
PM1 Unit 5
Presentation
•
Business
•
10th Grade
•
Practice Problem
•
Medium
Bobbie Jones
Used 7+ times
FREE Resource
48 Slides • 7 Questions
1
Budget Management
2

Earned Value Management: Definition, Formula & Examples - Video & Lesson Transcript | Study.com
You can open this webpage in a new tab.
3
57
Budget Management
Budget Development
• Good scheduling skills and abilities
• Understanding of the project scope
• Well developed WBS and project
schedule
4
57
Budget Management
Key reasons for overspending…
• Bad Luck
• Overly optimistic initial estimates
• Poor communication
• Poor cost/time estimating practices
5
58
Budget Management
Three methods of estimating
3. Bottom-up Estimating
Decomposition of the work into smaller
packages or more detail. Estimates are
made at the lowest level and then
summarizes, or aggregated, into the
higher level activities.
6
Cost Budgeting
• The planning process that involves
summarizing, or aggregating, the
estimated costs for individual
activities to establish a total cost
baseline for the project.
Budget Management
58
7
Cost Baseline
• Time based budget that is used as a
basis for measuring, monitoring, and
controlling the overall cost
performance of the project.
• Also represents “Planned Value”
Budget Management
58
8
Cost Baseline
Budget Management
58
9
Cost Control
• The process of influencing factors
that create variances, and controlling
changes to the project budget.
Budget Management
58
10
Funding Limit Reconciliation
A cost budgeting tool that involves the comparison and adjustment of the funding limits and the estimated costs by refining the scope and schedule of the project activities. A difference or variance on the planned expenditure and the funding limit usually causes the need for rescheduling of the work to meet the rate of the expenditures.
Budget Management
58
11
Multiple Choice
The board set a target for the project budget during the planning phase. While executing the project, they check to make sure she is within budget. They are looking to determine if they need to refine the scope of the project and change its timeline and costs for activities. Which tool is being used to manage the cost of this project?
cost of quality
cost performance baseline
funding limit reconciliation
vendor bid analysis
12
Project cost control includes:
• Ensuring changes are agreed upon
• Managing changes when they occur
• Assure potential cost overruns do
not exceed authorized funding
• Monitor cost performance and
understand variances
Budget Management
58
13
Project cost control includes:
• Recording all appropriate changes
against the cost baseline
• Preventing incorrect, inappropriate,
or unapproved changes
• Inform stakeholders of approved
changes
• Acting to bring overruns within limits
Budget Management
59
14
Cost Change Control System
• Defines the procedures by which the
cost baseline can be changed.
• WSDOT policy found in the Project
Control & Reporting Guide
• Also documented in the Project
Management Plan
Budget Management
59
15
What is Earned Value Management
(EVM)?
• A method of integrating scope, schedule,
and resources, and for measuring project
performance.
• It compares the amount of work that was
planned with what was actually earned
with what was actually spent to determine
if cost and schedule performance are as
planned.
Earned Value Management
59
16
What is needed for EVM?
• A baseline plan
• A project budget (BAC – Budget at
Completion)
• A project end date
• Tasks are identified & scheduled
• Each task has a budget or effort (resource
loaded / weighting)
• Actuals tracked
Earned Value Management
59
17
Multiple Choice
Mrs. Jones is building a gardent next to her porch. She estimates the work to build this garden will be $250 per day and will take six days to complete. What is the project's budget at completion?
$500
$600
$1,000
$1,500
18
To perform EVM, three values need
to be determined
• Planned Value (PV or BCWS)
• Actual Costs (AC or ACWP)
• Earned Value (EV or BCWP)
Earned Value Management
59
19
Planned Value (PV)
What are the budgeted costs of
the work scheduled?
•Time phased based on baseline
budget
•Only changes when baseline is
changed
•Also referred as “BCWS” & “BAC”
Earned Value Management
60
20
Multiple Choice
A project manager is building a real volleyball machine based on the national competition and has been given a budget of $1,500 and is 40% complete. The team planned to spend $500 a month on the three-month project. The manager is evaluating the status of the project at the end of the first month. What is the project's planned value?
$500
$600
$1,000
$1,500
21
Earned Value Management
60
Actual Costs (AC)
What are the actual costs of the
work performed?
•Based on the actual completion of
work packages
•Actual costs for reported work
•Also referred as “ACWP”
22
Earned Value Management
60
Earned Value (EV)
What are the budgeted costs of
the work performed?
•Based on the actual completion of
work packages
•Baseline value of the reported work
•Also referred as “BCWP”
23
Earned Value Management Example
Task – Drill & install 10 piezometers
• Budget - $100,000 ($10K per piezometer)
• Time – 10 weeks (1 piezometer per week)
At week 5:
• 4 piezometers drilled and installed
• $47,500 spent to date
PV = $50,000
AC = $47,500
EV = $40,000
24
Calculating Earned Value and
interpreting results
• to measure the progress of the project
• help identify trends
• forecast costs
• and identify ways to correct/mitigate
project pitfalls.
Earned Value Management
60
25
Multiple Choice
The high school hired a team to put new blinds in over the summer.
The project should take five days and cost $2,500 to complete. At the end of the second day, the project is 50% complete. What is the project's earned value at the end of the second day?
$500
$750
$1,000
$1,250
26
Cost Variance (CV)
CV = EV - AC
•Good News: If CV value is positive, the project is
currently under budget (spending less than
planned for the work)
•Bad News: If CV value is negative, the project is
currently over budget (spending more than
planned for the work)
Earned Value Management
60
27
Earned Value Management
60
Cost Performance Index
(CPI)
CPI = EV / AC
•Good News: If CPI value is >1 or =1, the project
cost trend is currently under or at planned budget
•Bad News: If CPI value <1, the project cost trend
is currently over budget
28
Earned Value Management
60
Cost Variance % (CV%)
CV% = CV / EV
•Good News: If CV% value is positive, the project
is currently under budget by the CV%
•Bad News: If CV% value is negative, the project is
currently over budget by the CV%
29
Earned Value Management
61
Schedule Variance (SV)
SV = EV - PV
•Good News*: If SV value is positive, the project is
currently ahead of schedule
•Bad News: If SV value is negative, the project is
currently behind schedule
* - not all positive SVs are good
30
Earned Value Management
61
Schedule Performance
Index (SPI)
SPI = EV / PV
•Good News: If SPI value is >1 or =1, the project
schedule trend is currently ahead or on planned
schedule
•Bad News: If SPI value <1, the project schedule
trend is currently behind schedule
31
Earned Value Management
61
Schedule Variance % (SV%)
SV% = SV / PV
•Good News: If SV value is positive, the project is
currently ahead of schedule
•Bad News: If SV value is negative, the project is
currently behind schedule
32
Dropdown
33
Dropdown
34
Match
Facts : AC $400 EV $450 PV $525 BAC $1,000
Calculate each of the following and match it to the correct answer
CPI
CV
SPI
SV
1.125
50
.86
-75
1.125
50
.86
-75
35
Earned Value Management
61
Estimate at Completion
(EAC)
#1
Actual costs to date plus a new estimate for all
remaining work (original plan no longer valid)
EAC = AC + ETC
(ETC🡺Estimate to Complete)
36
Earned Value Management
61
Actual costs to date plus remaining budget
(current variances are viewed as atypical of future
variances)
EAC = AC + BAC - EV
Estimate at Completion
(EAC)
#2
37
Earned Value Management
62
Estimate at Completion
(EAC)
#3 & #4
Actual costs to date plus remaining budget
modified by a performance factor (CPI) (current
variances are viewed as typical of future
variances).
EAC = AC + [(BAC - EV) / CPI]
EAC = BAC / CPI
38
Earned Value Management Example
Task – Drill & install 10 piezometers
• Budget - $100,000 ($10K per piezometer)
• Time – 10 weeks (1 piezometer per week)
At week 5:
• 4 piezometers drilled and installed
• $47,500 spent to date
PV = $50,000
AC = $47,500
EV = $40,000
CV = -$7,500
CPI = 0.82
CV% = -19%
SV = -$10,000
SPI = 0.80
SV% = -20%
39
Earned Value Scenario
62
40
Earned Value Scenario
63
41
Earned Value Scenario
64
42
Earned Value Scenario
65
43
Earned Value Scenario
65
BAC = $100,000 (current project budget)
EV = $42,000 (42% of project completed,
$100,000 planned)
PV = $56,000 (56% of project planned $100,000
completed – initial aging report)
AC = $48,000 (from actual expenditures
reporting)
Is this project on schedule / budget?
Or is it in trouble?
44
Earned Value Scenario
66
Cost Variance (CV):
CV = EV – AC
= $42,000 - $48,000
= - $6,000
Cost Performance Index (CPI):
CPI = EV / AC
= $42,000 / $48,000
= 0.875
Cost Variance % (CV%):
CV% = CV / EV
= - $6,000 / $42,000
= 14% OVER BUDGET
45
Earned Value Scenario
66
Schedule Variance (SV):
SV = EV – PV
= $42,000 - $56,000
= - $14,000
Schedule Performance Index (SPI):
SPI = EV / PV
= $42,000 / $56,000
= 0.750
Schedule Variance % (SV%):
SV% = SV / PV
= - $14,000 / $56,000
= 25% BEHIND SCHEDULE
46
Earned Value Scenario
67
Estimate at Completion (EAC):
Method #1:
EAC = AC + ETC (say $68,000)
= $48,000 + $68,000
= $116,000
(Change Management for $16,000 funds
request)
Method #2:
EAC = AC + BAC – EV
= $48,000 + $100,000 - $42,000
= $106,000
(Change Management for $6,000 funds
request)
47
Earned Value Scenario
67
Estimate to Complete (ETC):
Method #3
EAC = AC + [(BAC – EV) / CPI]
= $48,000 + [($100,000 - $42,000) / 0.875]
= $48,000 + $66,285
= $114,285
(Change Management for $14,285 funds
request)
Method #4
EAC = BAC / CPI
= $100,000 / 0.875
= $114,285
(Change Management for $14,285 funds
request)
48
Earned Value Scenario
68
49
Budget Management
Graphing Earned Value exercise
• Gantt chart baseline (report)
• EVM graph
• Task information
• Cost distribution
• EVM worksheets
50
Budget Management
Graphing Earned Value exercise
• Planned Value (PV) is always shown
in blue with circle nodes
• Actual Cost (AC) is always shown in
red with square nodes
• Earned Value (EV) is always shown in
green with triangle nodes
51
Budget Management
Graphing Earned Value exercise
• Work together as a team to calculate the
task cost (task budget) for each task
• Record these values on the worksheet with
the total (BAC) calculated
• Warning: Wait to plot on the EVM graph as
a class – we will use the Cost Distribution
Report
52
1w
2w
3w
4w
5w
6w
7w
8w
9w
10w
$10K
$20K
$30K
$40K
$50K
$60K
53
Budget Management
Graphing Earned Value – week 1
• Task A started on time – 30% complete
• Task B started 2 days late – 30% complete
• Task C started 1 day late – 25% complete
• Tasks D, E, F, G, H, and J have not started
• Project Management is on-going
• Actual Costs reported for week 1 = $5000
54
1w
2w
3w
4w
5w
6w
7w
8w
9w
10w
$10K
$20K
$30K
$40K
$50K
$60K
55
1w
2w
3w
4w
5w
6w
7w
8w
9w
10w
$10K
$20K
$30K
$40K
$50K
$60K
Schedule
Variance
Cost
Variance
Budget Management
Show answer
Auto Play
Slide 1 / 55
SLIDE
Similar Resources on Wayground
53 questions
Dive into the trenches...
Lesson
•
10th Grade
49 questions
Causes of the Great Depression
Lesson
•
9th - 10th Grade
45 questions
X Graders 1st Term PSAJ Preperation
Lesson
•
10th Grade
50 questions
GCSE Unit 2. Book 2. Lesson 1
Lesson
•
10th Grade
52 questions
Momentum & Impuls
Lesson
•
10th Grade
49 questions
GED Review; Undefined Expressions
Lesson
•
10th Grade
51 questions
Western Migration
Lesson
•
10th Grade
52 questions
Algebra 2 Unit 3 Lesson 4
Lesson
•
10th Grade
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
14 questions
Boundaries & Healthy Relationships
Lesson
•
6th - 8th Grade
13 questions
SMS Cafeteria Expectations Quiz
Quiz
•
6th - 8th Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
12 questions
SMS Restroom Expectations Quiz
Quiz
•
6th - 8th Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
10 questions
Pi Day Trivia!
Quiz
•
6th - 9th Grade