1.

Which statement BEST sums up how PRINCE2 management products are used in an Agile context?

a)

They are discarded because Agile doesn’t use documentation

b)

They must be used exactly as in traditional PRINCE2 with no changes

c)

They are still needed but can be tailored in form and detail, sometimes being represented by boards or other information radiators

d)

They are fully replaced by the product backlog

2.

Which Agile framework is lightweight and timeboxed, using sprints, a Product Owner, Scrum Master and Developers?

a)

Kanban

b)

Waterfall

c)

Scrum

d)

Lean Startup

3.

Which Agile approach is flow-based, emphasising limiting work-in-progress and managing flow on a board?

a)

Scrum

b)

Kanban

c)

Lean Startup

d)

Waterfall

4.

Which approach is most associated with MVP and the build-measure-learn cycle?

a)

Lean Startup

b)

Scrum

c)

Kanban

d)

Waterfall

5.

What is a timebox?

a)

A fixed amount of money for a project

b)

A fixed, maximum length of time for an activity, after which it ends regardless of how much is done

c)

A box where issues are stored

d)

A list of time estimates

6.

In Scrum, what is the fixed-length timebox where a small increment of product is created?

a)

Program

b)

Release

c)

Sprint

d)

Phase

7.

Which statement BEST describes Waterfall compared to Agile?

a)

Waterfall is iterative and incremental

b)

Waterfall is a linear, sequential development approach

c)

Waterfall always uses user stories

d)

Waterfall uses sprints and timeboxes

8.

What is a product backlog?

a)

A list of completed tasks

b)

A prioritised list of everything that might be needed in the product

c)

A schedule of staff holidays

d)

A list of technical defects only

9.

What is a sprint backlog?

a)

All the work on the project

b)

A list of risks for the sprint

c)

The set of product backlog items selected for a sprint plus a plan for delivering them

d)

A list of impediments

10.

Which statement BEST describes a user story?

a)

A detailed technical specification

b)

A short, simple description of a requirement from the user’s perspective

c)

A legal contract between customer and supplier

11.

Which is a common user story format?

a)

“As a , I want so that ”

b)

“If then else ”

c)

“Given when then ”

d)

“Who, what, when, where, why” as a paragraph

12.

What is an epic?

a)

A very high-priority defect

b)

A high-level, larger requirement that will later be broken down into smaller user stories

c)

A completed user story

d)

A detailed test script

13.

What does Definition of Done (DoD) describe?

a)

When the budget is spent

b)

The criteria for a story to be considered complete and releasable

c)

The order of items in the backlog

d)

The process for escalating issues

14.

What is the purpose of the Definition of Ready (DoR)?

a)

To confirm the project is justified

b)

To define when a user story is clear enough to be taken into a sprint

c)

To describe when the team can close a project

d)

To define when a risk can be closed

15.

What is the primary purpose of a daily stand-up (daily Scrum)?

a)

To re-negotiate the contract

b)

To assign blame for delays

c)

To quickly share information, inspect progress and surface impediments

d)

To run a detailed planning session for the next quarter

16.

What is the typical timebox for a daily stand-up?

a)

5 minutes

b)

15 minutes or less

c)

2 hours

d)

All morning

17.

What is a retrospective?

a)

A meeting to estimate the product backlog

b)

A meeting to look back on a timebox and identify improvements

c)

A meeting to sign the contract

d)

A meeting to re-prioritise the Business Case

18.

What is the primary output of a retrospective?

a)

A new Definition of Done

b)

A list of new features

c)

Concrete improvement actions for the next timebox

d)

A new project mandate

19.

What is a burn-down chart?

a)

A chart showing the team’s mood over time

b)

A chart showing remaining work over time in a sprint or release

c)

A chart showing costs against budget

d)

A chart showing risk probability

20.

What is a burn-up chart?

a)

A chart showing how much work has been completed over time, compared to total scope

b)

A chart showing staff turnover

c)

A chart tracking only defects

d)

A chart showing cost to completion

21.

What is velocity in Agile?

a)

The number of people on the team

b)

The rate of progress a team makes, often measured in story points completed per sprint

c)

The maximum number of tasks a team can handle

22.

How is velocity typically used?

a)

To punish teams that deliver fewer story points

b)

To empirically forecast how much work the team might deliver in future sprints

c)

To compare different teams across the organisation

d)

To calculate staff salaries

23.

What is a spike in Agile?

a)

A process to escalate variances from plan

b)

A piece of exploratory work used to learn about a requirement, risk or technical uncertainty

c)

A defect with high severity

d)

A security penetration test

24.

Which of the following is NOT a common Agile estimation technique?

a)

Story points

b)

T-shirt sizing

c)

Fibonacci sequence

d)

Exact hours for every task in a Gantt chart

25.

Why do many teams use the Fibonacci sequence (1, 2, 3, 5, 8, 13…) for story points?

a)

Because it is legally required

b)

To reflect increasing uncertainty with bigger items and avoid false precision

c)

To ensure all stories are the same size

d)

To calculate project cost directly

26.

What is T-shirt sizing in Agile estimation?

a)

Guessing how many T-shirts can be printed per sprint

b)

Categorising items as XS, S, M, L, XL to represent relative size/effort

c)

Measuring the size of the team

d)

Assigning story points based on clothes sizes literally

27.

What is an information radiator?

a)

A secure store for paper documents

b)

A communication channel that hides information from outsiders

c)

A visible display of key information (e.g. board, chart, dashboard) accessible to everyone

d)

A tool used only by the Project Board

28.

Which of the following is a GOOD example of an information radiator?

a)

A confidential email archive

b)

A physical or digital Kanban board showing work states

c)

A private notebook owned by the Project Manager

d)

A locked cabinet containing reports

29.

In Kanban, what is Work-In-Progress (WIP)?

a)

The number of completed tasks in the last sprint

b)

The items currently being worked on

c)

The total size of the backlog

d)

The number of impediments raised

30.

What is the purpose of WIP limits in Kanban?

a)

To reduce transparency

b)

To limit how many items can be in a given state, improving flow and reducing multitasking

c)

To restrict the number of people in a team

d)

To stop new work from being started at all

31.

What is the main focus of Kanban?

a)

Timeboxed sprints

b)

Managing flow and improving throughput

c)

Creating detailed upfront documentation

d)

Fixing scope and ignoring change

32.

Which Scrum event is mostly about planning what can be done in the upcoming sprint?

a)

Sprint review

b)

Sprint retrospective

c)

Sprint planning

d)

Daily Scrum

33.

Which Scrum event focuses on inspecting the increment and getting feedback from stakeholders?

a)

Sprint retrospective

b)

Sprint review

c)

Daily Scrum

d)

Backlog refinement

34.

Which Scrum event is dedicated to team reflection and improvement?

a)

Sprint review

b)

Sprint planning

c)

Sprint retrospective

d)

Daily Scrum

35.

What is the primary purpose of backlog refinement (grooming)?

a)

To finalise the project budget

b)

To break down, clarify and estimate backlog items so they are ready for future sprints

c)

To approve the Business Case

d)

To sign off the end of the project

36.

What is lead time in a flow-based Agile system?

a)

Time from when work starts to when it finishes

b)

Time from when a request is made to when it is delivered

c)

Time from start of sprint to end of sprint

d)

Time from project approval to go-live

37.

Which term describes the rate at which work items finish over a period of time?

a)

Throughput

b)

Velocity

c)

WIP

d)

Lead time

38.

Which of these best describes the role of Lean Startup within PRINCE2 Agile?

a)

A full replacement for PRINCE2

b)

An approach that can be used to test ideas early with MVPs and pivot if needed

c)

A technique for calculating stage tolerances

d)

A mandatory framework for all projects

39.

In Lean Startup, what does "pivot" mean?

a)

To cancel a project

b)

To change direction based on learning, while keeping some elements the same

c)

To freeze requirements

d)

To move the team to another building

40.

Which statement BEST describes the purpose of a sprint?

a)

To deliver a full, final product

b)

To provide a fixed period to deliver a potentially releasable increment and inspect/adapt

c)

To finalise the contract

d)

To deliver all project documentation

41.

What does it usually mean if a team's velocity increases over a few sprints?

a)

They have cheated the estimation process

b)

The team may be delivering more story points per sprint, though this must be interpreted carefully

c)

The project cost has gone down

d)

Risks have been eliminated

42.

Which statement about velocity is the safest?

a)

It is an exact measure of productivity and can be used to rank teams

b)

It is team-specific and best used for that team's own forecasting

c)

It should always increase every sprint

d)

It must be the same for all teams

43.

What is a release in Agile?

a)

A single user story

b)

A batch of product increments made available to users or customers

c)

A phase of the waterfall lifecycle

d)

A type of Kanban column

44.

In an Agile context, what does “incremental delivery” mean?

a)

Delivering everything at once at the end

b)

Delivering the product in small pieces that build up over time

c)

Delivering only documentation first

d)

Delivering only non-functional requirements

45.

Which statement BEST describes iterative development?

a)

Doing something once and never revisiting it

b)

Repeating cycles of building, testing and improving a product

c)

Writing all code, then testing at the very end

d)

Focusing on big design upfront

46.

Which of the following BEST differentiates Agile from Waterfall?

a)

Agile always costs less

b)

Agile delivers value early and often through small increments and frequent feedback

c)

Agile does not require planning

d)

Agile cannot be used with PRINCE2

47.

What is the primary purpose of using burn-down and burn-up charts in PRINCE2 Agile?

a)

To show detailed technical design

b)

To track and communicate progress and forecast completion

c)

To manage HR issues

d)

To plan staff training schedules

48.

Which of these BEST describes an Agile mindset?

a)

Focusing on strict adherence to a single method

b)

Valuing collaboration, learning, responsiveness to change and delivering value early

c)

Removing all governance and documentation

d)

Avoiding feedback from customers

49.

What is the best description of a flow-based Agile approach?

a)

Work is done in fixed sprints only

b)

Work moves continuously across states (e.g. To Do, Doing, Done) with a focus on flow and WIP limits

c)

Requirements are defined once at the start

d)

Work is batched into phases with gates

50.

Which technique is MOST helpful for visualising bottlenecks in a team’s workflow?

a)

Product backlog

b)

Kanban board with WIP limits

c)

Business Case

d)

Stage Plan

51.

Which statement BEST links Agile practices to PRINCE2 Agile?

a)

Agile practices replace the need for PRINCE2

b)

Agile practices provide techniques for delivery, which PRINCE2 uses within its governance and control structure

c)

Agile practices are only allowed at team level and are invisible to the project

d)

Agile practices are only used to write documentation

52.

Which statement BEST describes the PRINCE2 Agile behaviour of transparency?

a)

Keeping information confidential until the end of the project

b)

Making relevant information visible and understandable to those who need it

c)

Communicating only through formal documents

d)

Allowing only the Project Manager to see progress data

53.

Which behaviour is MOST supported by information radiators such as Kanban boards and burn charts?

a)

Exploration

b)

Transparency

c)

Secrecy

d)

Formality

54.

Which behaviour is about people working together, often across customer and supplier boundaries, to achieve a shared goal?

a)

Transparency

b)

Collaboration

c)

Exploration

d)

Self-organisation

55.

A customer representative and developers sit together to clarify requirements during a workshop. Which behaviour is MOST evident?

a)

Collaboration

b)

Exploration

c)

Self-organisation

d)

Transparency

56.

Which behaviour is MOST associated with using face-to-face communication, workshops and whiteboards to share information?

a)

Rich communication

b)

Transparency

c)

Self-organisation

d)

Exploration

57.

What is the key idea behind rich communication?

a)

Only written communication should be used

b)

Using the simplest, most effective channels (often face-to-face) to share complex information

c)

All communication must go through the Project Manager

d)

Relying on long email chains for evidence

58.

Which behaviour is MOST closely associated with teams deciding how to organise their own work within agreed constraints?

a)

Self-organisation

b)

Transparency

c)

Collaboration

d)

Exploration

59.

Which behaviour means “the people doing the work are trusted to plan and organise it”?

a)

Rich communication

b)

Self-organisation

c)

Transparency

d)

Exploration

60.

Which behaviour is MOST associated with learning, experimentation, and trying out ideas to improve products and ways of working?

a)

Transparency

b)

Collaboration

c)

Self-organisation

d)

Exploration

61.

Running a spike to test a technical approach before committing to it is an example of which behaviour?

a)

Rich communication

b)

Exploration

c)

Transparency

d)

Self-organisation

62.

Which PRINCE2 Agile behaviour is MOST supported by regular sprint reviews and demos with stakeholders?

a)

Transparency

b)

Self-organisation

c)

Exploration

d)

Rich communication

63.

Which behaviour helps reduce misunderstandings by encouraging direct, two-way conversation rather than long documents?

a)

Self-organisation

b)

Rich communication

c)

Transparency

d)

Exploration

64.

A team chooses their own way to split work in a sprint, within the scope of an agreed Work Package. Which behaviour is MOST evident?

a)

Self-organisation

b)

Transparency

c)

Collaboration

d)

Exploration

65.

Which behaviour is MOST associated with people from different roles sharing responsibility for success, rather than working in silos?

a)

Transparency

b)

Self-organisation

c)

Collaboration

d)

Exploration

66.

Which behaviour is MOST aligned with the PRINCE2 principle learn from experience?

a)

Transparency

b)

Exploration

c)

Self-organisation

d)

Rich communication

67.

What is the main purpose of the Agilometer?

a)

To measure the Project Manager’s performance

b)

To assess how suitable the project environment is for using Agile approaches

c)

To calculate velocity for the team

d)

To decide which team members should be moved to other projects

68.

Which statement about the Agilometer is CORRECT?

a)

It is used once at the end of the project

b)

It is used only on software projects

c)

It can be revisited over time to see whether Agile usage can be increased or needs to be reduced

d)

It replaces all risk management

69.

The Agilometer helps with which PRINCE2 principle?

a)

Tailor to suit the project environment

b)

Focus on products

c)

Manage by stages

d)

Continued business justification

70.

Which focus area is MOST concerned with how requirements are prioritised and managed (e.g. backlogs, MoSCoW, MVP)?

a)

Rich communication

b)

Frequent releases

c)

Requirements

d)

Agilometer

71.

Which statement BEST describes the Requirements focus area?

a)

It removes the need for a Business Case

b)

It provides guidance on prioritising, refining and managing requirements in an Agile way

c)

It focuses only on technical specifications

d)

It is only concerned with legal contract terms

72.

Which focus area is MOST concerned with ensuring that communication channels are effective, timely and appropriate?

a)

Rich communication

b)

Frequent releases

c)

Requirements

d)

Agilometer

73.

Which focus area is MOST likely to encourage workshops, stand-ups and visual boards?

a)

Agilometer

b)

Requirements

c)

Rich communication

d)

Frequent releases

74.

Which focus area is MOST concerned with how often the project delivers increments of the product to users or customers?

a)

Rich communication

b)

Requirements

c)

Frequent releases

d)

Agilometer

75.

What is the MAIN benefit of frequent releases in PRINCE2 Agile?

a)

They eliminate the need for testing

b)

They allow earlier feedback and earlier realization of benefits

c)

They replace the need for a Business Case

d)

They guarantee that scope will not change

76.

Which focus area MOST supports the PRINCE2 Agile target “embrace change”?

a)

Requirements

b)

Agilometer

c)

Frequent releases

d)

Rich communication

77.

Which focus area MOST supports the PRINCE2 Agile target “be on time and hit deadlines” by using short, controlled release cycles?

a)

Agilometer

b)

Frequent releases

c)

Requirements

d)

Rich communication

78.

Which behaviour is MOST enhanced by frequent, open discussions in workshops between customer and supplier teams?

a)

Transparency

b)

Collaboration

c)

Self-organisation

d)

Exploration

79.

A team decides to experiment with a new way of running retrospectives to see if it leads to better improvements. Which behaviour is MOST being demonstrated?

a)

Transparency

b)

Exploration

c)

Collaboration

d)

Rich communication

80.

Which behaviour BEST supports using progress information (like burn charts and Kanban boards) to make decisions without hiding bad news?

a)

Self-organisation

b)

Collaboration

c)

Exploration

d)

Transparency

81.

scope?

a)

Requirements

b)

Rich communication

c)

Frequent releases

d)

Agilometer

82.

A project uses frequent releases, each followed by user feedback that may reprioritise the backlog. Which two focus areas are MOST evident?

a)

Requirements and rich communication

b)

Frequent releases and requirements

c)

Agilometer and rich communication

d)

Rich communication and Agilometer

83.

The Agilometer highlights that the organisation’s culture is risk averse and documentation-heavy. What does this suggest?

a)

Agile cannot be used at all

b)

Agile must be used with very low levels of governance

c)

Agile can still be used, but PRINCE2 controls and Agile techniques must be tailored to manage these risks

d)

Waterfall must be used instead of PRINCE2

84.

Which behaviour is MOST likely to help a team respond quickly when a risk is identified in the Agilometer assessment?

a)

Transparency

b)

Self-organisation

c)

Exploration

d)

Collaboration

85.

Which focus area helps ensure that requirements are at the right level of detail at the right time?

a)

Requirements

b)

Frequent releases

c)

Rich communication

d)

Agilometer

86.

In PRINCE2 Agile, which behaviour BEST supports the idea that “people closest to the work know best how to do it”?

a)

Transparency

b)

Self-organisation

c)

Rich communication

d)

Exploration

87.

The project team holds a vision workshop with key stakeholders at the start to discuss goals, constraints and expectations. Which behaviour and focus area are MOST evident?

a)

Exploration and frequent releases

b)

Collaboration and rich communication

c)

Self-organisation and Agilometer

d)

Transparency and requirements

88.

Regularly inspecting whether Agile practices are working well and adjusting them is MOST closely linked to which behaviour?

a)

Exploration

b)

Collaboration

c)

Transparency

d)

Self-organisation

89.

Which behaviour is MOST visible when the team shares “bad news” early and honestly rather than hiding it?

a)

Transparency

b)

Exploration

c)

Collaboration

d)

Rich communication

90.

Which focus area is MOST likely to discuss how to handle dependencies between requirements, such as ordering of features?

a)

Agilometer

b)

Requirements

91.

Which focus area is MOST concerned with choosing appropriate channels such as stand-ups, chats, and workshops instead of long documents?

a)

Requirements

b)

Rich communication

c)

Frequent releases

d)

Agilometer

92.

Which behaviour is MOST encouraged when a project uses co-located teams or good online tools to communicate quickly?

a)

Transparency

b)

Self-organisation

c)

Rich communication

d)

Exploration

93.

Which focus area MOST directly supports using sprint reviews, demos and pilot releases to test how well the product meets user needs?

a)

Frequent releases

b)

Requirements

c)

Rich communication

d)

Agilometer

94.

Which behaviour is MOST likely to be discouraged if all decisions are made by the Project Manager and the team is given no freedom?

a)

Transparency

b)

Self-organisation

c)

Collaboration

d)

Exploration

95.

Which focus area MOST helps a project decide how “agile” it can safely be given its environment?

a)

Requirements

b)

Rich communication

c)

Frequent releases

d)

Agilometer

96.

Which behaviour primarily supports trying out new product ideas, such as MVPs or prototypes, to see how customers react?

a)

Self-organisation

b)

Exploration

c)

Transparency

d)

Collaboration

97.

What is a key reason PRINCE2 Agile emphasises frequent releases?

a)

To avoid using backlogs

b)

To give the Project Board fewer decisions

c)

To allow benefits and value to be realised earlier and reduce risk of building the wrong thing

d)

To minimise collaboration between business and technical people

98.

Which behaviour is MOST supported when a team regularly reviews how transparent they are and improves their boards and reporting?

a)

Exploration

b)

Self-organisation

c)

Transparency

d)

Collaboration

99.

Which statement BEST connects the behaviours and focus areas in PRINCE2 Agile?

a)

Behaviours define how people should act, and focus areas show where to apply Agile thinking and techniques

b)

Behaviours are optional, focus areas are mandatory

c)

Behaviours replace PRINCE2 principles, focus areas replace processes

d)

Behaviours are only for delivery teams, focus areas only for the Project Board