Procurement 10 soal (Chapter 12)

Total questions: 10

Worksheet time: 10mins

Name
Class
Date
1.

A project manager has just received formal acceptance and final payment from a client for a software development project. The project manager needs to begin preparing the final project report. Which of the following will be most useful in creating the final report?

a)

Stakeholder register

b)

Communication management plan

c)

Project charter

d)

Closing report register

2.

A vendor on your project informs you that they will be unable to perform the work as contracted after some equipment required for the project was destroyed in a hurricane. The vendor cites a clause in the contract that is designed to address the inability of party to execute their responsibilities due to extraordinary factors that were outside the control of the party. What clause does the vendor refer to?

a)

Arbitration

b)

Force majeure

c)

No-contest

d)

Termination

3.

You are leading a project with some of the deliverables outsourced to a vendor. You have been working closely with your procurement administrator to ensure that all claims, invoices, and final payments have been finalized with the vendor. Terms and conditions of the contract have been met, and all deliverables have been accepted. What should you do next?

a)

Notify the vendor that the contract has been completed

b)

Finalize all activities for the project and release the project team

c)

Conduct the final inspection of the vendor’s deliverable

d)

Carry out a structured review of the procurement process

4.

Which of the following is a tool or technique of the Plan Procurement Management process?

a)

Inspection

b)

Contract negotiation

c)

Risk-related contract decision analysis

d)

Data analysis

5.

The project manager is in discussion with vendors about their bids that came in higher than expected. Additionally, according to the vendor’s responses, none of them will be able to deliver by the deadline requested. The project manager talks to the sponsor and other key project stakeholders to see if additional funds are needed to cover the extra costs and deliver on schedule. What process is the project manager performing?

a)

Control Costs

b)

Control Schedule

c)

Acquire Resources

d)

Conduct Procurements

6.

As a project manager for a small company, you have been responsible for negotiating and issuing contracts. Although your company has pre-qualified vendors, and the agreements are standard, you think the procurements should be handled by someone with more knowledge on the subject rather than the project managers. Which of the following will you recommend?

a)

Decentralized purchasing

b)

Centralized purchasing

c)

Pre-qualified vendors

d)

Supply chain management

7.

A project manager is planning a project to build a new apartment complex on the site of a long-abandoned airport that was closed due to illegal dumping of fuel and oil. The project manager will need to provide a regulatory agency with a detailed explanation of how the cleanup will be performed before a permit can be caused. What would be the most appropriate bid document to send to potential vendors for the environment cleanup?

a)

Request for information (RFI)

b)

Request for advisement (RFA)

c)

Request for proposal (RFP)

d)

Request for quotation (RFQ)

8.

You recently received an email from a client, which states,” Thanks. We have received the goods you just shipped”. You begin to close out the project, send the final invoice to the client, and release all of your staffs. As you are preparing to leave for the day, you receive a voicemail from the client stating that the deliverables do not meet the required specifications. This information comes as a shock because you are sure the client has accepted the deliverables. What should you do now?

a)

Call the client and tell them that they have accepted the deliverables and should now pay the final invoice

b)

Call the client to understand why they think the deliverables do not meet the required specifications

c)

Contact the legal department to check the contract and ask them to suggest a course of action

d)

Ignore the voicemail from the client since their email indicates that they have already accepted the deliverables

9.

The Control Procurements process has eight inputs, including:

Project management plan

Project documents

Agreements

Procurements documentation

Work performance data

Enterprise environmental factors

Organizational process assets

Which of the following inputs is missing from the list?

a)

Project charter

b)

Project scope statement

c)

Schedule baseline

d)

Approved change requests

10.

Per organizational policy, any commodities purchased for a project must be either the least cost option available or a sole source. Which project process and tools and technique does this most impact?

a)

Source selection in Plan Procurement

b)

Data representation in Identity Stakeholders

c)

Pre-assignment in Acquire Resources

d)

Accepted deliverables in Validate Scope