wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

Project Evaluation and Finance Worksheet

Total questions: 84

Worksheet time: 42mins

Name
Class
Date
1.

If the annual depreciation charge for a project is increased in a particular operating year, what is the expected impact on the project’s after-tax cash flow for that year?

a)

It raises the project’s after-tax cash inflow because of the depreciation tax shield.

b)

It does not influence cash flow at all since depreciation is a non-cash expense.

c)

It increases the project’s accounting profit.

d)

It increases the amount of corporate income tax the project must pay.

2.

Which of the following is a key limitation of sensitivity analysis in project evaluation?

a)

It ignores the statistical correlation among input variables.

b)

It cannot test two variables moving at the same time.

c)

It cannot identify which input variable is most critical to project viability.

d)

It does not allow us to change one driver while holding others constant.

3.

When appraising the market competitiveness of a project's output (product/service), which aspects are typically assessed?

a)

The distribution network and sales promotion strategy.

b)

The product’s technical performance, perceived quality, and usefulness.

c)

The pricing level relative to competitors.

d)

All of the above.

4.

You are comparing two mutually exclusive investment projects whose economic lives (useful operating lives) are not the same. Which decision criterion is the most appropriate to make a fair comparison?

a)

Internal Rate of Return (IRR).

b)

Net Present Value (NPV).

c)

Payback Period / Discounted Payback Period.

d)

Equivalent Annual Annuity (EAA).

5.

In risk analysis using simulation (e.g. Monte Carlo simulation), what is considered a drawback?

a)

You must specify the probability distribution for each key input variable.

b)

You cannot model several inputs fluctuating at the same time.

c)

You cannot embed relationships between variables in the model.

d)

The method cannot estimate the probability that the project succeeds or fails.

6.

Suppose Project A and Project B yield exactly the same Net Present Value (NPV) when discounted at the required rate of return. This implies:

a)

The two projects generate identical yearly cash flows.

b)

Both projects face the same discount rate by definition.

c)

Both projects deliver equivalent financial value (i.e. equal economic worth) to the investor.

d)

The two projects will report the same net income.

7.

Regarding interest on debt during the construction / implementation phase of a project, which statement is correct?

a)

Only the interest incurred in Year 1 of construction is counted in total investment; later interest is excluded.

b)

Interest accrued during the grace period is not capitalized into the project’s total investment cost.

c)

Interest during construction is always excluded from the project cash flow statement used for appraisal (TIPV cash flow).

d)

Interest during construction refers only to interest without any grace period.

8.

When applying the Capital Asset Pricing Model (CAPM) to estimate the project’s required rate of return, the term RmRfRm - Rf is referred to as:

a)

The market risk premium.

b)

The risk-free benchmark rate.

c)

The prevailing market interest rate.

d)

The adjusted risk-free yield.

9.

For land-use rights with an indefinite term (no expiry), why is the terminal (salvage) value of the land at the end of the project typically assumed to be equal to its original acquisition cost in the cash flow analysis?

a)

Because accounting policy requires it.

b)

Because we only want to capture the project’s “internal” efficiency and ignore external gains.

c)

Because such land-use rights are not depreciated/amortized.

d)

Because any appreciation in land value over time is assumed to be negligible.

10.

The cost of preparing the project’s Environmental Impact Assessment (EIA) report should be treated as:

a)

An other expense that is excluded from both total investment and project cash flows.

b)

A cost outside the total investment and also excluded from cash flow projections.

c)

A cost that is capitalized in total investment but omitted from cash flow calculations.

d)

A cost that is included in total investment and also included in the project cash flow forecast.

11.

An increase in working capital requirement during the year will:

a)

Reduce the project’s investment cash flow.

b)

Increase the project’s operating cash flow.

c)

Reduce the project’s operating cash flow.

d)

Increase the project’s financing cash flow.

12.

Which principle of project cash flow forecasting is NOT correct?

a)

Include opportunity costs in project cash flows.

b)

Project value must be based on incremental cash flows.

c)

Include indirect costs in project cash flows.

d)

Include sunk costs in project cash flows.

13.

If the corporate income tax rate is 20%20\% , when interest expenses increase by 100100 units, then:

a)

After-tax profit increases by 80 units.

b)

After-tax profit decreases by 20 units.

c)

After-tax profit decreases by 80 units.

d)

After-tax profit increases by 20 units.

14.

Projects are classified as independent, dependent, or mutually exclusive projects based on:

a)

Importance and construction scale.

b)

Form of investment.

c)

Project implementing entity.

d)

Investment decision-making purpose.

15.

Which of the following statements indicates that two projects are independent?

a)

Accepting or rejecting this project does not affect accepting or rejecting the other project.

b)

Accepting this project requires abandoning the other project.

c)

None of the statements indicates independence.

d)

Accepting or rejecting this project leads to accepting or rejecting the other project.

16.

The difficulty in analyzing the impact of inflation on project effectiveness is:

a)

Many items cannot be converted from real to nominal prices.

b)

Difficult to estimate the impact of inflation on each project cash flow.

c)

Considering inflation reduces project effectiveness.

d)

Using nominal prices does not accurately estimate financial efficiency.

17.

Which of the following items does NOT belong to operating cash flows under the direct method from the Total Investment perspective?

a)

Interest expenses.

b)

Sales revenue.

c)

Cost of raw material purchase.

d)

Selling staff salaries.

18.

To discount the EPV (Equity Present Value) cash flow of a leveraged project, the discount rate used is:

a)

After-tax weighted average cost of capital (WACC).

b)

Project loan interest rate.

c)

Required return on equity.

d)

Industry average rate of return.

19.

When choosing the project’s design capacity, it is based on which factors?

a)

Organizational and managerial capability, investor’s financial capacity.

b)

All are correct.

20.

The value of an expansion project depends on:

a)

The incremental cash flows generated by the project

b)

The incremental revenue generated by the project

c)

The total cash flows generated by the project

d)

The accounting profit generated by the project

21.

For public-sector projects, the appraisal of socio-economic efficiency is to:

a)

Evaluate the project’s costs and benefits from the perspective of the entire economy and society

b)

All are correct

c)

Identify the project’s benefits from the perspective of the whole economy

d)

Assess the project’s impact on economic development

22.

Which of the following is a funding requirement of a project?

a)

Investment in other enterprises

b)

Financial investment

c)

Debt repayment

d)

Dividend distribution

23.

Economic analysis is the analysis of:

a)

All of the above

b)

Income distribution in the economy

c)

The ability to meet the basic needs of the economy

d)

The project’s contribution to economic growth

24.

Financial analysis of a project is the analysis of financial effectiveness for:

a)

Banks

b)

Investors

c)

All of the above

d)

Shareholders

25.

The project objectives need to be determined in which stage of the project cycle?

a)

Pre-feasibility study

b)

Feasibility study

c)

Investment opportunity study

d)

Project implementation

26.

Which of the following is a characteristic of an investment project?

a)

Human resources required for the project must be identified

b)

All of the above

c)

Potential risks must be identified

d)

The uniqueness of the project’s product must be described

27.

Investment projects are usually implemented within a period of time that is:

a)

With no determined ending time

b)

Short

c)

Relatively long

d)

Can be either short or relatively long

28.

Which of the following statements is correct?

a)

The capital scale of an investment project is often not determined in advance

b)

The definition of a project does not mention capital scale

c)

The total investment of a project is usually very large

d)

None of the above is correct

29.

Market analysis refers to the analysis of:

a)

Markets for project input products

b)

All of the above

c)

Labor market

d)

Markets for project output products

30.

Project liquidation is carried out in which case?

a)

The investment project has reached the end of its operating life

b)

All of the above

c)

The investor is forced to cease operations

d)

The investor goes bankrupt

31.

A project is considered feasible when:

a)

It is practically implementable

b)

All of the above

c)

It complies with all legal regulations

d)

It brings financial and/or socio-economic effectiveness

32.

Project implementation includes:

a)

All of the above

b)

Project preparation

c)

Project operation

d)

Project design and construction

33.

The initial investment capital of a project can take the form of:

a)

Financial assets, tangible assets, and intangible assets

b)

Fixed capital and working capital

c)

All of the above

d)

Equity capital and borrowed capital

34.

A project aimed at improving and enhancing the quality of products, goods, and services is:

a)

A deep investment project (vertical investment)

b)

All of the above

c)

A stand-alone investment project

d)

An expansion investment project

35.

The project analysis framework covers the following aspects:

a)

Market – Technical – Human resources

b)

Market – Technical – Human resources – Finance – Economy – Society

c)

Market – Technical – Human resources – Finance – Economy

d)

Market – Technical – Human resources – Finance

36.

Which of the following statements is correct?

a)

All projects, regardless of investment capital, must go through two stages: pre-feasibility and feasibility studies

b)

Projects with large investment capital must go through both pre-feasibility and feasibility studies, while smaller projects only require a feasibility study

c)

All projects, regardless of investment capital, only need a feasibility study

d)

Depending on the size and nature of the project, the competent authority will decide whether a feasibility study alone is sufficient or if both pre-feasibility and feasibility studies are required

37.

Technical analysis is the analysis of aspects such as:

a)

Project materials and inputs

b)

All of the above

c)

Project construction and equipment installation

d)

Environmental impacts of the project

38.

Private investment projects are aimed at:

a)

Social benefits

b)

Economic benefits

c)

Financial benefits

d)

All of the above

39.

Which of the following is a project investment activity?

a)

Has a start date and an end date

b)

Is done only once

c)

All of the above

d)

Creates a specific product

40.

When deciding whether to invest in a project under consideration, the investor often makes the mistake of:

a)

Accepting a project beyond the investor’s financial capacity

b)

Ignoring a project within the investor’s financial capacity

c)

All of the above

d)

Accepting a bad project and rejecting a good project

41.

The stage in which more accuracy is required for the key project variables is:

a)

Investment opportunity study

b)

Pre-feasibility study

c)

Project operation

d)

Feasibility study

42.

A project can be appraised from which perspective?

a)

Financial

b)

All of the above

c)

Social

d)

Economic

43.

Reviewing once again the financial, economic, and social criteria is carried out in which appraisal stage?

a)

Detailed design

b)

Feasibility study

c)

Pre-feasibility study

d)

Project operation

44.

In financial analysis/appraisal of a project, which price should be used?

a)

Market price

b)

Shadow price

c)

Real price

d)

Economic price

45.

The role of project appraisal is:

a)

To perform audit and inspection functions throughout the project’s economic life

b)

To avoid implementing ineffective projects while not missing valuable investment opportunities

c)

All of the above

d)

To save the economy’s resources and capital

46.

For private investment projects, the basis for state authorities to grant permits or provide support/incentives is:

a)

Feasibility in market, technical, and management aspects

b)

Economic and social efficiency

c)

All of the above

d)

Financial efficiency

47.

At which stage of the project cycle does the investor participate in appraisal?

a)

Feasibility study

b)

Operation stage

c)

Pre-feasibility study

d)

All stages of the project cycle

48.

What measures should the government take when a project brings financial efficiency to the investor but not economic benefits to the economy?

a)

Remove price ceiling regulations

b)

Subsidies

c)

Raise taxes

d)

All of the above

49.

Which of the following statements is correct?

a)

Appraising market, technical, personnel, and management aspects as a basis for financial appraisal

b)

Project appraisal content is based on each analysis and research content of the project

c)

All of the above

d)

Project appraisal clarifies feasibility in all related aspects of the project to be implemented

50.

For a project to be implemented, it must achieve efficiency in:

a)

Economic aspect

b)

Social aspect

c)

All of the above

d)

Financial aspect

51.

A project is considered feasible when it:

a)

Must be feasible under all appraisal perspectives

b)

All of the above

c)

Must ensure legality, scientific validity, and practicality

d)

Must be feasible in all research aspects

52.

What measures should the government take when a project does not bring financial efficiency to the investor but does bring economic benefits to the economy?

a)

Subsidies

b)

All of the above

c)

Reduce taxes

d)

Provide preferential conditions for the project

53.

Which of the following statements is NOT correct?

a)

Project appraisal helps investors determine capital structure for the project

b)

Project appraisal helps investors control risks

c)

Project appraisal helps investors reduce mistakes in decision-making

d)

Project appraisal helps investors make investment decisions to maximize profit

54.

Investors, banks, and shareholders appraise a project from which perspective?

a)

Basic needs

b)

Financial

c)

Income distribution

d)

Economic

55.

Government agencies appraise projects from which perspective?

a)

Economic

b)

Basic needs

c)

Income distribution

d)

All of the above

56.

The reason a company may terminate an existing project and start a new replacement project is:

a)

Changes in the company’s investment strategy

b)

Changes in consumer preferences

c)

The new project has a higher return than the previous one

d)

All of the above

57.

What measures should the government take when a project brings neither financial efficiency to the investor nor economic benefits to the economy?

a)

No subsidies

b)

The government does not need to take any measures

c)

Reduce taxes

d)

Impose a price ceiling

58.

Conservative estimation, which reduces projected benefits while inflating cost estimates, is done in which appraisal stage?

a)

Feasibility study

b)

Pre-feasibility study

c)

Investment opportunity study

d)

Project operation

59.

For public investment projects, the basis for state agencies to make investment decisions is:

a)

Financial efficiency

b)

Economic and social efficiency

c)

All of the above

d)

Feasibility in market, technical, and management aspects

60.

In appraising the competitiveness of a project’s product in the export market, the appraiser must consider:

a)

Competitors in the intended export market

b)

All of the above

c)

Whether quotas or technical barriers are imposed

d)

Importing countries’ standards

61.

The marketing strategy of a project includes:

a)

All of the above

b)

Sales methods

c)

After-sales services

d)

Delivery methods

62.

Appraising the competitiveness of a project’s product involves considering aspects such as:

a)

Product design

b)

Product quality

c)

Product price

d)

All of the above

63.

Market segmentation is based on:

a)

The project’s marketing strategy

b)

Specific customer behavior

c)

The project’s business strategy

d)

All of the above

64.

Customer analysis in market analysis must answer the question:

a)

Who makes the purchase decision and who participates in the decision?

b)

All of the above

c)

Why do customers buy that product?

d)

What products do customers buy in the market?

65.

The target market of a project can be:

a)

Domestic market

b)

Export market

c)

Import-substitute market

d)

All of the above

66.

Market appraisal is the appraisal aspect carried out:

a)

All of the above

b)

Before the technical aspect

c)

After the financial aspect

d)

After the management and personnel aspect

67.

Industry analysis of the project includes:

a)

Industry life cycle

b)

All of the above

c)

Opportunities and level of competition

d)

Key success factors

68.

Market appraisal is the basis for choosing:

a)

Investment scale

b)

Production plan

c)

Project technology and location

d)

All of the above

69.

Market segmentation must meet the requirement:

a)

Each segment must be clearly differentiated from others

b)

All of the above

c)

The segment must have a sufficiently large scale

d)

Customer behavior in the segment should be as similar as possible

70.

The project can distribute products through channels such as:

a)

Retailers

b)

All of the above

c)

Wholesalers

d)

Direct to consumers

71.

Competitor analysis includes:

a)

All of the above

b)

What are the strongest possible reactions from competitors?

c)

What plans or actions are competitors intending to take?

d)

What are the weaknesses of competitors?

72.

Forecasting the output or sales revenue of the project is based on:

a)

Marketing strategy

b)

Market demand

c)

Factory capacity

d)

All of the above

73.

Appraising the current supply-demand situation of the project’s products on the market will help the appraiser understand:

a)

The project’s potential market share

b)

The project’s target market

c)

Market capacity

d)

All of the above

74.

Forecasting the output of the project’s products supplied to the market is based on:

a)

Statistical data from ministries

b)

All of the above

c)

Industry analysis reports from professional organizations

d)

Data from associations

75.

Forecasting the output of the project’s products supplied to the market is based on:

a)

Statistical data from ministries

b)

All of the above

c)

Industry analysis reports from professional organizations

d)

Data from associations

76.

One of the contents of market appraisal is:

a)

Competitors

b)

All of the above

c)

The project’s target market

d)

Customers and market segmentation

77.

In appraising the project’s competitiveness in terms of price, the appraiser must compare the projected selling price with:

a)

Retail prices if the project sells directly to consumers

b)

Import prices if the project substitutes imported goods

c)

Wholesale prices if the project sells through distribution channels

d)

All of the above

78.

The project’s marketing strategy is developed on the basis of:

a)

Potential market

b)

Human and financial resources

c)

The project’s production program

d)

All of the above

79.

Customers in market analysis include:

a)

Customers buying competitors’ products

b)

Customers buying the project’s products

c)

Customers buying substitute products

d)

All of the above

80.

The project’s marketing strategy is developed in order to:

a)

Save selling costs

b)

Achieve the project’s objectives

c)

Attract customer attention to the project’s products

d)

All of the above

81.

Technical appraisal is the aspect carried out:

a)

After the financial aspect

b)

After the management and personnel aspect

c)

After the market aspect

d)

Before the management and personnel aspect

82.

To choose an appropriate technology, the appraiser must consider which factor?

a)

Socio-economic conditions and the economy’s ability to absorb technology

b)

Future technological trends

c)

Requirements of raw materials and ecological/environmental impacts

d)

All of the above

83.

The appraiser must consider the suitability of raw materials in relation to the following factors:

a)

Labor skill level

b)

Local customs and culture

c)

Planned production capacity of the factory

d)

All of the above

84.

Packaging costs depend on:

a)

Means of transporting products

b)

The project’s product policy

c)

Requirements for preserving finished products

d)

All of the above