A project manager is leading a construction project and the initial requirements have been fully defined. Midway through the project, a stakeholder requests a significant change. What should the project manager do first?
Waterfall Mindset1(AKF)

Quiz
•
Professional Development
•
Professional Development
•
Medium
Afghanistan Center
Used 18+ times
FREE Resource
12 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Implement the change immediately to meet stakeholder needs.
Perform a feasibility study to determine the impact of the change.
Reject the change as it is outside the scope defined in the planning phase.
Submit the change request to the change control board (CCB) for review.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the execution phase of a Waterfall project, the project manager realizes that one of the deliverables is taking longer to complete than initially planned. What is the most appropriate action?
Skip some quality checks to catch up on the schedule.
Reassign tasks to team members without consulting them.
Continue with the current plan as deviations are expected.
Update the project schedule and inform the stakeholders.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a Waterfall project, the design phase is complete, and the team is moving into the development phase. A team member suggests a minor change to improve the design. What should the project manager do?
Approve the change to improve the project outcome.
Reject the change as the design phase is already completed.
Implement the change and document it later.
Submit a change request and assess the impact.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is overseeing a software development project using the Waterfall methodology. The project is currently in the testing phase, and a critical bug is discovered. What should the project manager do?
Halt the testing phase and return to the development phase.
Log the bug and proceed with testing until the end of the phase.
Immediately implement a fix and continue testing.
Escalate the issue to the change control board.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A stakeholder wants to add a new feature to the product during the execution phase of a Waterfall project. How should the project manager respond?
Implement the feature to ensure stakeholder satisfaction.
Explain that changes are not allowed after the planning phase.
Submit a change request for impact analysis and review.
Integrate the feature into the project plan without formal approval.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a review meeting, a stakeholder expresses dissatisfaction with the current progress of the project. The project manager realizes that the issue stems from unclear requirements. What should the project manager do next?
Adjust the project deliverables to meet the stakeholder's expectations.
Review the original requirements document and initiate a change request if necessary.
Proceed with the project as planned to avoid delays.
Request additional funding to accommodate the changes.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a Waterfall project, the project manager notices that the team is consistently behind schedule. What is the most effective course of action?
Reduce the scope of the project to meet the deadlines.
Increase the working hours for the team members.
Conduct a detailed review of the project plan and adjust the timeline.
Move resources from other projects to speed up completion.
Create a free account and access millions of resources
Similar Resources on Quizizz
7 questions
Schedule Management Terms - Assignment

Quiz
•
Professional Development
15 questions
LO4 Project Conflict & Negotiations

Quiz
•
Professional Development
10 questions
Practice Exam 2 Part 3

Quiz
•
Professional Development
10 questions
Project Management

Quiz
•
Professional Development
10 questions
Project Integration Management Quiz

Quiz
•
Professional Development
7 questions
Waterfall Vs Agile Project Management

Quiz
•
Professional Development
15 questions
All-In-One Project+ PK0-005 Exam Guide - Chapter 05

Quiz
•
Professional Development
10 questions
Atoha PMP lesson 14

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade