Total questions: 40

Worksheet time: 40mins

Name
Class
Date
1.

How do Work in Progress (WIP) Limits relate to self-organization?

(choose the best two answers)

a)

As part of self-organization Scrum Teams figure cut their own WIP Limits.

b)

WIP Limits inhibit self-organization since they limit the team's autonomy to pull work.

c)

A Scrum Master defines a WIP Limit to help the Scrum Team self-organize.

d)

WIP Limits provide a boundary/container in which the Scrum Team self-organizes.

2.

Which of the following are flow metrics needed when doing Scrum with Kanban?

(choose the best four answers)

a)

Work in Progress (WIP)

b)

Work item Age

c)

Cycle Time

d)

Lead Time

e)

Throughput

3.

The definition of "Done" still applies if policies are explicitly-stated at each column of your workflow.

a)

True

b)

False

4.

What's the best use for the Work Item Aging metric?

(choose the best two answers)

a)

To influence the team's SLE.

b)

To help the team inspect and adapt their Sprint in the Daily Scrum.

c)

As a leading indicator to the length of feedback loop that Work Item.

d)

As an indicator of the Work Item size.

e)

To help the team inspect and adapt their process and definition of Workflow in their Retrospective.

5.

In which of these situations should the Scrum Team adjust their Work in Progress (WIP) Limits?

(choose the best answer)

a)

When they have extra capacity during the Sprint and want to start some new work items from the Sprint Backlog.

b)

When there is unplanned urgent work that emerges during the Sprint.

c)

When they want to improve their cycle time, flow and focus.

d)

When they see that the average story size they are working on is growing.

6.

What are possible benefits of supplementing Scrum with Kanban practices?

(choose the best three answers)

a)

May result in greater collaboration within Development Team.

b)

Scrum Teams no longer need the Sprint time box.

c)

Allows teams to release multiple times a Sprint.

d)

May help to discover areas of variability within your Sprint.

e)

May reduce an average cycle time.

7.

What might be considered during the Sprint Retrospective once a team decides to supplement their Scrum with Kanban?

(choose the best answer)

a)

Workflow.

b)

Current policies.

c)

WIP Limit.

d)

Metrics and charts such as cumulative flow, scatterplot and work item aging.

e)

All of the answers.

8.

What element of the Scrum framework or supporting practices is a from of the Work in Progress (WIP) Limit?

(choose the best answer)

a)

The Sprint Backlog.

b)

There is no such element in the Scrum framework.

c)

Definition of "Done".

d)

Burndown chart.

e)

Sprint Goal.

9.

Which of following are Kanban practices for Scrum?

(choose the best answer)

a)

Visualizing flow, limiting WIP, actively manage the Work in Progress (WIP), inspecting & adapting the workflow.

b)

Kaizen, remove delays, visualize policies, pull system.

c)

Small batches, limit WIP, eliminate waste, Kaizen.

d)

T-shirt size estimation, service level expectations, limit WIP.

e)

Class of service, cost of delay, visualize the workflow, limit WIP, manage flow.

10.

Which of these statements are true about Kanban and the Scrum theory of empiricism?

(choose the best two answers)

a)

The Kanban board provides Scrum Teams with transparency that helps them inspect and adapt their process.

b)

Kanban metrics are used in the Sprint Review to allow the Product Owner to inspect the Throughput and adapt the Development Team's Cycle Time.

c)

Kanban helps Scrum Teams deal with simple and complicated work where empiricism is not necessary.

d)

Kanban helps Scrum Teams achieve faster, healthier flow. That brings more rapid transparency about, the product, enabling a more effective inspection and adaptation loop.

11.

What is Kanban?

(choose the best answer)

a)

A strategy for optimizing the flow of stakeholder value through a process that uses a visual, Work in Progress (WIP) limted pull system.

b)

None of these answers.

c)

A set of practices that are additive to the Scrum framework.

d)

A methodology aimed at visualizing your workflow for effectiveness and enhance productivity within the team.

12.

If you reduce your batch size, your overall efficiency will always increase.

a)

True

b)

False

13.

Scrum Teams using Kanban can start to increase predictability by:

(choose the best answer)

a)

Visualizing the workflow using a Kanban board.

b)

Improving transparency by having a CFD, Control Chart and Aging chart.

c)

Inspecting and adapting the Product Backlog during the Sprint Review.

d)

Reducing the amount of work in progress by introducing Work in Progress (WIP) Limits.

14.

Which of the following is NOT an essential component to initially achieving flow?

(choose the best answer)

a)

Ensuring the product backlog is refined frequently.

b)

Limiting Work in Progress (WIP).

c)

Visualizing your workflow.

d)

Actively managing WIP.

e)

Inspecting & adapting your workflow.

15.

What is a probabilistic forecast intended to communicate?

(choose the best answer)

a)

The best way to predict the future performance of a team.

b)

A guarantee of when a certain amount of scope will be complete.

c)

A forecast based on past performance that can help discussions about the likelihood of achieving a certain goal in a given time frame.

16.

What are the two things that constitute a Kanban board?

(choose the best two answers)

a)

Work in Progress (WIP) Limits.

b)

Visualization of your workflow.

c)

Class of service.

d)

Swim lanes per PBI type.

17.

Which of the following metrics are likely to be reviewed during flow-based Daily Scrum?

(choose the best two answers)

a)

Throughput.

b)

Cycle Time.

c)

Process control chart and Scrum Team's 85th percentile.

d)

Work in Progress (WIP).

e)

Work item age.

18.

What is the flow metric used to forecast how many items will be done for a date?

(choose the best answer)

a)

Work in Progress (WIP).

b)

Load time.

c)

Throughput.

d)

Cycle time.

19.

Within the same Kanban system, Work in Progress (WIP) is NOT a leading indicator for:

(choose the best answer)

a)

Story points delivered.

b)

Cycle time.

c)

Throughput.

d)

Number of Product Backlog items finished in a Sprint.

20.

Upon which of the five Scrum Values does Professional Scrum with Kanban build?

(choose the best three answers)

a)

Transparency.

b)

Openness.

c)

Focus.

d)

Professionalism.

e)

Courage.

21.

The Scrum Framework contains elements that can be treated as explicit policies.

a)

True

b)

False

22.

Your Scrum Team's cycle time is currently 8 days or less with 85% confidence. The learn has set the Service Level Expectation (SLE) accondingly. If an item in progress has just aged past your dataset's 50th percentile, what can we say about the chance it will fail to meet the team's 8-day SLE?

(choose the best answer)

a)

We cannot predict with any level of confidence what will happen with the work item at this point.

b)

There is now a higher chance to meet the team's SLE.

c)

Nothing changed. We're still 85% confident the card will meet the SLE.

d)

There is now a lower chance it will meet the team's SLE.

23.

What is the best chart (analytic) to determine "When will it be finished?" for a single item in the Product Backlog?

(choose the best answer)

a)

Throughput run chart.

b)

WIP Aging chart.

c)

Cumulative Flow diagram (CFD).

d)

Cycle Time scattemplot.

24.

Which of these statements about Sprints and Kanban is NOT correct?

(choose the best answer)

a)

The Sprint is an example of an explicit policy for how a team is working.

b)

The Sprint is an example of limiting Work in Progress (WIP).

c)

The Sprint is an example of a cadence.

d)

A Scrum Team will eventually stop using Sprints if they correctly implement Kanban.

25.

What does it mean when a development learn chooses to communicate an 85% 5-day service level expectation (SLE)?

(choose the best answer)

a)

In the last Sprint the learn has been able to complete 85% of product backlog items within 5 days of starting work on the item.

b)

The team promises to have 85% of all product backlog items done within 5 days.

c)

The learn expects they will complete a work item 5 days of when they start working on it 85% of the time.

d)

The team can get any critical system backup within 5 days.

26.

Which of the following are lagging indicator metrics?

(choose the best three answers)

a)

Work Item Aging.

b)

Velocity.

c)

Work in Progress.

d)

Cycle Time.

e)

Throughput.

27.

Limiting Work in Progress (WIP) will likely reduce the amount of collaboration in the Scrum Team.

a)

True

b)

False

28.

For a specific Sprint Backlog item that has been "started", what is the best chart (analytic) to determine when it will be "finished"?

a)

Control chart.

b)

Work Item Aging Chart.

c)

Throughput Chart.

d)

Cumulative Flow diagram (CFD)

29.

Which of these are typically included in the definition of "Workflow" policies?

(choose the best four answers)

a)

WIP Limits.

b)

Work Item types.

c)

Burndown chart.

d)

Visualization policies.

e)

Pull/prioritization policies.

30.

A forescast is a calculation about the future completion of an items that includes two things. What are those two things?

(choose the best two answers)

a)

A commitment.

b)

A range of elapsed days.

c)

A velocity.

d)

A probability.

31.

What is true about the Sprint Goal if the Development Team reserved capacity for unplanned work during an upcoming sprint?

(choose the best answer)

a)

The Development Team should never reserve any capacity for unplanned work. It is inefficient if a Development Team's forecast does not take into account all of their capacity.

b)

The Sprint Goal becomes more important. It can help the Development Team maintain their focus as new Product Backlog items are brought into the Sprint Backlog.

c)

The Sprint Goal no longer helps the Development Team. They do not know what they will be working on.

32.

Little's Law states that:

(choose the best answer)

a)

Average Throughput = Average Cycle Time / Average Work in Progress.

b)

Average Cycle Time = Average Work in Progress / Average Throughput.

c)

Average Throughput = Average Cycle Time * Average Work in Progress.

d)

Average Work in Progress = Average Cycle Time / Average Throughput.

33.

Which statements best describe the purpose of a Scrum Team's definition of "Workflow"?

(choose the best three answers)

a)

It provides a common understanding of when the work is considered to be started and finished.

b)

It creates transparency over the Work in Progress (WIP) limiting rules.

c)

It defines how value flows through the system.

d)

It makes handoff policies explicit by defining clear quality gates between the development stages.

e)

It is used as a checklist of all the states that every work item should go through before it is considered to be "Done".

34.

For teams practicing Professional Scrum with Kanban, what are the most appropriate metrics to inspect?

(choose the best answer)

a)

Control Chart, CFD and Aging Chart.

b)

Story points and historical velocity.

c)

User stories t-shirt size.

d)

All of the answers.

e)

None of these are Kanban for Scrum Teams metrics.

35.

When can a Work in Progress (WIP) Limit change?

(choose the best answer)

a)

At any time.

b)

When Product Owner decides to change it.

c)

It never changes.

d)

Only during the Sprint Retrospective.

e)

Only during Sprint Planning.

36.

What is the potential benefic of limiting Work in Progress (WIP)?

(choose the best answer)

a)

Shorter feedback cycles.

b)

More sustainable pace of work.

c)

Faster realization of value.

d)

Improved collaboration.

e)

All of the answers.

37.

When using Kanban in a Scrum environment, some resistance may be found to introducing Work in Progress (WIP) Limits. What is an alternative to introducing WIP Limits in Kanban?

(choose the best answer)

a)

None, Professional Scrum with Kanban cannot be used without explicit WIP Limits.

b)

Building a strong team identity using Squads and tribes.

c)

Using Kanban boards that improve visualization and enhance communication.

d)

Conducing Daily Stand Up meetings that control not having too much work.

38.

Who must change the Work in Progress (WIP) Limits in the definition of "Workflow" when urgent work emerges from the Sprint?

(choose the best answer)

a)

The Product Owner.

b)

No one. WIP Limits cannot be modified during a Sprint.

c)

The Scrum Master.

d)

The Development Team.

e)

No one. Urgent work is not a reason to change WIP Limits.

39.

What might a Scrum team visualize with Kanban?

(choose the best three answers)

a)

The Sprint Retrospective.

b)

The Product Backlog.

c)

The definition of "Done".

d)

The Sprint Backlog.

40.

Which of the following are leading indicator metrics?

(choose the best two answers)

a)

Cycle Time.

b)

Service Level Expectation.

c)

Work in Progress.

d)

Work Item Aging.

e)

Monte Carlo.