1.
You have joined a project in which requirements are elaborated at several intervals during delivery, and the delivery is divided into subsets of the overall product. Change is incorporated at periodic intervals, and risk and cost are controlled by progressively elaborating the plans with new information. Key stakeholders are regularly involved.
What development approach is used on your project?
a)
Agile
b)
Predictive
c)
Hybrid
d)
Periodic
2.
The project team has been arguing about what should go into the project management plan. They've built the same product over a hundred times before and have always been bothered that the project management plan never seemed to get completed. They were determined to get it done right this time. The team has come to you for advice regarding the project management plan. The most appropriate response you can give them is:
a)
Use project phase concepts; initiate, plan, execute, monitor & control, and close
b)
They need training in project management
c)
The 'project' is really operations
d)
Tell them to take direction from the PMO
3.
All of the statements about the project life cycle are true except which of the following
a)
The project life cycle consists of five distinct phases
b)
The project life cycle is different for every organization
c)
The project life cycle works with the project management life cycle to help meet project objectives
d)
The project life cycle can be modified depending on the needs of the project
4.
You are the Project Managers of XYZ consultants. The Project team members are from Finance and HR departments. The team members report to Finance and HR Managers respectively, and you have limited over them. What type of organizational hierarchy does XYZ consultants follow?
a)
Matrix organization
b)
Projectized organization
c)
Functional organization
d)
None of these.
5.
You have been assigned to lead an initiative for which the business case has not been sufficiently made to get approval to initiate a hybrid project. In some of the past projects, teams realized too late into project execution that no one in the company had the skills needed to build some of the features, so it was developed by a contractor, resulting in cost overruns. What would you do differently in your assignment to avoid cost overruns?
a)
Start with a proof of concept
b)
Use burndown charts for reporting
c)
Develop a project charter
d)
Encourage team knowledge sharing
6.
A project has just been initiated to transform an organization from a functional organizational structure to project-oriented. If the project is successful in meeting its objectives, what will be the most likely outcome? (Choose three.)
a)
The organization will shift from the current state to the desired future state.
b)
The project manager(s) will have control over the project budget
c)
Employees will be grouped by the work being done (engineering. manufacturing, etc.)
d)
The project manager(s) will have significantiy more authority over projects.
e)
The role of the project manager(s) will be defined as a project coordinator
7.
An organization is about to undertake three complex agile projects that will have interdependencies between them. Each project has a team consisting of six members and is led by a scrum master. The projects are part of a bigger program.
What is the best strategy for the program manager to coordinate the work between the projects?
a)
Suggest that the scrum masters establish a scrum of scrums between the projects
b)
Allow the project teams to work independently to expedite the delivery of value
c)
Combine the project teams into one large scrum team led by a scrum master
d)
Ensure that all project activities are scheduled during initial project planning
8.
A company operating in a high-tech industry with new technologies emerging every few months charters a project that is expected to have unstable requirements for its whole duration. A project manager is assigned, and the sponsor requests the project manager to suggest a strategy that best supports the adaptability and resiliency of the project in this environment.
Which of the following capabilities should the project leader leverage for this strategy?
a)
Expediting decision making to occur at the first possible moment
b)
Acquiring project team members with a highly specialized set of skills
c)
Limiting the exposure to tacit knowledge and leveraging explicit knowledge
d)
Incorporating short feedback loops to adapt the product and process quickly
9.
A senior executive suggests initiating a project to replace a significant portion of the company's labor force with an automated production line. Other company executives are skeptical that this approach is the best way to increase profit margins and wonder if they are ready to sponsor such an effort.
What is the first thing that should be done in this scenario?
a)
Performing a needs assessment
b)
Consulting with the project management office
c)
Appointing a project sponsor to create a project charter
d)
Providing a project manager with the authority to apply organizational resources
10.
An organization has established a controling project management office (PMO). The first task of the PMO is to update the guidelines for project compliance in the organization. which of the following could the PMO enforce? (Choose three.)
a)
Use of particular project management methodologies
b)
Adoption of specific templates, forms, and tools
c)
Adherence to local health regulations
d)
Conformance to governance frameworks
e)
Assignment of project managers by the PMO