)

Operating personnel responsible for the release

12.

Failure mode is defined as "The manner of failure". For risk-based inspection, the failure of concern is:

a)

Loss of production time

b)

Loss of profits

c)

Loss of control

d)

Loss of containment

13.

According to API RP 580, RBI will identify whether the consequence or probability of failure or both is driving the risk. When risk is driven by probability of failure, generally:

a)

There is a potential for risk management through inspection

b)

There is a potential for risk management through maintenance

c)

There is a potential for risk management through operations

d)

There is a potential for risk management through initial design

14.

Items located to the risk (above) the "ISO-risk line are:

a)

To be ignored and no further action is required

b)

Unacceptable and should be mitigated

c)

Are considered only if affects production

d)

Must be taken out of service immediately

15.

The probability of failure analysis should address:

a)

Impact possibilities

b)

The need to erect barriers to protect the item under consideration

c)

All damage mechanisms the equipment, under consideration, is susceptible to

d)

Cost of repairs to return the equipment, under consideration, to serviceable condition

16.

The objective of Risk-Based Inspection is to:

a)

Develop a single inspection plan to cover all equipment installed

b)

Direct management's decision process of prioritizing resources to manage risk

c)

Direct the risk assessment teams focus

d)

Provide guidelines for conducting inspection on equipment that is in storage

17.

The Risk-Based Inspection methodology is intended to:

a)

Be used as a standalone process

b)

Prevent the use of any other inspection methods

c)

Determine what equipment should be replaced

d)

Complement other risk-based and safety initiatives

18.

The purpose of establishing operational boundaries is:

a)

To identify minor process parameters that will have minor impact on deterioration

b)

To identify who is responsible for operational up-sets

c)

To identify areas in the operating unit that can be operated outside the boundary limits with no impact on safety

d)

To identify key process parameters that may impact deterioration

19.

The RBI assessment is a team effort; the team leader is typically responsible for all the following except:

a)

Preparing the report and distributing it to the proper personnel

b)

Formation of the team

c)

Following up to assure the appropriate risk mitigation actions have been implemented

d)

Assuring adequate funding is available

20.

Utilization of RBI provides a vehicle for continuously improving the inspection of facilities and systematically reducing the risk associated with:

a)

Pressure boundary failures

b)

Operational upsets

c)

Improper repair activity

d)

Employing non-certified inspectors

21.

The accuracy of any type of RBI analysis depends on sound quality data and:

a)

Access to codes and standards

b)

Knowledgeable personnel

c)

The commitment of owner/users to the program

d)

The use of dedicated software

22.

Which of the following influences the uncertainty of the risk associated with pressure equipment primarily by improving knowledge of the deterioration state and predictability of the probability of failure?

a)

System operating records

b)

Comparison with equipment in similar service

c)

Published data

d)

Inspection

23.

API RP 580 defines failure as:

a)

Loss of most of the stored product

b)

Loss of life

c)

Loss of containment

d)

Loss of power

24.

Potential hazards identified in a Process Hazards Analysis (PHA) will often affect which part of the risk equation.

a)

Probability of failure

b)

Consequence of failure

c)

It will have no bearing on the risk equation

d)

Economic outcome

25.

Items required in a qualitative approach for RBI assessment:

a)

Need to be individually assessed

b)

Require a great deal of data reporting

c)

Only need to be categorized into broad ranges

d)

Environmental and atmospheric considerations

26.

The key to developing an optimization program is the ability to assess the risk associated with each item of equipment and then:

a)

Isolate each piece of equipment

b)

Replace each piece of equipment with new equipment

c)

Determine the most appropriate inspection techniques

d)

Determine the most efficient type of barrier to place around each piece of equipment

27.

Susceptibility to deterioration is often designated as high, medium, or low based on two main considerations:

a)

Environmental conditions and operational runs

b)

Environmental conditions and material of construction combination

c)

Time and temperatures of the current process run and materials of construction

d)

Environmental conditions and proximity of other operating units

28.

The mode of failure primarily affects:

a)

The magnitude of the cost of replacement equipment

b)

The magnitude of operational changes

c)

The magnitude of repair costs

d)

The magnitude of the consequence

29.

Once a credible damage mechanism has been identified:

a)

The corresponding repair method can also be identified

b)

The associated maintenance program can be identified

c)

The associated mitigation method can be identified

d)

The associated failure mode should be identified

30.

Data inputs based on descriptive information using engineering judgement and experience as the basis for analysis is considered a:

a)

Waste of time and resources

b)

Qualitative approach

c)

Engineering analysis

d)

Quantitative approach

31.

RBI uses a team approach. The equipment inspector or inspection specialist is responsible for:

a)

Obtaining data on the condition and history of the equipment in the study

b)

Performing the inspections required because of the study

c)

Assigning specific equipment to the other members of the team

d)

The equipment inspector or inspection specialist has no role in the RBI study

32.

The RBI methodology used to perform the RBI analysis should be documented so that:

a)

Should a failure occur, blame can be assigned to a specific member of the team

b)

Mitigation procedures can be implemented

c)

It is clear what type of assessment was performed

d)

The process can be shared with other organizations

33.

It is important to maintain and update an RBI program to ensure all the following information is included except:

a)

Most recent inspection

b)

Most recent process

c)

Most recent maintenance

d)

Most recent run time

34.

"Methods that use engineering judgement and experience as the bases for the analysis of probabilities and consequences of failure" is a definition of which of the following?

a)

Event Tree

b)

Hazard and Operability (HAZOP) Study

c)

Qualitative Risk Analysis

d)

Quantitative Risk Analysis

35.

RBI represents the next generation of inspection approaches and interval due date setting, recognizing that the goal of inspection is:

a)

To promote better relationships with the surrounding communities

b)

Safety and reliability of operating facilities

c)

To provide gainful employment for inspection personnel

d)

To determine which operating method is most economical

36.

Managing risk and reducing risk results in all the following except:

a)

Improved utilization of personnel

b)

Improved safety

c)

Avoided loss of containment

d)

Avoided commercial losses

37.

It is advantageous to group equipment, within a process unit, into systems or circuits where common environmental operating conditions exist based on all the following except:

a)

Metallurgy

b)

Equipment in similar service at other locations

c)

Process chemistry

d)

Equipment design and operating history

38.

Data quality has a direct relation to which of the following?

a)

The cost of keeping the system online

b)

The relative accuracy of the RBI analysis

c)

Which analysis approaches are used

d)

Only on the quantitative RBI analysis

39.

The consequence of loss of containment is evaluated as:

a)

Commercial value of product lost

b)

Cost to clean up the spill

c)

Loss of fluid to the environment

d)

Damage to rotating equipment such as pumps

40.

The primary work products of the RBI assessment and management approach are plans that address:

a)

Ways to manage risk on equipment level

b)

Ways to manage risk on a plant-wide level

c)

Ways to manage risk on a unit level

d)

Ways to manage risk at a corporate level

41.

The primary product of a Risk Based Inspection effort should be:

a)

Overall improvement of equipment operating cost and thus profit

b)

An inspection plan for each equipment item evaluated

c)

The ability to run an equipment item to its very lowest safety margin

d)

Defining methods of repair that circumvent regulatory requirements

42.

Facilities End of Life strategies focus:

a)

on eliminating all inspection activity on the equipment

b)

on eliminating maintenance activity on the equipment

c)

reducing operating personnel numbers

d)

inspection efforts on high risk areas

43.

Particular attention to monitoring Integrity Operating Windows (IOWs) should be provided:

a)

During start-up, normal operations, and shutdowns

b)

During shutdowns, significant process upsets, and during normal operations

c)

During start-up, significant processes upset, and shutdowns

d)

During normal operations and prolonged shutdowns

44.

Qualified personnel should evaluate each significant change to determine the potential for change in risk. It may be good to conduct an RBI assessment after significant changes in process conditions, deterioration mechanisms/rates/severities, or:

a)

Profit margins

b)

Operating personnel experience

c)

RBI premises

d)

Replacement of key pieces of equipment

45.

Emergency depressurizing/de-inventory is a risk mitigation activity that:

a)

Creates the greatest danger to equipment

b)

Reduces the amount and rate of release

c)

Should be achieved within one hour to affect explosion/fire risk

d)

Should only be used as an absolute last resort

46.

The figure shown here is an example of which of the following RBI assessment approaches?

a)

Continuum of approaches

b)

Semi-quantitative approach

c)

Qualitative approach

d)

Quantitative approach

47.

Some risks cannot be managed by inspection alone. Examples where inspection may not be sufficient to manage risk to accepted levels include all but which of the following.

a)

New equipment

b)

Equipment nearing retirement

c)

Consequence-dominated risks

d)

Failure mechanisms where avoidance of failure primarily depends on operating within a define pressure/temperature envelope

48.

Emergency isolation capability can reduce all but which of the following?

a)

Explosion

b)

Sabotage

c)

Toxic

d)

Fire

49.

The probabilities of incidents generally__________ with the severity of the incident:

a)

Increase

b)

Remain constant

c)

Are monitored

d)

Decrease

50.

Each type of damage mechanism has its own characteristic failure mode. For a specific damage mechanism, the expected mode of failure should be considered when considering:

a)

The consequence of incidents in the aftermath of an equipment failure

b)

The long-term economic impact in the aftermath of an equipment failure

c)

The probability of incidents in the aftermath of an equipment failure

d)

The appropriate coating to be applied to the equipment

51.

The probability of failure is determined by tw main considerations. What are they?

a)

The initial cost of construction and potential cost of repair

b)

Damage mechanisms and effectiveness of the inspection program

c)

The maintenance and operating personnel

d)

Specific gravity of the stored product and weather conditions

52.

In most plants, a large percentage of the total risk will be:

a)

Concentrated on a relatively small percentage of the equipment

b)

Concentrated on equipment that is difficult to reach and inspect

c)

Concentrated on equipment that is run the most often

d)

Concentrated on a relatively large percentage of the equipment

53.

Which of the following is the primary audience for API RP 580?

a)

Operating personnel responsible for safe operation of equipment

b)

Maintenance personnel responsible for the routine maintenance of the equipment

c)

Inspection and engineering personnel responsible for mechanical integrity and operability of equipment

d)

Repair organization responsible for repairing equipment

54.

Termination of the ability of a system, structure, or component to perform its required function of containment of fluid is a definition of:

a)

External event

b)

Probability

c)

Risk

d)

Failure

55.

In most consequence evaluation, a key element in determining the magnitude of the consequence is:

a)

The cost of lost production

b)

The volume of fluid released

c)

The cost of repairs

d)

The effect of plant though put

56.

A fitness for service analysis can be performed to determine what size flaws, if found in future inspection;

a)

Could be ignored

b)

Would have the highest potential for failure

c)

Would require repair or equipment replacement

d)

Would be self arresting

57.

Which of the following would not be considered a variable in assessing remaining life and future inspection plans?

a)

Damage mechanisms

b)

Rate of deterioration

c)

Equipment tolerance to the types of deterioration

d)

The consequence of failure

58.

In the RBI roles, responsibilities, and qualification discussion of API RP 580, in addition to providing sponsorship and resources for the RBI assessment, management is also responsible for:

a)

Providing the resources and follow-up system to implement risk mitigation decisions

b)

Providing the resources necessary to conduct inspection decisions of the RBI team

c)

Providing funding to purchase special team uniforms

d)

Providing the resources necessary to conduct future follow-up RBI studies

59.

According to the consequence effect categories discussion API 580, toxic releases are only addressed when they affect:

a)

Toxic releases are always addressed regardless where they happen

b)

Only when it appears the release will drift over waterways

c)

Only when they affect personnel (site and public)

d)

Only when they affect the public, especially schools, hospitals, universities, etc.

60.

One of the most important aspects of managing risk through RBI is:

a)

Choosing the RBI team members

b)

Understanding the RBI pitfalls

c)

The development and use of mitigation strategies

d)

To clearly document all assumptions made during the analysis of the probability of failure and consequence of failure

61.

A fundamental difference among the qualitative, semi-qualitative, and quantitative RBI assessment approaches:

a)

Is insignificant

b)

Are how many financial resources the user wishes to expend

c)

Is the amount and detail of input, calculations, and output

d)

Is based entirely on the personnel resources available

62.

Risk-based inspection is focused on a systematic determination of:

a)

Total facility operating costs

b)

Relative risks

c)

Absolute risk

d)

Average risk factors

63.

Combining the probability of one or more events with its consequences will determine:

a)

What department will be responsible for repairs and clean up

b)

The risk of the operation

c)

How long will the plant be shut down for retrofit

d)

The most cost effective method of operation to prevent the event in the first place

64.

An effective Process Safety Management program includes:

a)

A well-structured and effective pressure equipment operating manual

b)

A well-structured and effective pressure equipment maintenance program

c)

A well-structured and effective pressure equipment replacement program

d)

A well-structured and effective pressure equipment inspection program

65.

Managing risk by using RBI assessment can be useful in implementing an effective inspection program that meets performance-based safety and environmental requirements. Risk-based Inspection focuses...

a)

On areas where the greatest risk exists

b)

Only on potential events that can be predicted

c)

On areas that are critical to the operation of the plant

d)

On areas that will result in operational cost reduction

66.

A/an___________ should be consulted to define the equipment damage mechanisms and potential failure modes:

a)

Professional Engineer (PE)

b)

Inspection department from another user

c)

An inspector with at least ten years' experience

d)

Corrosion Specialist

67.

One goal of risk analysis is to communicate the results:

a)

in precise terms that are clear only to the RBI team members

b)

Using as many acronyms as possible to keep the report short

c)

In a familiar format that a variety of people can understand

d)

Ina format that only people who use RBI daily will understand

68.

When more quantitative consequence and probability data are being used, and where numeric risk values are more meaningful, which of the following is used:

a)

Risk matrix

b)

Event tree

c)

Risk plot

d)

Risk management graph

69.

In addition to identifying, monitoring, and measuring damage mechanisms, inspection also provides which of the following?

a)

Gainful employment for inspectors

b)

Input in the prediction of when the damage will reach a critical point

c)

Input to operating personnel on the best method to operate the process unit

d)

Input to purchasing personnel on the best vendor to purchase replacement equipment

70.

Key parameters that can affect the future risk are all but which of the following?

a)

Inspection frequency

b)

Internal, on-stream, or external inspection

c)

Tools and techniques

d)

The continued current operating parameters