Contract account
Quiz
•
Other
•
University
•
Practice Problem
•
Hard
oluwafemi israel
Used 1+ times
FREE Resource
Enhance your content in a minute
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
Segun construction limited has signed a fixed contract price at N600 million for the construction of a big estate in Osun. Material costs delivered to site is N150 million, depreciation of plant and equipment used is N25 million, Labour cost amounted to N50 million, selling and promotion cost is N50 million and the estimated cost of completion amounted to N275 million. The estimated total profit of the contract is ___
N120 million
N109 million
N150 million
N100 million
2.
MULTIPLE CHOICE QUESTION
30 sec • 10 pts
__ is an advance payment by an employer to the contractee to enable the commencement of the contract work
Retention fee
Mobilization fee
Deferred costs
Over billing
3.
MULTIPLE CHOICE QUESTION
30 sec • 10 pts
The following are contract costs in line with IAS 11 except
Labour cost
Advertisement cost
Depreciation of plant and machinery used in the contract
Materials used in construction
4.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
Israel construction plc has signed a fixed price contract at N500 million
The following costs were incurred at the end of the first Accounting period
Wages N25 million, Direct expenses N10 million, Material used N50million, Depreciation of plant and equipment N15 million, cost of work not certified N15 million. The value of work certified amounted to N150 million. The notional profit is ___
N85 million
N70 million
N65 million
N100 million
5.
MULTIPLE CHOICE QUESTION
30 sec • 10 pts
__ is the accumulated certifiable cost relating to contract that is yet to be completed
Cost of work certified
Cost of work not certified
Contract work in progress
Retention fee
6.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
Segun construction limited has signed a fixed contract price at N600 million for the construction of a big estate in Osun. Material costs delivered to site is N150 million, depreciation of plant and equipment used is N25 million, Labour cost amounted to N50 million, selling and promotion cost is N50 million and the estimated cost of completion amounted to N275 million. The percentage of completion of the contract is ___
25%
35%
30%
45%
7.
MULTIPLE CHOICE QUESTION
1 min • 10 pts
Israel plc undertook a contract for building an estate for N200 million. The contract cost of N50 million was incurred up to 31st December, 2023 and expect further cost to complete the construction will be N170 million. How much should be recognized in the statement of profit or loss in 2023?
N50 million
N170 million
N20 million
N30 million
Answer explanation
Since it is probable that the total costs of N220 million (170+50) will exceed the total revenue. The expected loss of N20 million should be recognized as expenses
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
12 questions
CMA I - Intro & Cost Classification
Quiz
•
University
20 questions
Adopt Me! Quiz
Quiz
•
KG - University
10 questions
FunWithCSW
Quiz
•
University
13 questions
Lego
Quiz
•
KG - Professional Dev...
14 questions
Financial Sector (CSEC)
Quiz
•
5th Grade - University
20 questions
Retail PKK
Quiz
•
University
10 questions
Capital Budgeting and Capital Ratioining Quiz
Quiz
•
University
20 questions
Materials and Methods and Results Discussions Conclusion Rec
Quiz
•
University
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
15 questions
4:3 Model Multiplication of Decimals by Whole Numbers
Quiz
•
5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
The Best Christmas Pageant Ever Chapters 1 & 2
Quiz
•
4th Grade
12 questions
Unit 4 Review Day
Quiz
•
3rd Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
Discover more resources for Other
26 questions
Christmas Movie Trivia
Lesson
•
8th Grade - Professio...
7 questions
Different Types of Energy
Interactive video
•
4th Grade - University
20 questions
Slopes and Slope-Intercept Form
Quiz
•
8th Grade - University
7 questions
Force and Motion
Interactive video
•
4th Grade - University
7 questions
Biomolecules (Updated)
Interactive video
•
11th Grade - University
20 questions
Winter/Holiday Trivia
Quiz
•
KG - University
10 questions
WINTER WIN Time - ELA - 12/9/2025
Quiz
•
KG - University
7 questions
Human Impact on Resources
Interactive video
•
4th Grade - University