SG20_Test_S4_CH5 Scope

Total questions: 10

Worksheet time: 10mins

Name
Class
Date
1.
A project requires ongoing stakeholder engagement and needs to respond to high levels of change. The project manager selects a hybrid life cycle for the project and prioritizes the work items in a backlog. At the beginning of each iteration, the team determines how many backlog items they can deliver. Which project management process(es) will the project team need to repeat with each iteration?
a)

Processes are not performed on a hybrid project

b)

Collect Requirements and Create WBS

c)

Identify Stakeholders and Close Project or Phase

d)

Collect Requirements and Define Scope

2.
Near the end of an iteration, the project team is ready to lead a product review with the product manager. What is the objective of the review?
a)

Validate the product scope

b)

Manage product quality

c)

Control the product scope

d)

Close the project or phase

3.
As your project progresses, a team member suggests a minor modification to one of the project deliverables, saying that the modification will improve the overall performance of the final product. You believe that the modification constitutes a minor change to the project scope, schedule, and budget, and should be approved without going to the change control board. What should you do next?
a)

Approve the change request. As the project manager, you should use expert judgment to decide what is best for the project.

b)

Meet with the change control board members individually and try to persuade them to approve the change request.

c)

Submit the change request to the change control board and abide by their decision.

d)

Review the change management plan and follow the established process for processing change requests.

4.
You are leading a project that was supposed to be managed using agile methods. Every week, however, the product owner holds a five-hour backlog refinement meeting with the project team where she presents the project scope broken down to the work package level. After three iterations, the project team's velocity is slower than expected. What is your best course of action?
a)
Ask the product owner to decompose the scope down to the task level and assign the tasks to the team members
b)
Advise the product owner to hold two five-hour backlog refinement meetings per week to gain further clarity on the scope
c)
Coach the product owner on presenting the overall story concept with one-hour weekly backlog refinement meetings
d)
Hold a team-building exercise with the team members and product owner to improve the communication between them
5.
You are leading a software development project for a client. The change control board (CCB) has been inundated with change requests from the client throughout the project as the product has evolved. This situation drives the team crazy and makes controlling the project scope extremely challenging and time-consuming. Which of the following tailoring considerations might you have missed earlier in the project?
a)
Diversity
b)
Stability of requirements
c)
Physical location
d)
Validation and control
6.
Planning is underway for a project to develop a new online collaboration tool. The team will use the extreme Programming (XP) method to develop the tool, while the deployment to the customers will be managed using a waterfall approach. The agile coach wants to gather early customer feedback on a working tool to ensure it's aligned with the product vision. What is the best course of action?
a)
Develop the complete set of features and showcase it at a developer's conference
b)
Create a wireframe for the public to use and provide feedback
c)
Plan for the development of an MVP for a release to a subset of customers
d)
Perform decomposition to create the work breakdown structure
7.
A software development project will use an iterative and incremental approach to produce project deliverables. What planning strategy would work best for this project?
a)
Decomposing epics into features and further into user stories
b)
Outsourcing project planning to an external subject matter expert
c)
Breaking down high-level deliverables into work packages
d)
Planning product scope and refraining from planning project scope
8.
A project manager is currently in the process of determining, documenting, and managing stakeholder needs and requirements. Due to the sensitive nature of the project, there is a concern that some stakeholders will not provide candid feedback unless confidentiality is maintained. What is the project manager's best course of action?
a)
Conduct interviews to elicit information from stakeholders by talking to them directly
b)
Use brainstorming to generate and collect multiple ideas related to project requirements
c)
Hold a focus group to learn about stakeholder expectations and attitudes about the project
d)
Use multicriteria decision analysis to provide a systematic analytical approach for establishing criteria
9.
Gold plating had been an issue with your current software development project. However, you found that ever since instituting daily stand-up meetings, no more features or functionalities that the customer did not request have been introduced into the project. What is your best course of action to prevent gold plating for the remainder of the current project and on future projects?
a)
Bring up the topic during the project retrospective
b)
Capture the best practice in the lessons learned register
c)
Gold plating adds customer value and should not be prevented
d)
Ensure that the scope management plan includes daily stand-up meetings
10.
The project team reports that they have finished creating the requirements management plan, the requirements documentation, and the requirements traceability matrix. The team informs that they are going to start working on the project work breakdown structure (WBS) next. What has the project team forgotten to do?
a)
Create the project scope statement
b)
Complete the project management plan
c)
Update the lessons learned register
d)
Perform the Validate Scope process