Quiz Day 1 - RCC Training

Authored by Krisna Irawan

Professional Development

Professional Development

Used 6+ times

Quiz Day 1 - RCC Training
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Manakah diantara berikut ini yang merupakan 3 major activities proyek Revitalisasi RCC, kecuali...

Pengerukan Area New Construction Jetty

EPC TA (Reactor, Orifice Chamber, Boiler Modules dll)

Pembangunan Single Pipeline & Single Point Mooring

Pembangunan New Construction Jetty Akses Mobilisasi Heavy Equipment

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Salah satu objektif Revitalisasi RCC yang diharapkan adalah peningkatan performance RCC capacity. Berapa MBSD RCC Capacity di 95%?

88.1

78.8

100

83.1

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Timing eksekusi pelaksanaan TA Revitalisasi RCC yang rencananya dilaksanakan pada bulan Februari 2022 hingga Maret 2022 memiliki durasi waktu selama ... hari

30

60

45

90

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Berikut adalah lingkup pekerjaan Revitalisasi RCC untuk CO Boiler, kecuali...

Penggantian full module, soot blower dan burner

Penggantian existing platform & ladder

Penggantian Refractory

Chemical cleaning (Soda boiling)

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Equipment manakah diantara berikut ini yang dilakukan total replacement untuk Expansion Bellow Joint?

15-EBJ-104

15-EBJ-108

15-EBJ-108B

15-EBJ-103 A/B/C/D

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Salah satu metode cutting Regenerator yang digunakan dalam lingkup Revitalisasi yaitu kecuali...

Water jet cutting

Diamond wire cutting

Disc cutting

Grinder machine cutting

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Manakah berikut ini yang merupakan urutan tata waktu shutdown yang benar

Preparation & supporting - COF & Cooling down - Blind System - HC freeing - ECR - TA execution

Preparation & supporting - COF & Cooling down - HC freeing - Blind System - ECR - TA execution

Preparation & supporting - COF & Cooling down - ECR - HC freeing - Blind System - TA execution

Preparation & supporting - HC freeing - Blind System - ECR - TA execution - COF & Cooling down

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?