All-In-One Project+ PK0-005 Exam Guide - Chapter 05

All-In-One Project+ PK0-005 Exam Guide - Chapter 05

Professional Development

15 Qs

quiz-placeholder

Similar activities

Test Management

Test Management

Professional Development

20 Qs

Pre-Test Project Management [15/04/25]

Pre-Test Project Management [15/04/25]

Professional Development

20 Qs

PMP Assessment

PMP Assessment

Professional Development

20 Qs

Procurement 10 soal (Chapter 12)

Procurement 10 soal (Chapter 12)

Professional Development

10 Qs

Chapter 1-3

Chapter 1-3

Professional Development

18 Qs

SG20_Test_S6_CH7 Cost

SG20_Test_S6_CH7 Cost

Professional Development

10 Qs

Schedule Management Plan

Schedule Management Plan

Professional Development

15 Qs

Project Procurement Management 2022

Project Procurement Management 2022

Professional Development

20 Qs

All-In-One Project+ PK0-005 Exam Guide - Chapter 05

All-In-One Project+ PK0-005 Exam Guide - Chapter 05

Assessment

Quiz

Professional Development

Professional Development

Easy

Created by

Patrick Pepin

Used 1+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are the project manager for your organization.

Management has asked that you create a detailed cost estimate for a new solution they'd like you to implement.
What type of project estimating must account for every expense within a project before the work begins?

Bottom-up estimating

Top-down estimating

Zero-based budgeting

Parametric estimating

Answer explanation

Bottom-up estimating requires the project manager to account for all expenses within the project to arrive at a grand total for the project

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are the project manager of the JHN Project.

You have estimated the project will cost $129 for each unit installed.

There are 1,200 units on this project.


What type of estimate is this?

Bottom-up

Top-down

Analogous

Parametric

Answer explanation

This is an example of a parametric estimate.

The units will cost $129 each; this is the parameter.

As there are 1,200 units on the project, the estimate is calculated by multiplying the parameter of $129 by the total number of units needed, 1,200, for an estimate of $154,800

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Harry is the project manager for his organization.

Midori, his manager, has asked that Harry create a bottom-up cost estimate for a new project.

What is bottom-up cost estimating?

  1. Using last year's budget plus 20 percent to equal the current year's budget

Using this year's budget with a 20 percent plus or minus shift in the bottom line

The process of working toward a zero balance as the bottom line in a budget

  1. The process of creating a detailed estimate for each work package in a WBS

Answer explanation

  1. Bottom-up estimating is a process that requires the project manager to create a detailed estimate for each work package in the WBS.

  2. Every work package can be cost estimated, and it's the sum of the work packages cost estimates that help determine the bottom-up estimate.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are the project manager for your organization.

Your current project is similar to a project you finished recently for your organization.

You decide to base the current project cost estimate on the previous project.

What type of cost estimating are you using in this instance?

Analogous

Parametric

Definitive

  1. Rough order of magnitude

Answer explanation

This is an example of analogous estimating.

By creating an analogy berween the current project and the previous project, the project manager can predict curtent costs.

To use an analogous estimate, you must have accurate historical information.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should a project manager do to predict the total cost of an IT implementation project accurately?

List all of the expenses and add them up using best- and worst-case scenarios
for each expense

  1. List all of the expenses, including labor, and add them up using an average-case scenario for each expense.

Divide the project into phases and assign a dollar amount to each phase.

Divide the project into phases and estimate a dollar amount for each milestone within a phase.

Answer explanation

The project manager should not create one grand total for a project.

In order for the project manager to se a true picture of thae work, they should segment the project into phases and assign each phase a dollar amount based on the work to be completed within it.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a fully burdened workload?

It is when an employee has reached their maximum number of hours allotted for any given project

It is when a consultant has reached their maximum number of hours allotted for billable time for a project or task within the project.

It is the prediction of the number of hours required by staff to complete each phase of the project.

It is the record of the number of hours required by staff to complete each phase of the project.

Answer explanation

  1. A fully burdened workload is the prediction of the actual hours required by the team members to complete a given project.

  2. This process allows the project manager to predict the financial obligations corresponding to time and create a sense of urgency as to when each task must be completed.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why should an IT project manager use most likely, optimistic, and pessimistic scenarios when calculating the time required for a task?

Some staff members will take longer than other staff members to do the same type of work.

Each staff member will have a dollar amount assigned to the work hour.
The optimistic and pessimistic scenarios can predict which staff member is the most valuable

The most likely, optimistic, and pessimistic scenarios allow an IT project manager to predict the average time expense required to complete a task.

The most likely, optimistic, and pessimistic scenarios allow an IT project manager to predict the average amount of labor required to complete a task

Answer explanation

  1. Using the most likely, optimistic, and pessimistic scenarios allows a project manager to predict the average amount of time the team member requires to complete a task.

  2. The project manager uses this value to assign a dollar amount to the work to be completed.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?