PMI SH - Ensure Knowledge Transfer for Project Continuity

PMI SH - Ensure Knowledge Transfer for Project Continuity

1st - 3rd Grade

5 Qs

quiz-placeholder

Similar activities

Course 1- Foundations of Project Management

Course 1- Foundations of Project Management

1st - 3rd Grade

10 Qs

PM Quiz

PM Quiz

1st - 10th Grade

10 Qs

PMI SH - Plan and Manage Schedule

PMI SH - Plan and Manage Schedule

1st - 3rd Grade

8 Qs

PMI-ACP (10B)

PMI-ACP (10B)

1st Grade

10 Qs

Agile Knowledge Quiz

Agile Knowledge Quiz

KG - 3rd Grade

10 Qs

CEO Competency

CEO Competency

1st Grade

7 Qs

Chapt2

Chapt2

1st Grade

10 Qs

Chapt3

Chapt3

1st Grade

10 Qs

PMI SH - Ensure Knowledge Transfer for Project Continuity

PMI SH - Ensure Knowledge Transfer for Project Continuity

Assessment

Quiz

Professional Development

1st - 3rd Grade

Hard

Created by

sudiyuwono wowo

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager working in an agile environment realizes that some new team members are having difficulty understanding how more senior team members accomplished certain results on the project. 

What should the project manager do?

Arrange a review meeting with stakeholders.

Ensure team members focus on their tasks.

Assess the need for knowledge transfer.

Encourage and facilitate peer mentoring.

Answer explanation

Solution: D. Encourage and facilitate peer mentoring.

Encouraging and facilitating peer mentoring can be an effective way for new team members to learn from more experienced team members and understand how certain results were achieved on the project. This can also help promote collaboration and teamwork among team members. 
The other options are incorrect.
Organizing a stakeholder meeting or ensuring team members focus on their tasks does not directly address the root cause of the issue, which is the difficulty of new team members in understanding what older team members did. 
Assessing the need for knowledge transfer can help to avoid similar situations in the future, but peer mentoring is a more practical and effective solution.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager's team has identified the lack of proper knowledge transfer expectations in the project. Which of the obstacles does not apply in this situation?

A systematic review of the completed project

Personally handled failures and mistakes

Insufficient individual motivation to document the lessons learned

Sparse leadership involvement to promote knowledge transfer

Answer explanation

Solution: A. A systematic review of the completed project

Any review is a knowledge transfer exercise.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is involved in an e-commerce development project. The project has been completed successfully using the hybrid model and initiated operations handover. The project manager notices that the development team is relaxed and not spending time on the handover process, which is impacting application support.

How should the project manager handle this situation?

Confront the development team and demand their immediate attention to the handover process.

Meet with the development team to discuss the importance of the handover process and its impact on application support.

Delegate the responsibility of the handover process to another team member to ensure it gets done properly.

Disregard the issue and expect that the development team will address and resolve the issue on their own.

Answer explanation

Solution: B. Meet with the development team to discuss the importance of the handover process and its impact on application support.

Meeting with the development team to discuss the importance of the handover process and its impact on application support is the most effective and constructive approach in this situation. This will give the development team a chance to understand the issue and come up with a plan to address it. It allows for communication, understanding, and collaboration to find a solution to the problem. 

The other options are incorrect because they could potentially lead to negative outcomes and should be avoided.

Confronting the development team is not the best solution because it could make them defensive and less likely to cooperate. This can make it difficult for the project manager to effectively manage the team and get their cooperation in the future. It is important to understand why the development team is not spending time on the handover process. 

Delegating the responsibility of the handover process is not the best solution because it could create confusion and delay the process. It is important for the project manager to stay involved in the handover process to ensure that it is done correctly.

Disregarding the issue is not the best solution because it is likely to lead to problems down the road and is not an appropriate way to handle the situation. If the handover process is not done properly, it could impact the performance of the application and lead to customer dissatisfaction.

4.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

A project manager is assigned to a project that is already in progress because the original project manager left the organization unexpectedly. Unfortunately, the previous project manager did not adhere to the organization's knowledge transfer procedures prior to leaving the organization. What can the new project manager do to fill the knowledge gaps? (Choose 3)

Review the project documentation, including the project plan, requirements document, and risk register.

Proceed with the project as planned and engage in job shadowing activities. 

Meet with key stakeholders to understand their expectations and priorities.

Interview team members to learn about their areas of expertise and experience with the project.

E.Reach out to the previous project manager and request a comprehensive knowledge transfer.

Answer explanation

Solution: A, C, D. 

  • Review the project documentation, including the project plan, requirements document, and risk register.

  • Meet with key stakeholders to understand their expectations and priorities.

  • Interview team members to learn about their areas of expertise and experience with the project.

All three correct options are practical and effective ways for a new project manager to fill knowledge gaps when the previous project manager has not adhered to knowledge transfer procedures.

Reviewing project documentation can provide insights into the project's history, goals, scope, and potential risks. It helps the new project manager get up to speed on what has already been done and planned.

Meeting with key stakeholders is important for ensuring that the project stays on track and meets the needs of the people who are most invested in its success. 

Interviewing team members helps the new project manager gain a deeper understanding of the project from those actively involved. This can also help to build relationships with the team.

The other options are incorrect because they are less practical or effective.

Proceeding with the project as planned and engaging in job shadowing activities may not be sufficient to fill all knowledge gaps. It doesn't address the need for a comprehensive understanding of the project's history and documentation.

Reaching out to the previous project manager may not be feasible or productive. It's important to consider that the question states the previous manager left unexpectedly and did not adhere to knowledge transfer procedures. It may not be realistic to expect a comprehensive knowledge transfer from them. 

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

After consultation with executive stakeholders, it was decided that the project manager would replace a vendor while the project is in the execution phase. The new vendor simply has more domain knowledge and was not identified earlier, but is probably the right vendor candidate now.

Which of the following documents would contain the best information for the new vendor?

Request for Information (RFI)

Request for Quote (RFQ)

Request for Proposal (RFP)

Request for Contract (RFC)

Answer explanation

Solution: C. Request for Proposal (RFP)

The RFP contains all the functional and non functional requirements and the acceptance criteria. The other documents are brief from the scope point of view RFC and RFQ may have the RFP as a reference and RFI can focus on a specific aspect only.

An RFP is used when there is a problem in the project and the solution is not easy to determine. This is the most formal of the “request for” documents and has strict procurement rules for content, timeline, and seller responses.