1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project team is involved in a make-or-buy analysis and they had decided it is best to buy the products needed. They are evaluating the contract format they will use to minimize the risk. What type of contract will provide the seller with the most risk when entering into a contract?
Answer explanation
B is correct. The Fixed Price contract provides the seller with the most risk because the contract limits the amount that the buyer will pay for the project, meaning that the seller needs to have a detailed understanding of the project.
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The e-commerce system failed, preventing the fulfillment of customer orders. Although the new methodology is excellent, the risk response plan did not solve the problem. Which of the following steps would you take first?
Answer explanation
B is correct. This is a chicken and egg question in that you more than likely will do all the answers, but what comes first? Fixing the problem, then determining why the Risk Response Plan failed, and why the problem happened, then adjusting the Risk Response Plan would be the sequence for the other answers.
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The Project Manager is creating an estimate for building a warehouse. It is a similar project to what he builds about 3 times a year. He is using the rule of thumb of $100 per square foot to calculate the estimate. What type of estimate is this?
Answer explanation
A is correct. The parametric estimate involves using a parameter of an amount per unit. In this case, $100 per square foot is the parameter.
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Answer explanation
C is correct. INVEST acronym for writing effective user stories: Independent, Negotiable, Valuable, Estimatable, Small, and Testable.
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Answer explanation
C is correct. All except C are risk strategies
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Answer explanation
B is correct. Co-location means put all team members physically together in the same office in order to improve communication. Not always is possible, but it still being an excellent agile best practice.
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The Project Manager and team are involved in planning on a new technology project. They are in the process of breaking the work down into the smaller, more manageable pieces, ultimately leading to activities. What are they creating?
Answer explanation
A is correct. The work package is the smallest level that the WBS is broken into. The next level of Decomposition is to create Activity list
Create a free account and access millions of resources
Similar Resources on Wayground
20 questions
Risk management

Quiz
•
Professional Development
20 questions
All-in-one CAPM/PMP: Chapter 5

Quiz
•
Professional Development
10 questions
Quiz Lesson 3 - Topic F (Risks)

Quiz
•
Professional Development
15 questions
Kuis 1 Project Administration

Quiz
•
Professional Development
10 questions
EDGE Phase II GC - Recap Quiz

Quiz
•
Professional Development
10 questions
Project Finance (control and reporting)

Quiz
•
Professional Development
20 questions
Insurance Basics & Auto Insurance

Quiz
•
9th Grade - Professio...
13 questions
WildChina business terms

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
9/11 Experience and Reflections

Interactive video
•
10th - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
9 questions
Tips & Tricks

Lesson
•
6th - 8th Grade