IB Business Management MCQ QuizIB_Business_Management_Gantt char

IB Business Management MCQ QuizIB_Business_Management_Gantt char

12th Grade

10 Qs

quiz-placeholder

Similar activities

Fundamentals of Management

Fundamentals of Management

12th Grade

10 Qs

PMI Vocab Review 1 Fill in Blanks

PMI Vocab Review 1 Fill in Blanks

9th - 12th Grade

10 Qs

Checkpoint in Planning

Checkpoint in Planning

12th Grade

11 Qs

Nature and Concept of Managemet

Nature and Concept of Managemet

11th - 12th Grade

15 Qs

Quality Management Challenge Quiz

Quality Management Challenge Quiz

12th Grade

15 Qs

GANTT

GANTT

8th - 12th Grade

10 Qs

IB Business Management - BMT - Gantt Charts Quiz

IB Business Management - BMT - Gantt Charts Quiz

9th Grade - University

13 Qs

Management Theories

Management Theories

7th Grade - University

10 Qs

IB Business Management MCQ QuizIB_Business_Management_Gantt char

IB Business Management MCQ QuizIB_Business_Management_Gantt char

Assessment

Quiz

Business

12th Grade

Hard

Created by

Daniel Roberts

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main purpose of a Gantt chart?

A planning tool that visually depicts the sequencing and scheduling of activities in a project

A summary of weighted driving and restraining forces to support a decision

An analysis of the costs and revenues of a firm to establish the number of products that must be sold

The categorization of the current strengths and weaknesses of a firm

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Identify the direction of the bars in a Gantt chart.

Circular

Horizontal

Lateral

Vertical

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Identify a limitation of using a Gantt chart.

Planning of project tasks to meet a deadline

Recognition of milestones

Relationship between the duration and the importance of a task

Visual identification of a critical path

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Identify the most appropriate first step when preparing a Gantt chart.

Determine the duration of each activity in a project

Enter activities into the relevant project management software

Identify the activities of the project

Track progress of each activity in the project

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Identify the business activity least likely to require a Gantt chart.

Analysis of current economic conditions

Construction of a new research facility

Implementation of a rebranding strategy

Relocation of the administration team

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Identify the least likely use of a Gantt chart.

Monitor project progress

Prepare and manage a comprehensive project

Sequence tasks to manage logistics

To evaluate an investment decision

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Identify the critical path from the sample Gantt chart.

A, B, D, E, F, H, J

B, D, F, G, I, J

B, E, F, G, H, J

C, D, F, G, I, J

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?