Project Management Quiz

Total questions: 60

Worksheet time: 38mins

Name
Class
Date
1.

When do stakeholders have the most influence over the project’s product and costs?

a)

During the writing of the project charter

b)

During the construction of the work breakdown structure

c)

During scope definition

d)

At the beginning of the project

2.

A construction project has just completed the initiation processes. Planning is ready to begin. Which have they completed and are they starting?

a)

The project management plan and project execution

b)

The project execution and monitoring and controlling

c)

The project charter and project planning

d)

The project charter and project execution

3.

Which of the following is a 'hands-off' leadership style?

a)

Laissez-faire

b)

Servant

c)

Transactional

d)

Charismatic

4.

What is the main role of the Functional Manager?

a)

Defines business processes

b)

Manages the Project Managers

c)

Controls the resources

d)

Manages the project when there is no PMO available

5.

Who typically pays for the project and owns the work of the project when complete?

a)

Project Manager

b)

Functional Manager

c)

Customer

d)

Sponsor

6.

Which is an advantage of a functional organization?

a)

Business unit competency

b)

Resources have a place to go when the project starts

c)

Optimization for a single focus on a project

d)

Having to obtain approval from project management

7.

In a project-oriented organization, who controls the resources?

a)

Senior Management

b)

Functional Manager

c)

Project Leader

d)

Project Manager

8.

Which is an advantage of a project-oriented organization?

a)

Having to get approval from the Function Manager

b)

Resources have a place to go when the project starts

c)

Optimization for a single focus on a project

d)

Resources have a place to go when the project ends

9.

What is the main deliverable from the planning process group?

a)

Project management plan

b)

A signed contract

c)

Project charter

d)

Work results

10.

Which is NOT a component of the PMI Talent Triangle?

a)

Technical project management

b)

Informational project management

c)

Leadership

d)

Strategic and business management

11.

What does the Functional Manager focus on when discussing post-project costs and usage?

a)

Project Life Cycle

b)

Project Management Life Cycle

c)

Program Management Life Cycle

d)

Product Life Cycle

12.

What is a Project Manager’s primary stance on change?

a)

To control unnecessary change

b)

Expedite all change requests to the Change Control Board

c)

Delay changes so the project can be completed

d)

Protect the Change Control Board from excessive changes

13.

Weak matrices resemble which type of organization?

a)

Functional

b)

Project-oriented

c)

Strong Matrix

d)

Balance Matrix

14.

In a matrix organization, communications are typically:

a)

Simple

b)

Open and honest

c)

Complex

d)

Difficult to automate

15.

Which is NOT included in the benefits management plan?

a)

Requests for change

b)

Target benefits

c)

Benefits owner

d)

Risks

16.

Which statement about the project environment is FALSE?

a)

Projects are planned in social/economic contexts

b)

Projects may have unintended impacts

c)

The team rarely considers political contexts

d)

Projects may have intended impacts

17.

Which statement about projects vs. operations is FALSE?

a)

Projects are rarely used for strategic plans

b)

Both are constrained by resources

c)

Operations are ongoing; projects are temporary

d)

Both are planned/executed

18.

What should the PM do if the WBS is excluded?

a)

Update schedule/budget

b)

Begin execution

c)

Discuss ramifications

d)

Notify the team

19.

Which organization audits projects for improvement?

a)

Weak matrix

b)

Project Management Office (PMO)

c)

Project-oriented

d)

Balanced matrix

20.

Market conditions and time limitations are examples of:

a)

Constraints

b)

Assumptions

c)

Risk planning

d)

Economic consumption

21.

Stakeholder management does NOT include:

a)

Create conflicts among stakeholders

b)

Determine requirements

c)

Manage influence

d)

Identify stakeholders

22.

In which structure does the PM have the highest authority?

a)

Strong matrix

b)

Weak matrix

c)

Project-oriented

d)

Functional

23.

A project coordinator is typically found in:

a)

Strong matrix

b)

Weak matrix

c)

Project-oriented

d)

Functional

24.

How are Process Groups linked?

a)

The WBS

b)

Objectives becoming action plans

c)

Outputs becoming inputs

d)

No significant links

25.

What is needed to start the scope management plan?

a)

Project Charter

b)

WBS

c)

Scope control system

d)

Change requests

26.

Key stakeholders play a critical role in the. The key stakeholders’ engagement and

involvement with projects vary from organization to organization and from project to project. Which of the following gives

the maximum level of engagement in a project?

a)


From project evaluation

through realizing business

benefits.

b)

From requirements

through delivery.

c)

From planning through

executing.

d)

From initiation through

closing.

27.

Rules of Schedule Performance Measurement Include

a)

SV Schedule Performance and SVI

b)

Free Float

c)

Fast Tracking

d)

Schedule Deliverable

28.

Is a schedule compression technique that applies the least cost for the greatest compression

a)

LEast Effort

b)

Crashing

c)

Free Float

d)

Schedule Variance

29.

Which 3 processes should the business analyst perform to improve communication with stakeholders and ensure that stakeholders commit to the project?

a)

determine the approach to communication and the participation of the stakeholders

b)

identify the stakeholders

c)

manage the commitment and communication of the stakeholders

d)

study the alignment of the project with the strategic plan

e)

manage project quality

30.

Cost Variance Formula CV

a)

EV+ BAC- CV

b)

CV=EV-AC

c)

In this example SV is less than CV

d)

CV-AC= SV

31.

CV Cost Variance compares (AC) Actual Costs with "Actual Work Done known" as (a)  

32.

CV is less than Zero- which are true

a)

The Project is slowing down

b)

CV=AC-EV CV = 7500-8500= (- 500)

c)

The Project is on Budget

d)

The Project is over budget

33.

From the Diagram on the Left Can you give me the Critical Path Answer based on Activity 1, 2, 3, 4 Give in numbers only. Separated by commas .

(a)  

34.

WBS Numbering System shows that work packages are decomposed after ______ in a project?

a)

Charter

b)

the PM declares them

c)

After Project Deliverables

d)

Control Account Planner votes

35.

Looking at the Critical Path on the Left Diagram what is the max Float ?

a)

26

b)

8

c)

21

d)

7

36.

Forward Pass is calculated in a network diagram with what Data

a)

LS

b)

Critical Path

c)

Early Start Early Finish times

d)

Late Start Late Finish

37.

For the diagram on the left EF= what formula? ES=What formula? Choose 2 that are true.

a)

EF= ES*CPM

b)

EF=ES+ Duration -1

c)

ES=Highest (Previous) +1

d)

EF=ES+CPM

38.

What Model is this for Quality Control

a)

Pareto

b)

Monte Carlo

c)

Deming

d)

QA Model with Burn Up Chart

39.

Estimating Costs for a Project includes- choose 3

a)

Pricing Estimates

b)

Estimates labor cost

c)

Includes COQ Cost of Quality

d)

Time and Resources

40.

This is an example of what Variance?

(a)  

41.

(BAC) Budget at Completion-- Choose all that are true 3

a)

Is a Baseline

b)

Sum of all PVs

c)

Done at the Final Phase of a project

d)

BAC is 1600 based on chart diagram example

42.

What is CPI ? Choose 3--**** Note projects less than 100% are over budget

a)

CPI is > than 100%

b)

83%

c)

CPI= BAC/EAC

d)

CPI is < than 100%

43.

At 100% schedule progress, PV = BAC = 100, If the Schedule Performance Index is 1 then what is true below? Choose 3

a)

SPI=EV/PV

b)

SPI= 100

c)

EV=100

d)

EV not Equal to PV

44.

This is what? Best Answer?

a)

This is and example of fishing for quality at Toyota USA

b)

Effects are engineered for the solutiosn

c)

this diagram is a cause and effect diagram

45.

What determines Schedule Progress in a Project??????????Choose 2

a)

CPI=EV/AC Cost Performance Index

b)

Variance Reports

c)

SPI=PV/EV

d)

Schedule Performance Index

46.

What is true about (EAC) Estimated Cost at Completion. Choose 2 correct answers.

a)

EAC=AC+(BAC-EV)

b)

EAC=AC+ETC

c)

EAC=BAC/CPI

d)

EAC=AC+(BAC-EV) / (CPI x SPI)

47.

From the Agile Project Diagram on the left on Day 3 of a Sprint what is true?

a)

Deliverables are created on day 3

b)

Team takes product data from Backlog

c)

Deliverables are from Release Schedule

d)

No Value is generated

48.

An interactive technique where future planning is the highest priority

a)

Rolling Wave

b)

sine wave

c)

CPM

d)

SPI

49.

You are a PM on a Amazon SSD Project that was planned for Critical Path completion in 120 days. Jeff Bezos wanted an earlier delivery in 100 days as Prime Season is approaching. Calculate Crashing Activity A B C D by X Days, would give the compression to make the former CEO happy.

(a)  

50.

You need to shorten your project by 10 days. Only 2 activities can be crashed: Choose 4 that are true from the data adjacent as a PM Crashing to meet a Sponsor/Customer demand.


a)

days that are a max value

b)

Crash X by 5 days and Crash Y by 5 days

c)

Crash X by 10 days

d)

TC

e)
  1. Cheaper activities Here, both are needed, but X is cheaper per day.

51.

This diagram is an example of ? Choose the best 2 . Disregard the Data@

a)

Monte Carlos Diagram

b)

Precedence Diagram

c)

Flowing Back Pass

d)

AON

52.

Develop a Schedule Methods include: Choose 3

a)

Agile or MS Project

b)

Schedule Compression Fast Tracking

c)

PMIS Systems Project Management Information Systems

d)

Crashing

53.

What is the Critical Chain in this project? @@Hint to optimize scheduling-longest resource constrained path

a)

A → C → D

b)

A → B → D and A → C → D (Parallel chains)

c)

A → B → D

d)

A → B → C →D

54.

How does CCM differ from traditional Critical Path Method (CPM)?

a)

.
CCM only works in Agile.

b)


CCM removes all float.

c)

CCM ignores dependencies.

d)


CCM adds buffers (Project Buffer, Feeding Buffer).

55.

What is EAC Forecast? choose 3 .*** Note. CPI = EV / AC ( Cost efficiency (1 = on budget).) EV% Complete × BAC Measures work actually done.

a)

Estimating cost of completing all of the work expressed as the sum of the actual cost to date

b)

EAC=CPI+BAV/EV

c)

EAC= AC+BAC-EV

d)

EAC=BAC/CPI

56.

You are managing a construction project with a Budget at Completion (BAC) of $500,000. After 6 months, the following data is reported: Based on the current Cost Performance Index (CPI), what is the Estimate at Completion (EAC) if the project continues at the same cost efficiency? CHOOSE 2

a)

450,000$

b)

Ea. 1$ spent,only1spent,only0.91 of

c)

FORMULA

d)

520,000$

57.

What factors are these for a PM? Choose 1

a)

Day 1 Amazon Factors

b)

Enterprise Environmental Factors

c)

Fear

d)

OPAs

58.

OPAs include all the following Except?

a)
  • Processes/procedures (e.g., change control guidelines)

  • Lessons learned repositories

b)
  • Historical data (e.g., past project files)

c)
  • Templates (e.g., WBS, risk registers)

d)

Other Projects Accounting

59.

If the project had unclear requirements, which contract type would shift risk to the buyer? Choose 2 answers.

a)

FFIF

b)

CPFF (Cost-Plus Fixed Fee)

c)

T&M (Time and Materials).

d)

FFP

60.

You are a PM on a R&D project for Space X. Elon calls you and wants to know are the knowns for NASA client to remove a Sat-3 orbiting earth-as its crashing. ? Choose 2 best for Space X

a)

CPFF

b)

FFIF

c)

NASA the buyer bears cost

d)

EPA