wayground logo

Free Printable Worksheets

NEW

Font size

S
M
L
XL
Worksheets

How to Create a Timeline in Microsoft Project

Total questions: 72

Worksheet time: 1hrs 12mins

Name
Class
Date
1.

In Microsoft Project 2016, what is the first step to build a basic project timeline when no template is provided?

a)

Create a Task List by entering tasks under Task Name

b)

Turn on the built-in Timeline template in Project Options

c)

Enable automatic task generation from Outlook

d)

Import a schedule from Excel before adding tasks

2.

According to the tutorial, which version feature makes Microsoft Project 2016 more robust compared with earlier releases?

a)

A built-in Timeline template for all projects

b)

A handy search tool called Tell Me for finding features

c)

Automatic vendor contact management

d)

Exclusive file format incompatible with 2010/2013

3.

When creating the task list, what guidance is given about ordering tasks?

a)

Enter tasks alphabetically for easier lookup

b)

Prioritize tasks in the order they need to be completed

c)

Sort tasks by responsible resource first

d)

Group tasks by duration length

4.

Which action adds a new task name to your project when starting from a blank file?

a)

Open Microsoft Project, click Blank Project, and type in a cell under Task Name

b)

Create a new calendar and assign it to a resource

c)

Switch to the Report tab and insert a chart

d)

Right‑click the Gantt chart bars and choose New Task

5.

What is the correct procedure to enter start and finish dates for a task so that duration is calculated automatically?

a)

Type dates into Notes and let Project infer duration

b)

Click the Start cell to select a date, then tab to the Finish cell and enter the end date

c)

Enter duration first and Project fills Start/Finish with today's date

d)

Use the Predecessors column only; dates are not entered manually

6.

What appears when you click the down arrow in a Start or Finish cell while entering dates?

a)

A resource allocation dialog

b)

A calendar you can use to select a date

c)

A predecessor linking wizard

d)

A baseline variance report

7.

As you add Start and Finish dates, what visual change occurs in the right‑hand pane?

a)

Milestone diamonds are hidden

b)

Bar charts are added to the timeline

c)

Critical path turns red automatically

d)

Resource histogram displays by default

8.

Which tab must you click before adding tasks to the Timeline bar above the task list?

a)

Task tab

b)

View tab

c)

Project tab

d)

Format tab

9.

After switching to the required tab, how do you add a task to the Timeline?

a)

Drag the task bar into the Timeline pane

b)

Right‑click a Task cell and choose Add to Timeline

c)

Enable Timeline template and tasks populate automatically

d)

Enter the task name directly into the Timeline bar

10.

Which column shows the automatically calculated amount of time after Start and Finish dates are entered?

a)

Predecessors

b)

Duration

c)

Task Mode

d)

Resource Names

11.

Within the Report tab, how do you run the Resource Cost Overview specifically?

a)

Click Visual Reports and choose Cash Flow

b)

Click Costs dropdown and select Resource Cost Overview

c)

Click In Progress and choose Earned Value Report

d)

Click Dashboards and select Task Cost Overview

12.

If the scheduling options set Auto scheduled tasks scheduled on: Manually Scheduled, what is the practical implication for newly auto scheduled tasks?

a)

They will respect calendar defaults but not constraints

b)

They will be converted to fixed units automatically

c)

They will honor manual dates rather than recalculating automatically

d)

They will be split into in-progress segments by default

13.

According to the instructions, what is the primary purpose of tracking tasks in Microsoft Project?

a)

To determine if tasks are on time or behind schedule

b)

To automatically assign resources to tasks

c)

To export the Gantt chart to Excel

d)

To lock the project so no changes can be made

14.

Which tab should you click to see task options and mark a task as on track?

a)

Resource tab

b)

Task tab

c)

View tab

d)

Report tab

15.

Where is the Mark on Track button located when updating a task’s status?

a)

In the Quick Access Toolbar

b)

In the ribbon after selecting the Task tab

c)

Inside the Update Tasks dialog box

d)

In the Gantt chart’s right-click menu

16.

Which predetermined percentages can be used to denote task progress directly from the ribbon?

a)

10%, 30%, 60%, 90%

b)

0%, 25%, 50%, 75%, 100%

c)

5%, 20%, 40%, 80%, 100%

d)

0%, 20%, 40%, 60%, 80%

17.

What immediate visual change appears on the Gantt chart when a predetermined percentage is applied to a task?

a)

The task bar color changes to red

b)

A line is drawn through the corresponding task bar indicating completion amount

c)

The task bar disappears until refreshed

d)

A pop-up notes are added to the task

18.

Which action should you take to update a task that has fallen behind or finished early?

a)

Delete and recreate the task

b)

Open Project Options

c)

Click the down arrow next to Mark on Track and choose Update Tasks

d)

Switch to the Report tab and print the status

19.

When using Update Tasks, what types of changes can you make in the dialog box?

a)

Only change resource assignments

b)

Update status and change start and end dates

c)

Export the task to CSV

d)

Enable baseline tracking only

20.

In the Update Tasks dialog, which field directly indicates progress as a fraction of completion?

a)

Actual work

b)

% Complete

c)

Remaining duration

d)

Predecessors

21.

If you want to quickly mark the selected tasks as half complete, which ribbon control should you use?

a)

Respect Links

b)

50% Complete button among predetermined percentages

c)

Inactivate

d)

Manage Tasks pane

22.

Why is keeping task status updated throughout the project important?

a)

It enables accurate monitoring of schedule performance

b)

It automatically increases standard rates

c)

It disables manual scheduling

d)

It merges multiple projects into one

23.

Which view is the default view in MS-Project 2016 and divides the window into a task table and a time scale?

a)

Network Diagram view

b)

Calendar view

c)

Gantt Chart view

d)

Task Usage view

24.

In MS-Project 2016, what does the task table (left area) primarily list according to the description?

a)

Project tasks with their accompanying information

b)

Only resource names and costs

c)

Milestones without dates

d)

Baseline snapshots only

25.

What do the task bars in the time scale area of the Gantt Chart view show?

a)

Actual costs by resource

b)

Duration from planned start to planned finish dates

c)

Team communication history

d)

Risk severity levels

26.

Which UI elements are highlighted as part of MS-Project 2016’s interface making it familiar to MS-Office users?

a)

Command Line and Macros pane

b)

Ribbon, Quick Access toolbar, Backstage view, and context-sensitive menus

c)

Only classic menus without toolbars

d)

Touch-only navigation with gesture controls

27.

According to Figure C.1, which control lets you quickly switch between views at the bottom of the window?

a)

Zoom Slider

b)

View Shortcut

c)

Timeline Toggle

d)

Calendar Picker

28.

When starting MS-Project 2016 to create a new project, which action opens a blank project from the Start screen?

a)

Select Import Existing Plan

b)

Click Blank Project in the right pane

c)

Choose New from the Help menu

d)

Open Calendar and add a task

29.

By default, what start date does MS-Project 2016 use for a new project before you change it?

a)

The earliest task’s start date

b)

The current system date

c)

The first day of the fiscal year

d)

No date until tasks are entered

30.

Which sequence correctly navigates to set the project start date to 1st of August 2018?

a)

File tab > Options > Schedule > Start Date

b)

Project tab > Project Information > Start Date field and calendar pick > OK

c)

Resource tab > Change Working Time > Start Date field > Apply

d)

View tab > Tables > Entry > Start Date column > Save

31.

What primary purpose does MS-Project 2016 serve according to the introduction?

a)

Graphic design for marketing campaigns

b)

Assisting managers to effectively manage projects by simplifying tasks like linking, assigning, and scheduling

c)

Financial accounting and tax filing

d)

Customer relationship management and ticketing

32.

In the Gantt Chart view, what happens when you move the separator bar between the time scale and task table?

a)

It deletes tasks from the table

b)

It zooms the timeline automatically

c)

It displays more of either the time scale or the task table area

d)

It opens the Project Information dialog

33.

In MS-Project 2016, what visual icon indicates a manually scheduled task in the Task Mode field?

a)

A push pin icon

b)

A calendar icon

c)

A stopwatch icon

d)

A chain link icon

34.

Which units can be used to enter task duration when manually scheduling in MS-Project 2016? Select the best answer.

a)

Only days (d)

b)

Months (mo), weeks (w), days (d), hours (h), or minutes (m)

c)

Only hours (h) and minutes (m)

d)

Weeks (w) and days (d) only

35.

By default, how are new tasks initially scheduled when you start a project in MS-Project 2016?

a)

Automatically scheduled with fixed dates

b)

Manually scheduled, allowing full control of duration and dates

c)

Unscheduled until constraints are added

d)

Auto-scheduled with a 3-day estimate

36.

When you change the project Start date in the Project Information dialog box, where is this change reflected?

a)

Only in the Resource Sheet

b)

In the Network Diagram view

c)

In the time scale of the Gantt Chart view

d)

Only in the Task Usage view

37.

While creating a manually scheduled task, you enter Start as 1st Aug 2018 and Duration as 1w. What will MS-Project 2016 do next?

a)

Leave Finish blank until you enter it manually

b)

Automatically fill the Finish field and draw a task bar for the timeframe

c)

Convert the task to auto-scheduled

d)

Prompt to add resource assignments before calculating dates

38.

Which statement best describes automatically scheduled tasks in MS-Project 2016?

a)

Dates and durations are fixed by the user and never recalculated

b)

Project automatically calculates dates and durations and marks them with a Gantt-bar icon in Task Mode

c)

Auto-scheduled tasks cannot be linked

d)

Auto-scheduled tasks always use a 3-day default

39.

When you switch a task’s Task Mode to Auto Scheduled, what default duration does MS-Project 2016 assign before you confirm the data?

a)

0 days

b)

1 day (with “?” indicating an estimate)

c)

3 days

d)

1 week

40.

After setting a task to Auto Scheduled, you change the Duration to 1d. What happens to the dates?

a)

Start and Finish must be retyped; no recalculation occurs

b)

Project recalculates the Finish date and updates the Finish field

c)

Only the Start date updates; Finish remains the same

d)

The task converts to manual scheduling

41.

According to the instructions, which sequence of task names includes auto-scheduled tasks followed by a manual task?

a)

Install Cabinet; Finish Electrical; Install Appliance

b)

Carpentry Pick Up; Install Appliance; Finish Electrical (manual)

c)

Finish Tub, Wall; Install Cabinet; Carpentry Pick Up

d)

Install Appliance; Carpentry Pick Up; Install Cabinet

42.

What is the default task relationship created by MS-Project 2016 when linking tasks?

a)

Start-to-start: both tasks begin together

b)

Finish-to-start: the first task must finish before the second starts

c)

Finish-to-finish: both tasks finish at the same time

d)

Start-to-finish: the second task finishes when the first starts

43.

Which action allows you to change a task from manual scheduling to automatic scheduling (or vice versa) at any point during a project?

a)

Open Project Information and edit the Calendar

b)

Change the Task Mode field for the task

c)

Modify the Resource Sheet to trigger recalculation

d)

Insert a constraint in the Predecessors column

44.

A project begins with limited information and macro-level planning. Which scheduling approach can be handy at that time?

a)

Automatic scheduling to enforce calculated dates

b)

Manual scheduling to control duration and set tentative dates

c)

Resource leveling to adjust assignments

d)

Critical path compression to reduce duration

45.

In MS-Project 2016, what is the primary purpose of inserting a summary task when organizing project work?

a)

To automatically link all tasks with finish-to-start relationships

b)

To group related tasks under a bold, outdented heading with subtasks indented beneath

c)

To convert manually scheduled tasks into automatically scheduled tasks

d)

To lock task dates so they cannot be adjusted by dependencies

46.

Which ribbon path contains the command used to insert a summary task in MS-Project 2016?

a)

Task tab > Insert group > Insert Summary Task

b)

Project tab > Schedule group > Link Selected Tasks

c)

Resource tab > Properties group > Task Information

d)

View tab > Gantt Chart group > Add to Timeline

47.

When you insert a summary task with existing tasks selected, what immediate change happens to those tasks according to the instructions?

a)

They are deleted from the plan

b)

They become milestones under the summary task

c)

They turn into subtasks beneath the newly created summary task

d)

They are set to 100% complete

48.

After inserting a new summary task, which placeholder text initially populates its Task Name field before you rename it?

a)

b)

c)

d)

49.

According to the update procedure, what numeric range can be entered in the Percent complete box to indicate task progress?

a)

1% to 99%

b)

0% to 50%

c)

0% to 100%

d)

25% to 100%

50.

Which action opens the Task Information dialog box to update percent complete for a specific activity (e.g., Finish Tub, Wall)?

a)

Right-click the task and choose Notes

b)

Double-click the task name in the Task Name column

c)

Select the task and press Ctrl+I

d)

Click the Milestone button on the Task tab

51.

Where is the Percent complete field located when updating a task’s progress through the Task Information dialog?

a)

On the Predecessors tab

b)

On the General tab

c)

On the Resources tab

d)

On the Advanced tab

52.

What visual indicator appears in the time scale after entering a percent complete value and clicking OK?

a)

A blue milestone diamond replaces the task bar

b)

A progress bar is added within the task bar to show completion

c)

The task bar turns red to indicate risk

d)

A calendar icon appears next to the task name

53.

Which quick-update buttons are available on the ribbon for setting task completion without opening the Task Information dialog?

a)

0%, 25%, 50%, 75%, and 100% complete

b)

10%, 20%, 40%, 60%, and 80% complete

c)

10%, 30%, 60%, and 90% complete

d)

5%, 25%, 50%, and 95% complete

54.

When organizing tasks under a summary task, how are the summary and its subtasks visually formatted by default?

a)

Summary tasks are italicized and subtasks are bold

b)

Summary tasks are bold and outdented; subtasks are indented beneath them

c)

Both summary and subtasks are underlined

d)

Subtasks are outdented while summary tasks are indented

55.

In MS Project 2016, which resource type best represents people or machinery assigned to tasks that incur an hourly cost?

a)

Material resource

b)

Work resource

c)

Cost resource

d)

Generic resource

56.

You are adding a resource named Graham in the Resource Sheet. Which field must be set to ensure he is treated as a person whose time can be scheduled?

a)

Type set to Work

b)

Material set to Steel

c)

Cost Accrual set to Start

d)

Units set to 0%

57.

According to the instructions, what hourly rate should you enter in the Std. Rate field for the Electricians group when adding Graham?

a)

$15

b)

$20

c)

$25

d)

$30

58.

When adding the second resource, John, which group and standard rate should be associated with him?

a)

Electricians; Std Rate $20

b)

Carpenters; Std Rate $30

c)

Plumbers; Std Rate $25

d)

Painters; Std Rate $18

59.

Which sequence correctly opens the dialog to change a resource’s work hours in MS Project 2016?

a)

Open Task Information > Advanced tab > Calendar

b)

Double-click resource name > General tab > Change Working Time

c)

Right-click the task > Information > Resources

d)

File menu > Options > Schedule

60.

To set Monday through Friday to specific working times for John, which option must be selected in the Details for "[Default]" dialog?

a)

Use times from base calendar

b)

Set days to nonworking time

c)

Set day(s) to these specific working times

d)

Override resource calendar with project calendar

61.

After selecting Monday through Friday, what From and To times should be entered to reflect John’s schedule?

a)

8:00 AM to 5:00 PM

b)

7:30 AM to 4:30 PM

c)

9:00 AM to 6:00 PM

d)

7:00 AM to 3:00 PM

62.

What is the primary purpose of adding resources to your project before assigning them to tasks?

a)

To automatically complete tasks without scheduling

b)

To make them available for assignment to tasks within the project

c)

To lock the project calendar from changes

d)

To convert cost resources into materials

63.

In MS Project 2016, which action switches the view to Gantt Chart before assigning a resource to a task?

a)

Click Gantt Chart on the View tab in the Task Views group

b)

Open Task Details Form from the Resource tab

c)

Choose Timeline on the View tab under Zoom

d)

Enable Network Diagram from the Report tab

64.

When assigning a single resource in the task table, where do you click to select and check the resource name?

a)

In the Resource Names field of the relevant task

b)

In the Duration field of the task

c)

In the Task Name column header

d)

In the Indicators column to open the dialog

65.

While assigning Graham to the Finish Electrical task, what is the correct step to confirm the assignment using the drop-down list?

a)

Click the down arrow in Resource Names and check the box next to Graham

b)

Type Graham in the Notes field and press Enter

c)

Right-click the task and choose Mark on Track

d)

Open Assign Resources and set Graham’s Max Units to 0%

66.

What should you do if the Resource Names column is not visible in the task table while preparing to assign a resource?

a)

Use the scroll bar or move the separator between the Gantt-chart area and the task table to display it

b)

Switch to Calendar view and back to Gantt Chart

c)

Run a report to refresh the table

d)

Delete and reinsert the task to reveal the column

67.

According to the note in Figure C.14, what does a burning man (red person) icon in the Indicators field signify?

a)

The resource is overallocated

b)

The task is on the critical path

c)

The task has a deadline

d)

The task contains a hyperlink

68.

What is the primary purpose of assigning multiple resources to a single task in MS Project 2016?

a)

To reduce the amount of time needed to complete the task

b)

To increase the task’s baseline cost automatically

c)

To lock the task against rescheduling

d)

To prevent resource leveling from changing assignments

69.

Which Ribbon tab and group contain the Assign Resources button used to add multiple resources to a task?

a)

Resource tab, Assignments group

b)

View tab, Task Views group

c)

Task tab, Schedule group

d)

Project tab, Properties group

70.

What is the correct sequence to assign multiple resources using the Assign Resources dialog for the Install Appliance task?

a)

Select the task, open Assign Resources, choose Graham and click Assign, then choose John and click Assign, and finally click Close

b)

Open Task Information, set constraint type, then add Graham and John in Notes, click OK

c)

Select John in Resource Sheet, set Max Units, then link tasks, and click Close

d)

Switch to Network Diagram, select Graham and John, and click Auto Schedule

71.

Where in the Assign Resources dialog do you select the people to add to the task?

a)

In the Resource Name column of the dialog

b)

In the Task Name column of the Gantt table

c)

In the Indicators field of the task row

d)

In the Duration box of Task Information

72.

Which step explicitly closes the Assign Resources dialog after adding Graham and John to the task?

a)

Click the Close button

b)

Press F9 to recalculate

c)

Open Task Details Form

d)

Turn on Manual Scheduling