Engineering Quiz

Total questions: 118

Worksheet time: 59mins

Name
Class
Date
1.

Onset of plastic deformation will result due to Hardening

a)

a. Hardening

b)

b. Ductility

c)

c.      Necking

d)

d. Yielding

2.

 

Strain Unit?

a)

a.      Dimension less

b)

b.      ¼ PI

c)

c.      Pa

d)

d.      N/mm2

3.

You discover violation of specification at nearly end of the project, what you will do…

a)

a.      Inform to Client and ask what to do

b)

b.      You will try to find some loophole to escape from the problem arisen

c)

c.      Do nothing , its Boss problem ,he will handle it later

d)

d.      Punish the violator

4.

What is the function of the barometer?

a)

a.      Measure the pressure differential

b)

b.      Related to tube measurement

c)

c.      Measure the atmospheric pressure

d)

d.      All of above

5.

Some devices to be installed (don’t remember-may fire sprinkler ) related to distance from the Centre of elevator

a)

a.      6.4 meter

b)

b.      4.6 meter

c)

c.      3 meter

d)

d.      1.5 meter

6.

  Fire resistance of the vertical wall

a)

a.      Less than 15 min resistance

b)

b.      Less than 30 min resistance

c)

c.      Less than 1 hour  resistance

d)

d.      Less than 2 hour resistance

7.

Efficiency of a power plant if the efficiencies of the boiler, turbine and generator are 88, 40 and 98%, respectively.

a)

a.      35 %   {  E power plant = [E boiler] [E turbine] [E generator] = (0.88) (0.40) (0.98) = 0.35 }

b)

b.      42%     

c)

c.      90%

d)

d.      15% 

8.

Activity B has 4 days  LAG compare to A  what does it mean

a)

a.       Activity B start  4 days before A completion

b)

b.      Activity A and B both will start on 4th day

c)

c.      4 day waiting time between Activities A & B

d)

d.      None of above

9.

If you are going to start with oil pipeline construction which is the following engineer you are going to choose:

a)

a. Petroleum

b)

b. Mechanical

c)

c. Civil

d)

d. Chemical

10.

Molecular formula of refrigerant  R410a

a)

a.      CH2FCF3

b)

b.     50%CH2F2/50%CH2CF3

c)

c.      CHF2CF3

d)

d. None of these

11.

Fast tracking to be performed in the project

a)

a.       Compress the schedule without changing the scope of project

b)

b.      Compress the schedule without changing the cost of the project

c)

c.       

d)

d.      All of above

12.

Project is awarded , what you will do next

a)

a.      Plan the work

b)

b, Develop project charter

c)

a.      Develop schedule

d)

b.      Define scope

13.

Testing of heat detector( NFPA 72)

a)

a.      Quarterly

b)

b.      Annually

c)

c.      Monthly

d)

d.      Semiannually

14.

Isolated system is a system that:

a)

a.      Mass is not entering or leaving the system while the energy can be transfer

b)

b.      Neither mass nor the energy enter or leaves the system

c)

c.      Mass leave and enters the system while energy don’t

d)

d.      None of the above

15.

Coefficient of performance of a refrigerator that consumes 800 watts of power to remove heat at a rate of 5 BTU per second.

a)

a.      4.6

b)

b.      6.6      ( 5 x 1055/800 = 6.6)   ( where 1BTU=1055 j) & ( 1 watt =  1j/s)

c)

c.      8.2

d)

d.      3.5

16.

One of the following is not process of the project:

a)

a.      Concept

b)

b.      Initiating

c)

c.      Planning

d)

d.      Executing

17.

Which test generally performs after installation of fire damper?

a)

a.      Fire test

b)

b.      Smoke test

c)

c.      Both A& B

d)

d.      All of above

18.

In context of Ideal Gases , following is true

a)

a.      PV= nRT

b)

b.      PR= nVT

c)

c.      n=RT/PV

d)

d.      None of above

19.

Software programming flow

a)

a.      Plan,Do,Check,Act

b)

b.      Plan,Do,Act,Check

c)

c.      Plan,Act,Do,Check

d)

d. Non of these

20.

When need high pressure with low discharge

a)

a.      Centrifugal pump

b)

b.      Axial pump

c)

c.      Propeller pump

d)

d.      Reciprocating pump

21.

Enclosed parking area ventilation need the capacity at normal time

a)

a.      47 L/min for the square meter area

b)

b.      300 L/min for the square meter area

c)

c.      6 L/min for the square meter area

d)

d.      87 L/min for the square meter area

22.

As per NFPA supervisory control valve inspection frequency

a)

a.      Monthly

b)

b.      Quarterly

c)

c.      Semi –annually

d)

d.      Annually

23.

As per NFPA supervisory control valve testing frequency

a)

a.      Monthly

b)

b.      Quarterly

c)

c.      Semi –annually

d)

d.      Annually

24.

Which kind of wall keep between two building blocks to avoid spreading of fire from one to another

a)

a.      Shear wall

b)

b.      Retainer wall

c)

c.      Fire wall

d)

d.      None of above

25.

Without using photo voltaic cell solar power used for which air conditioning

a)

a.      Vapor compression

b)

b.       Vapor absorption

c)

c.      Using battery

d)

d. Hot pipe

26.

Heat stress happen in the metal due to

a)

a.      Temperature

b)

b.      Temperature gradient

c)

c.      Molecular arrangement

d)

d.      Cooling

27.

As per NFPA water sprinkler testing frequency

a)

a.      Monthly

b)

b.      Semi – annually

c)

c.      Weekly

d)

d.      Annually

28.

Inspection for the manual call point done

a)

a.      Monthly

b)

b.      Semi – annually

c)

c.      Annually

d)

d.      Quarterly

29.

First step of Scope planning starts with

a)

a.      Budgeting

b)

b.      Current earning estimation

c)

c.      Objectives and requirements to satisfy customer

d)

d. Non of these

30.

In network which point getting more inward flow

a)

a.      Float

b)

b.      Critical path

c)

c.      Slack

d)

d.      Merging point

31.

Car bumper purpose

a)

a.      High speed impact

b)

b.      Low speed impact

c)

c. a & b

d)

d. Non of the above

32.

Brake lining have character of

a)

a.      Wear resistance

b)

b.      Temperature dissipation

c)

c.      Resistance to heat

d)

d.      All above

33.

Intersecting point for WBS and OBS

a)

a.      Cost account

b)

b.      Intersect matrix

c)

c.      Project matrix

d)

d.      None of above

34.

What is the least level of WBS

a)

a.      Deliverable

b)

b.      Cost

c)

c.      Work package

d)

d.      Lowest sub deliverable

35.

NFPA trained person takes minimum time for investigation and reset fire preventive system

a)

a.      3 min

b)

b.      30 min

c)

c.      1 hour

d)

d.      3 hour

36.

What is the rating of fire wall required for four story or more?

a)

a.      1 hour

b)

b.      2 hour

c)

c.      30 min

d)

d.      45 min

37.

Priming the pump means:

a)

a.      To paint the pump casing with primer to avoid pump rusting

b)

b.      Remove air from pump casing and impeller

c)

c.      Remove air from pump piping

d)

d.      Non of these

38.

If your boss has already assigned a new project and you are the project manager what is the first thing to do

a)

a.      Make a report about project processes

b)

b.      Make a report about project cost needed

c)

c.       Ask your boss about the team work

d)

d.      Make Modification about Planning Process.

39.

If we increase the Insulation around the pipe heat will transfer due to

a)

a.      Increase of conduction and decrease of convection

b)

b.      Decrease of conduction and increase of convection

c)

c.      Increase both of conduction and convection

d)

d.      Decrease both of conduction and convection

40.

Total angles inside the Hexagonal shape

a)

a.      360

b)

b.      720

c)

c.      900

d)

d. Non of these

41.

System used for car park for hazard detection

a)

a.      NFPA88A

b)

b.      NFPA170

c)

c.      ICP

d)

d.      Not recall

42.

The opening in structural car parking should be --------from all building

a)

a.      5%

b)

b.      10%

c)

c.      15%

d)

d.      Above 40%

43.

Inspection of heat detector according to NFPA

a)

a.      Monthly

b)

b.     Semi Annually

c)

c.      Weekly

d)

d.      Annually

44.

Visual Inspection of zone control value as per NFPA

a)

a.      Semiannually

b)

b.      Quarterly

c)

c.      Monthly

d)

d.      Weekly

45.

Which of these devices used to control the hazards?

a)

a.      Fire damper

b)

b.      Smoke controls

c)

c.      Stack dumper

d)

d.      Not recall

46.

Turbulent flow can be determining by

a)

a.      Reynold's number

b)

b.      Weber's number

c)

c.      Mole number

d)

d.      Specific weight

47.

Centripetal force acts at the radius of circle

a)

a.      From the Centre of the circle

b)

b.      To the Centre of the circle

c)

c.      Outside the circle

d)

d.      None of these

48.

Frictional gear at automobile cars used to

a)

a.      Reduced speed

b)

b.      Turn around

c)

c.      To stop speed

d)

d.      None of these

49.

Hooke’s laws holds good up to

a)

a.      Yield point

b)

b.      Limit of proportionality

c)

c.      Breaking point

d)

d.      Electric limit

50.

when heat   is Transferred by molecular collision, it is referred to as heat transfer by

a)

a.      conduction

b)

b.      radiation

c)

c.      convection

d)

d.      Correction and radiation

51.

In convection heat transfer from hot flue gases to water tube, even though flow may be turbulent, a laminar flow region (boundary layer of film) exist close to the tube. The heat transfer through this film takes place by.

a)

a.      Convection

b)

b.      Radiation

c)

c.      Conduction

d)

d.      Both convection and conduction

52.

Architecture visit the site gypsum board wall team work with very poor quality, what should do?

a)

a.      Stop work immediately

b)

b.      Call superintendent responsible for work and inform him

c)

c.      Call the owner and tell him

d)

d.      Contact main General Contractor

53.

Government need to build new library, where should contrast

a)

a.      Near recreation & garden areas

b)

b.      Near bus station

c)

c.      Near school

d)

d.      Near jobs office & Government areas

54.

Your boss gives new assignment which you don’t know about it, what you should do?

a)

a.      Inform him the truth

b)

b.      Get help from good Engineer to support you

c)

c.      Study it & do his effort to do it

d)

d.      None of these

55.

The tendency of a liquid surface to contract is due to the following property

a)

a.      Cohesion

b)

b.      adhesive

c)

c.      viscosity

d)

d.      surface tension

56.

Buoyant force is

a)

a.      The result force acting on a floating body

b)

b.      The resultant force on a body due to the fluid surrounding it.

c)

c.      Equal to the volume of liquid dis‐placed

d)

d.      None of the above

57.

According to Bernoulli’s equation for steady ideal fluid flow

a)

a.      Principal of conservation of mass holds

b)

b.      velocity and pressure are inversely proportional

c)

c.      Total energy constant throughout

d)

d.      The energy is constant along a stream line but may vary stream lines but may a cross streamline

58.

At the Center line of pipe flowing under pressure where the velocity gradient zero, the shear will be

a)

a.      Minimum

b)

b.      Maximum

c)

c.      Zero

d)

d.      Could be any value

59.

Which part stop spark & fire inside duct

a)

a.      Spark arrestor

b)

b.      Fire dumper

c)

c.      Grills

d)

d.      None of these

60.

Insert smoke inside HVAC Duct to check

a)

a.      Leak

b)

b.      Air velocity

c)

c.      Density

d)

d.      Oxygen level

61.

Inspections for heat detector as per NFPA could be

a)

a.      Weekly

b)

b.      Semi Annually

c)

c.      Monthly

d)

d.      Quarterly

62.

Which parameters affect the fluid speed?

a)

a.      Density

b)

b.      Viscosity

c)

c.      Homogenouslye

d)

d.      None of these

63.

If you were awarded a project, you will start work:

a)

a.      One week before the approval of the authorities

b)

b.      After the approval of the authorities

c)

c.      One day before the approval of the authorities

d)

d. None of these

64.

Project Scope Management:

a)

a.      Define scope and control scope

b)

b.      Executing scope and verify scope

c)

c.      Closing process and Create work breakdown structure

d)

d.      All of the above

65.

Scope Management starts with is:

a)

a.      To identify the client requirements

b)

b.      Meet the team

c)

c.      Review strategic plan

d)

d. None of these

66.

Final as built drawings for what purpose

a)

a.      To keep record for later maintenance

b)

b.      To give more work to architect

c)

c.      To be used for further renovation

d)

d. None of these

67.

Control department work starts

a)

a.      From the beginning of the project

b)

b.      During construction

c)

c.      After construction

d)

d. None of these

68.

Project management is ideally suited except

a)

a.      Accountability

b)

b.      Flexibility

c)

c.      Innovation

d)

d.      Repeatability

e)

e.      Speed

69.

A critical path is the ----------------------in the project management:

a)

a.      longest

b)

b.      shortest

c)

c.      a & b

d)

d.      none

70.

The forward pass review of the project management will indicate the following:

a)

a.      The earliest start of the task

b)

b.      The earliest finish of the task

c)

c.      Critical path (longest path)

d)

d.      All of the above

71.

The back pass review of the project will indicate the following:

a)

a.      The latest start of the task.

b)

b.      The earliest finish of the task.

c)

a.      The critical path..

d)

b.      All of the above

72.

Intersecting point for WBS and OBS

a)

a.      Cost account

b)

b.      Intersect matrix

c)

c.      Project matrix

d)

d.      None of above

73.

For operation and designed auto mobile factory

a)

a.      Mechanical Engineer

b)

b.      Civil Engineer

c)

c.      Chemical Engineer

d)

d.      Petroleum Engineer

74.

Which of the following discipline is most suitable for doing a natural gas pipeline work?

a)

a.      Mechanical Engg

b)

b.      Petroleum Engg

c)

c.      Chemical Engg

d)

d.      Civil Engg

75.

Gypsum board at residence and industrial building used except

a)

a.      Low cost

b)

b.      Ease of installation

c)

c.      Recyclability

d)

d. None of these

76.

Which one of the following is suitable in engineering manner?   “Decision shall be based on reason than situation’’.

a)

a.      Quantity Thinking.

b)

b.      Logical Thinking.

c)

c.      Interpersonal Skills.

d)

d.      Honesty.

77.

An activity in a project network can be represented by which of the following?

a)

a.      Arrow

b)

b.      Line

c)

c.      Node 

d)

d.      All of the above

78.

Before starting work at site, the major factor has to be checked is?

a)

a.      Access to site (EFE)

b)

b.      Storage of Water, tools & equipment

c)

c.      Safety

d)

d.      Approval from MMUP / Civil / Defense etc.

79.

Software programming flow

a)

a.      Plan, Do, Check, Act

b)

b.      Plan, Do, Act, Check

c)

c.      Plan, Act, Do, Check

d)

d. None of these

80.

First step of Scope planning starts with

a)

a.      Budgeting

b)

b.      Current earning estimation

c)

c.      Objectives and requirements to satisfy customer

d)

d. None of these

81.

In network which point getting more inward flow

a)

a.      Float

b)

b.      Critical path

c)

c.      Slack

d)

d.      Merging point

82.

Molal ideal gas specific heat depends on

a)

a.      Temperature

b)

b.      Pressure

c)

c.      Both temperature and pressure

d)

d.      Molecular counting

83.

Car bumper purpose

a)

a.      High speed impact

b)

b.      Low speed impact

c)

a & b

d)

None of these

84.

Brake lining have character of

a)

a.      Wear resistance

b)

b.      Temperature dissipation

c)

c.      Resistance to heat

d)

d.      All above

85.

Intersecting point for WBS and OBS

a)

a.      Cost account

b)

b.      Intersect matrix

c)

c.      Project matrix

d)

d.      None of above

86.

What is the least level of WBS

a)

a.      Deliverable

b)

b.      Cost

c)

c.      Work package

d)

d.      Lowest sub deliverable

87.

NFPA trained person takes minimum time for investigation and reset fire preventive system

a)

a.      3 min

b)

b.      30 min

c)

c.      1 hour

d)

d.      3 hour

88.

What is the rating of fire wall required for four story or more?

a)

a.      1 hour

b)

b.      2 hour

c)

c.      30 min

d)

d.      45 min

89.

Priming the pump means:

a)

a.      To paint the pump casing with primer to avoid pump rusting

b)

b.      Remove air from pump casing and impeller

c)

c.      Remove air from pump piping

d)

d.      None of these

90.

If your boss has already assigned a new project and you are the project manager what is the first thing to do

a)

a.      Make a report about project processes

b)

b.      Make a report about project cost needed

c)

c.       Ask your boss about the team work

d)

d.      Make Modification about Planning Process.

91.

If you were awarded a project, you will start work

a)

a.      After the approval of the authorities

b)

b.      One day before the approval of the authorities

c)

c.      One week before the approval of the authorities

d)

d. None of these

92.

Project Scope Management

a)

a.      Executing scope and verify scope

b)

b.      Define scope and control scope

c)

c.      Closing process and Create work breakdown structuree

d)

d.      All of the above

93.

Scope Management starts with is

a)

a.      To identify the client requirements

b)

b.      Review strategic plan

c)

c.      Meet the team

d)

d. None of these

94.

Final as built drawings for what purpose

a)

a.      To give more work to architect

b)

b.      To keep record for later maintenance

c)

c.      To be used for further renovation

95.

Control department work starts

a)

a.      After construction

b)

b.      During construction

c)

c.      From the beginning of the project

96.

Project management is ideally suited except

a)

a.      Speed

b)

b.      Accountability

c)

c.      Flexibility

d)

d.      Repeatability

97.

A critical path is the ----------------------in the project management:

a)

a.      Longest

b)

b.      Shortest

c)

c.      None

98.

The forward pass review of the project management will indicate the following:

a)

a.      The earliest start of the task

b)

b.      Critical path (longest path)

c)

c.      The earliest finish of the task

d)

d.      All of the above

99.

Intersecting point for WBS and OBS

a)

a.      Project matrix

b)

b.      Intersect matrix

c)

c.      None of above

d)

d.      Cost account

100.

Gypsum board at residence and industrial building used except

a)

a.      Low cost

b)

b.      Ease of installation

c)

c.      Recyclability

101.

Acceptable reasons for project stopping, except?

a)

a.      Frustration

b)

b.      Labor dispute

c)

c.      Natural calamities

d)

d.      None of above

102.

Before starting work at site, the major factor has to be checked is?

a)

a.      Approval from MMUP / Civil / Defense etc.

b)

b.      Access to site (EFE)

c)

c.      Storage of Water, tools & equipment

d)

d.      All of the above

103.

Software programming flow

a)

a.      Plan, Do, Act, Check

b)

b.      Plan, Act, Do, Check

c)

c.      Plan, Do, Check, Act

104.

In network which point getting more inward flow?

a)

a.      Slack

b)

b.      Float

c)

c.      Critical path

d)

d.      Merging point

105.

What is the least level of WBS

a)

a.      Deliverable

b)

b.      Work package

c)

c.      Cost

d)

d.      None of above

106.

The most important end state of project initiation is

a)

a.      Management provides the budget required

b)

b.      Management assigns a project manager

c)

c.      Management approves the project charter

d)

d.      Management agrees to the details of works to be done

107.

What is the duration of the project?

a)

a.      45weeks

b)

b.      46weeks

c)

c.      47weeks

d)

d.      44weeks

108.

The main activity in project scope definition is to

a)

a.      Select team members

b)

b.      Define the work breakdown structure

c)

c.      Analyze the current budget plan

d)

d.      Set up the meeting on project

e)

e.      Meet with team members

109.

Project Control will be:

a)

a.      Before construction

b)

b.      During construction

c)

c.      Throughout the process

d)

d.      After construction

110.

Which is not part of Scope Management?

a)

a.      Execute Scope

b)

b.      Define scope

c)

c.      Verify Scope

d)

d.      None of the above

111.

Process to identify, study, analyze, and rectify root cause of incidents is called:

a)

a.      Quality Control Procedures

b)

b.      Cause and Effect Analysis

c)

c.      Pareto Analysis

d)

d.      Risk Opportunity Management

112.

In the context of time management, which is not a typical type of activity dependency:

a)

a.      Mandatory dependency

b)

b.      Discretionary dependency

c)

c.      Multiple dependency

d)

d.      External dependency

113.

Which is not a resource related to activities

a)

a.      Material

b)

b.      Time

c)

c.      Manpower

d)

d.      Machinery

114.

Process of decomposing deliverables into smaller, more manageable components is complete when

a)

a.      Each work element can be found in the WBS

b)

b.      Project justification has been established

c)

c.      Change request have occurred

d)

d.      Cost and duration estimates can be developed

115.

Project life cycle is different than product life cycle in that project life cycle:

a)

a.      Is different for each industry

b)

b.      Covers different project

c)

c.      Describes project management activities

d)

d.      Does not incorporate methodology

116.

Best time to assign a project manager to a project is during:

a)

a.      Closing

b)

b.      Monitoring and Controlling

c)

c.      Execution

d)

d.      Initiation

117.

The final step in the definition of a work breakdown structure is to

a)

a.      Develop the responsibility matrix

b)

b.      Assign the cost account to a manager

c)

c.      Assign the work package to a manager

d)

d.      Assign codes for each activity of the work package

118.

What are the most important components of sustainability?

a)

a.      Environmental

b)

b.      Social

c)

c.      Economical

d)

d.      All are equally important