wayground logo

Free Printable Worksheets

NEW

Font size

S
M
L
XL
Worksheets

Monitoring & Controlling - PM Quiz

Total questions: 11

Worksheet time: 6mins

Name
Class
Date
1.

The difference between the value of work completed to a point in time and the actual costs to the same point in time.

a)

Cost Baseline

b)

Variance at Completion

c)

Schedule Variance

d)

Cost Variance

2.

To Complete Performance Index

a)

Addressing root cause of the most frequent problems makes the greatest impact on quality.

b)

To stay within budget, what rate do we need to meet for the remaining work?

c)

Cost of completing the remaining authorized work

d)

A measure of schedule efficiency expressed as the ratio of earned value to planned value

3.

Which of the following is not a function of integrated change control?

a)

Reviewing, approving, or denying all recommended corrective and preventive actions

b)

Formal acceptance documentation

c)

Documenting the complete impact of requested changes

d)

Coordinating changes across the entire project

4.

Nic is working on an IT implementation at a remote site. His team has 10 remote workers. They are testing implementation daily. What shows a graphic display of the interaction of process variables, used to determine if the process variables are within acceptable limits?

a)

Statistical samples

b)

Control charts

c)

Run charts

d)

Flowcharts

5.

The __________ is an approved plan for the project work to which project execution is compared and deviations are measured for management control.

a)

Performance report

b)

Quality control measurement

c)

Forecast

d)

Performance measurement baseline

6.

What is the process of monitoring the status of the project and product scope and managing changes to the scope baseline?

a)

Control scope

b)

Variance analysis

c)

Configuration management system

d)

Change control system

7.

___________ is the process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes.

a)

Quality checklists

b)

Quality metrics

c)

Perform quality control

d)

Quality control measures

8.

Lauren is a new Project Manager for a statewide initiative. What is the process of tracking, reviewing, and regulating the progress to meet the performance

objectives defined in the project management plan?

a)

Work performance information

b)

Project management methodology

c)

Earned value technique

d)

Monitor and control project work

9.

Alan is managing the project finances. This item compares the amount of the contingency reserves remaining to the amount of risk remaining at

any time in the project.

a)

Reserve analysis

b)

Risk reassessment

c)

Risk audits

d)

Risk review

10.

This equals the revised estimate for the work remaining, as determined by the performing organization.

a)

Estimate to completion (ETC) based on atypical variances

b)

Estimate to completion (ETC) based on typical variances

c)

Estimate to completion (ETC) based on planned value

d)

Estimate to completion (ETC) based on new estimate

11.

Earned value (EV) minus planned value (PV) equals

a)

Cost variance (CV)

b)

Schedule variance (SV)

c)

Cost performance index (CPI)

d)

Schedule performance index (SPI)